Data center water treatment is two jobs, not one. A liquid-cooled hall has a facility water system on the building side and a closed technical cooling system on the IT side, and the two are separated by a coolant distribution unit. The building side is a conventional industrial water problem: makeup treatment, tower or chiller chemistry, filtration and blowdown. The closed loop is a high-purity water problem, with tight limits on conductivity, chlorides, sulfates and particulate, because that water passes through cold plate channels narrower than a pencil lead. Paul Industries builds, cleans and treats both sides.

Data center water treatment starts with two separate water loops

On the building side is the facility water system: condenser water to a cooling tower, chilled water from a chiller plant, or a dry cooler circuit. On the IT side is the technical cooling system, the closed secondary loop feeding rear-door heat exchangers, cold plates or immersion tanks. A coolant distribution unit sits between them, moving heat across a plate heat exchanger while keeping the two volumes of water physically separate.

That separation is why the loops are treated differently. The facility side is open to the atmosphere in any evaporative design, so it concentrates minerals, collects airborne dirt and grows biology, and is managed with inhibitor, biocide and controlled blowdown. The closed loop never evaporates, should never see air once filled, and holds a small fixed volume sitting against the same metals for years. Treating it like building chilled water is the most common and most expensive mistake in liquid cooling data center work.

Water quality in the closed technical cooling loop

ASHRAE Technical Committee 9.9 publishes the reference the industry works from. Its facility water supply classes, designated W17, W27, W32, W40, W45 and W+ after the upper supply temperature in degrees Celsius (earlier editions called them W1 to W5), describe temperature bands, from chilled water up to warm water operation needing no mechanical chiller. They are temperature classes, not quality classes; water quality for the technical cooling loop is addressed separately, and the recurring parameters are pH held in a narrow band, low conductivity, limits on chlorides and sulfates, a limit on total particulate, and control of bacteria.

The reasons are mechanical. Chlorides and sulfates pit stainless steel and attack copper. Conductivity is the practical proxy for dissolved ionic load and for galvanic activity between dissimilar metals, and a liquid cooled rack commonly puts copper cold plates, stainless distribution, elastomer hose and sometimes aluminum in one circuit, so the inhibitor has to protect every metal present, not the dominant one. Galvanized pipe does not belong anywhere in the loop, because the zinc sheds. Brazing or soldering flux left inside a line becomes a corrosive deposit and a particulate source. Particulate is the quiet failure mode: the cold plate manufacturer states a filtration micron rating for a reason, and that number binds the piping contractor.

Cleaning, flushing and passivation before IT equipment is connected

A newly fabricated loop is dirty. It holds weld scale and heat tint, cutting oil and swarf, thread sealant, flux residue at any brazed joint, construction grit, and preservative oils from pumps and valves. Leave it in and the first thing the cold plates see is particulate.

The sequence we run on a new loop is pressure test, degrease, high velocity flush on temporary pumps and strainers, chemical cleaning or pickling where weld scale is present, passivation of the stainless portions following ASTM A380 for cleaning and ASTM A967 for the passivation treatment, a final flush with treated water, then filter changes until particle count and chemistry hold steady across consecutive samples. Only then is the loop charged with the inhibited fluid the equipment maker specifies and released to the IT side. It is the same discipline we apply where an unpassivated stainless surface fails inspection: see passivation services and high-purity water systems.

Data center cooling systems and how they work

How are data centers cooled, and how does data center cooling work? Every data center cooling system does two jobs: it collects heat from the IT equipment, and it rejects that heat outdoors. Collection happens through air across computer room air handlers, liquid through cold plates, or a fluid bath. Rejection happens at a chiller plant, a cooling tower, a dry cooler or a combination, and that plant, not the white space, is where almost all data center cooling water is consumed. The types of data center cooling systems in service today are mostly combinations of the heat rejection methods below.

Heat rejection method How it works Water consumed on site Mechanical and water scope
Water-cooled chillers with cooling towers Chillers make chilled water; condenser heat leaves through evaporative towers Highest: evaporation, drift and blowdown Condenser and chilled water piping, tower water treatment, makeup softening or reverse osmosis
Air-cooled chillers Refrigeration with condenser heat rejected to outdoor air Minimal Chilled water piping, pumps, glycol where freezing is possible
Dry coolers Closed finned coil and fans, no evaporation Near zero Glycol loop piping, fill, inhibitor and testing
Dry coolers with adiabatic assist Incoming air pre-cooled by evaporating water on pads or sprays during peak hours Low and seasonal Adiabatic water supply, treatment and drainage
Waterside economizer A plate heat exchanger lets cold condenser water make chilled water with the chillers off Set by the tower or cooler it uses, with less compressor energy Heat exchanger, valves and tie-ins to the chilled water plant
Direct and indirect evaporative air cooling Outdoor or recirculated air cooled by evaporating water Moderate Water supply, treatment and drain-down

Data center cooling technologies differ more inside the white space than in the plant. Air cooling with a CRAH unit, a computer room air handler that blows room air across a chilled water coil, still serves most existing halls; a CRAC unit does the same job with its own refrigerant circuit instead of chilled water. Data center water cooling moves the heat transfer closer to the chips. A data center water cooling system on the IT side runs through a coolant distribution unit, and the data center cooling liquid in that loop is treated water or a water and propylene glycol mixture with inhibitors, chosen to the equipment maker’s specification. A data center chiller plant is often still needed for the air-cooled share of the load, so data center HVAC and liquid cooling run side by side in most new buildings, and data center water cooling systems have to be designed around both.

Data center cooling methods are chosen by the owner’s engineer, and the equipment comes from data center cooling companies that manufacture chillers, coolant distribution units, CRAH units and dry coolers. No single data center cooling solution fits every climate and water supply. Paul Industries builds the data center cooling infrastructure that connects the equipment: the piping, pumps, heat exchangers and water treatment systems, and the cleaning and commissioning of every loop. The manufacturers supply the data center cooling solutions themselves. For AI data center cooling, where a single rack can exceed 100 kilowatts, that infrastructure is the part of the building most likely to change between phases, because an AI data center cooling system usually adds a liquid loop to a plant first sized for air. The data center HVAC system on the air side and the building controls are usually separate trade packages.

Direct to chip, immersion and air cooling compared

Most liquid cooling data center design work begins by deciding how close the water gets to the silicon. The closer it gets, the more heat a rack rejects and the tighter the water quality must be.

Cooling approach How heat leaves the rack Water systems required Filtration (micron)
Air cooling with CRAH units Room air across a chilled water coil Chilled water and condenser water, facility side only Coarse strainers; air filters do the work
Rear-door heat exchanger Rack exhaust air through a coil on the cabinet Facility chilled water, sometimes a secondary loop Strainers sized to the coil passages
Direct to chip, single phase Fluid through cold plates on the processors Facility water plus a closed technical loop through a coolant distribution unit Fine filtration to the cold plate maker’s rating
Single phase immersion Dielectric fluid in a tank, cooled by a water coil Facility water to the tank exchanger; the dielectric fluid is not water Fluid conditioning per the fluid supplier

A direct to chip liquid cooling data center still air cools memory, drives and power supplies, so the building runs chilled water, condenser water and a technical loop at once. That mixed condition, not any single system, is what complicates the mechanical scope.

What is direct to chip cooling? It is liquid cooling in which a cold plate, a metal block with fine internal channels, sits directly on the processor and carries coolant through it, so heat enters the liquid at the chip instead of the room air. Cold plate cooling is the dominant form of direct to chip cooling because it fits standard racks and servers, and it is the reason the technical loop has to be cleaner than any building water system. In a direct to chip cooling data center, the coolant distribution unit, the row manifolds and the rack hoses are the new mechanical scope.

Immersion cooling takes the opposite approach: servers sit in a tank of dielectric fluid that does not conduct electricity. In single phase immersion cooling the fluid stays liquid and is pumped through a heat exchanger that hands the heat to facility water. In two phase immersion cooling the fluid boils at a low temperature on the hot components and condenses on a coil above the bath; many of those fluids are fluorinated, and regulatory attention to PFAS chemicals has made fluid selection a procurement question as much as an engineering one. Immersion cooling for data centers remains a smaller share of installed capacity than cold plates, and liquid immersion cooling for data centers changes the water scope less than people expect: the dielectric fluid never touches building water, and the facility side is a conventional heat exchanger connection. An immersion cooling data center hall still needs clean, treated facility water like any other.

A rear door heat exchanger data center retrofit is the least disruptive step. A chilled water coil replaces the cabinet’s rear door and cools the exhaust air before it reaches the room, which raises rack capacity without changing the servers. It still brings water into the white space, so isolation valves, leak detection and water quality on that branch need the same care as a liquid loop.

Cooling towers, chilled water and makeup water treatment

Where heat is rejected evaporatively, data center cooling water chemistry is governed by cycles of concentration: the ratio of dissolved solids in the circulating water to the makeup. More cycles save water and raise scaling and corrosion risk; fewer cycles wastes water and sewer capacity. The control points are conductivity-driven blowdown, inhibitor dosed to the cycles actually held, side-stream filtration to pull airborne dirt out before it becomes basin sludge, and biological control. Legionella risk management belongs in writing, in a water management plan of the kind ASHRAE Standard 188 describes, because a cooling tower is an aerosol generator.

A data center chilled water system on the closed side behaves differently: no evaporation and therefore no concentration, but a large volume of water against carbon steel, needing a corrosion inhibitor, a reserve confirmed by testing, and a way to add makeup without drawing in oxygen and dirt. Makeup is chosen from the water available at the site, which is why data center water treatment systems look different from one campus to the next.

Makeup water condition Treatment commonly justified Why
Hard municipal supply Softening Removing calcium and magnesium lets the tower hold more cycles without carbonate scale
High dissolved solids, silica or chlorides Reverse osmosis Lowers the dissolved load so cycles are set by chemistry, not one aggressive ion
Reclaimed or non-potable supply Filtration, disinfection, often reverse osmosis Reuse water carries nutrients, ammonia and solids that drive biofouling
Well water with iron or manganese Oxidation and filtration first Iron fouls membranes, softener resin and heat transfer surfaces
Closed loop fill and top-up Deionized or reverse osmosis water with inhibitor A closed loop has no blowdown, so whatever goes in stays in

Data center water usage: how much water data centers use

Data center water usage is now a planning issue on almost every new campus, and the real numbers are larger than most people expect and smaller than many headlines suggest. How much water do data centers use nationally? Lawrence Berkeley National Laboratory’s 2024 report for the Department of Energy put direct data center water consumption in the United States at about 66 billion liters in 2023, roughly 17.4 billion gallons, up from 21.2 billion liters in 2014. Hyperscale and colocation facilities accounted for 84 percent of that total. The same report estimated a far larger indirect footprint, nearly 800 billion liters, consumed at the power plants that generate data center electricity.

Why do data centers need water at all? Mostly because evaporation is the cheapest way to reject heat: a cooling tower removes heat by evaporating part of the condenser water, so the site keeps buying makeup water to replace what leaves. Per site, data center water use depends on how heat is rejected. A large campus on evaporative cooling towers can draw millions of gallons on a hot day, and figures of up to 5 million gallons a day are cited for the biggest facilities, while a site on dry coolers and closed loops may use little beyond domestic water. That is why data center water usage per day is a poor way to compare two sites unless the cooling design is known. Data center water consumption, meaning water that evaporates or otherwise leaves and is not returned to the local source, is the figure a water utility cares about.

AI data center water use is rising for a specific reason. AI training hardware runs at rack densities that air cannot cool, so the heat goes into water, and the Berkeley Lab report expects average water usage effectiveness to climb from just over 0.36 liters per kilowatt-hour through 2023 to between 0.45 and 0.48 by 2028 as hyperscale and liquid-cooled capacity grows. Even so, AI data center water usage is decided by the heat rejection plant: the same load can be met by evaporative towers that consume water or by dry coolers that consume very little and use more electricity instead. Every AI data center water consumption estimate is really an estimate of that design choice.

Water usage, reuse and what happens to the cooling water

Water usage effectiveness, published by The Green Grid as liters of water per kilowatt-hour of IT energy, is the reported number, and it is driven almost entirely by whether heat is rejected evaporatively. Two questions follow: what happens to data center cooling water, and can data center cooling water be reused.

Where does data center water go? In an evaporative design most of it leaves as vapor from the tower and the rest as blowdown to drain, so data center cooling water consumption is genuinely consumptive. In a closed design the water does not leave except through leaks, maintenance drain-downs and fluid changes, which is why closed loop data center cooling water usage is near zero once the loop is filled, and why operators adding liquid cooling can cut reported water use while raising rack density. So do data centers use closed loop cooling? Every data center liquid cooling deployment does on the IT side, where a closed loop cooling system carries coolant from the coolant distribution unit to the cold plates; whether the site is also closed on the heat rejection side depends on whether it rejects heat through dry coolers or evaporative towers.

Is data center water recycled? Inside a closed loop it is recirculated for years, which is why data center water usage closed loop figures are so low. Across the site, data center water recycling means recovering blowdown or using reclaimed municipal water, and that reuse is real, but it is an engineering project rather than a setting. Tower blowdown can be recovered and partly reused after filtration and treatment. Reclaimed municipal and other non-potable supplies can serve as makeup with heavier pretreatment and biological control. Can salt water be used to cool data centers? At some coastal sites, yes: seawater passes through titanium plate heat exchangers and never enters the building loops, at the cost of intake permitting, screening and corrosion-resistant materials. Air handler condensate can be captured. And effluent headed to sewer often needs pretreatment to satisfy a local discharge permit, its own scope of work.

Data center wastewater, water quality and pollution concerns

Most data center wastewater is cooling tower blowdown and, where reverse osmosis is used, membrane reject. Both carry the minerals that arrived with the makeup water, concentrated several times over, plus residual treatment chemicals. The discharge normally goes to the sanitary sewer under the local utility’s permit, which applies the federal pretreatment rules in 40 CFR Part 403 along with local limits. Data center wastewater treatment before discharge is typically pH adjustment, solids removal and, where limits require it, neutralization or dechlorination of residual biocide.

Do data centers pollute water? The direct exposure is that discharge and the chemicals used in cooling, and public concern about data center water pollution and data center water contamination mostly comes back to those two. The safeguards are the same as in any industrial plant: a treatment program with known chemicals and dosing records, blowdown monitored against permit limits, secondary containment for chemical storage, and backflow prevention so cooling water can never reach the potable supply. Data center water quality inside the building, in the closed technical loop, is a separate subject covered above. See wastewater and effluent pretreatment and commercial reverse osmosis systems.

Data center piping: fabrication, welding and installation

Materials split along the same line as the chemistry. Facility chilled water and condenser water are usually carbon steel with grooved or welded joints. The technical cooling loop is normally stainless, joined by welding rather than brazing so no flux ever enters the circuit, and welded orbitally on tube runs for a repeatable, clean internal surface. Our data center piping scope covers shop fabrication of spools and skids, field installation, supports and bracing, pressure testing to the governing code, and tie-ins to existing plant.

Prefabrication matters here more than on most jobs. A data center is commissioned in phases while neighboring halls are live, so fewer hot work hours and open pipe ends inside the building is a direct schedule and risk saving. Spools, pump skids, coolant distribution unit connections and filtration assemblies built and tested in the shop arrive ready to set, which is how data center piping installation holds a short schedule. See process piping, stainless and hygienic piping and turnkey process systems.

Commissioning records and handover documentation

A loop is not finished because it holds pressure. The handover package should carry the weld map and weld records with welder and procedure identification, pressure test records, the flushing report with velocities and duration, cleaning and passivation records including method and verification, particle counts or filter change logs, baseline water chemistry with the inhibitor and its concentration, and maintenance intervals for filters, inhibitor testing and heat exchanger inspection. That package lets an operator later prove what the water was at acceptance, and preventive maintenance keeps it true.

Data center construction: where the mechanical and water scope fits

Data center construction is led by a general contractor or design-builder, with mechanical, electrical and plumbing trade partners carrying much of the cost. In data center MEP terms, Paul Industries sits on the mechanical and process side: chilled water, condenser water and technical cooling loop piping, water treatment systems, pumps and heat exchangers, and the cleaning and commissioning of all of them. We work as an industrial mechanical contractor alongside the data center construction companies that hold the prime contract. Electrical, controls and the building shell are other trades.

Hyperscale data center construction and AI data center construction add two pressures. Schedules are compressed and phased, so halls are built and commissioned while their neighbors run live. And the cooling design changes during the program as rack densities rise, so liquid loops are added to plants designed for air. Modular data center construction answers both with prefabrication: pipe spool fabrication in the shop, pump and filtration skids built and tested off site, and coolant distribution unit connections delivered ready to set. Mechanical and cooling systems are among the largest lines in data center construction cost, and prefabrication is one of the few ways to reduce field labor without reducing quality. See process skid fabrication and orbital welding services.

For owners and data center construction contractors choosing a mechanical partner, the details that separate data center construction services firms are the unglamorous ones: pipe flushing to a written procedure with velocities and filter logs rather than a fill and drain; chilled water piping insulation that is closed cell with a continuous vapor retarder, because condensation on cold pipe above racks is a leak by another name; and test and cleaning records handed over as part of the work. Whichever data center construction company holds the prime contract, those records should arrive with the mechanical scope, not after it.

What to require from a data center water and piping contractor

Buyers searching for data center water treatment companies, or for liquid cooling data center companies, find chemical suppliers, equipment makers and mechanical contractors doing quite different things. Before awarding the mechanical scope, ask any data center piping contractor for the following.

  • Welder and procedure qualifications for the materials in your loop, plus a weld map from a recent job.
  • A written flush, clean and passivation procedure with acceptance criteria, not the phrase “flushed and filled”.
  • Demonstrated high-purity water work, because the closed loop is a high-purity problem in facility clothing.
  • Contractual acceptance of the cold plate and coolant distribution unit maker’s water quality and filtration limits.
  • In-house fabrication capacity, so a phased schedule is not gated by a fabrication subcontractor.
  • The commissioning document list offered up front, not assembled after turnover.
  • Service and maintenance from the same firm that built it.
  • Clarity about scope boundaries, including what the contractor does not do.

Data center commissioning: the mechanical and water scope

Data center commissioning levels are usually described as five stages, and the water and piping systems run through most of them. The labels vary between owners and commissioning agents, so the scope should be written against the owner’s own commissioning plan, but the sequence is broadly consistent.

Level What it covers Where the piping and water work sits
Level 1 Factory or vendor verification of major equipment before it ships Witnessing or reviewing tests on pumps, heat exchangers and coolant distribution units where the owner requires it
Level 2 Installation verification and site acceptance of delivered equipment Piping installed to drawings, supports, welds, labelling and the pressure test records
Level 3 Pre-functional checks and startup of individual systems Flushing, cleaning and passivation of new loops, fill, venting and first water chemistry
Level 4 Functional performance testing of each system on its own Flow and differential pressure across branches, valve operation and loop balancing
Level 5 Integrated systems testing, with all systems running together under load Supporting the load bank test, holding water quality, and correcting what the integrated test exposes

Of the 5 levels of data center commissioning, the ones most often compressed on a fast schedule are three and four, and that is exactly where a cooling loop is either cleaned properly or carries construction debris into the first cold plates. Data center commissioning services that treat the water system as a deliverable, with its own records, catch this before Level 5 rather than during it. When comparing data center commissioning companies, ask which levels they self-perform and which they only witness.

Coolant distribution unit piping and connection

A coolant distribution unit, or CDU, is the boundary between the facility water system and the technical cooling system that feeds the IT equipment. Inside it are the pumps, the heat exchanger that keeps the two loops separate, filtration and the controls. The coolant distribution unit itself is supplied by its manufacturer. The work around it is where installation quality decides whether it performs: the facility-side supply and return, the secondary-side distribution to the racks or rows, isolation and bypass valves, strainers, drains and vents, and the instrumentation the controls depend on.

Whichever coolant distribution unit data center teams specify, three installation details matter more than they appear to. Every secondary-side connection must be clean before the CDU is first filled, because the unit’s own filtration is sized for operating particulate, not for weld scale and swarf. Materials on the secondary side must match the manufacturer’s stated wetted-material list, because one incompatible fitting can introduce galvanic corrosion into an otherwise clean loop. And the flush has to run through the distribution with the IT connections bypassed, so that nothing reaches a cold plate until the loop is proven clean.

Data center cooling tower water treatment and piping

A data center cooling tower rejects heat by evaporating water, which concentrates every dissolved solid left behind. Treatment manages three things at once: scale from hardness and silica as concentration rises, corrosion of the condenser water piping and heat exchangers, and biological growth including the Legionella risk that ASHRAE Standard 188 asks owners to manage through a written water management program. The levers are the cycles of concentration the makeup water will support, chemical treatment matched to that water, side-stream filtration to keep suspended solids out of the exchangers, and blowdown sized so concentration stays where the program sets it.

The piping side is often overlooked. Dead legs in condenser water piping, low points that cannot drain, and bypasses that stagnate in winter all give bacteria somewhere to settle regardless of how good the chemistry is. A data center cooling tower installation should be reviewed for drainability and stagnant sections at design, not after the first positive sample. Our cooling tower water treatment page covers blowdown, chemical feed, side stream filtration and Legionella control in full.

On data center cooling towers, a cooling tower water treatment chemical program usually has four parts: a scale inhibitor such as a phosphonate or polymer, a corrosion inhibitor including an azole where copper is present, an oxidizing biocide such as chlorine or bromine, often alternated with a non-oxidizing biocide, and a dispersant that keeps solids moving to blowdown. Legionella cooling tower risk is controlled by that biocide program together with the written water management plan, routine sampling, and physical upkeep: drift eliminators in good condition, clean basins and no stagnant piping.

Dry coolers, adiabatic cooling and glycol loops

Dry cooler vs cooling tower is the central trade-off in data center water use. A cooling tower cools water by evaporating part of it, which brings the loop close to the outdoor wet-bulb temperature but consumes water continuously. A dry cooler passes the loop through a finned coil with fans, consuming no water but only able to cool toward the outdoor dry-bulb temperature, which is higher. Warm-water liquid cooling, with facility water supplied in ASHRAE’s higher temperature classes, is what makes a dry cooler for data center service practical in many climates.

Adiabatic cooling bridges the two. During the hottest hours, water is sprayed or wetted onto pads ahead of the dry cooler coil, and its evaporation pre-cools the incoming air. Adiabatic cooling data center designs use water only seasonally, but that water still needs treatment, drainage and Legionella management, and pads and nozzles scale quickly on hard water. Evaporative cooling data center designs that cool the air directly, or through an air-to-air exchanger, trade water for energy the same way and carry the same water treatment duties.

Any loop that runs outdoors in a freezing climate is usually a glycol cooling system. A closed loop glycol cooling system needs inhibited propylene or ethylene glycol at a measured concentration, periodic testing of glycol strength, pH and inhibitor reserve, and the understanding that glycol reduces heat transfer, so concentration should be set to the freeze protection actually required. Automotive antifreeze has no place in it. A waterside economizer adds a plate heat exchanger between condenser water and chilled water so that in cold weather the tower or dry cooler makes chilled water with the chillers off; its plate pack is a fouling point that belongs in the maintenance plan. See heat exchangers and process chillers.

Data center maintenance for cooling water and piping systems

Data center maintenance on the water side keeps acceptance-day conditions true for years. A data center maintenance service contract for the cooling systems typically covers inhibitor and glycol testing, filter and strainer changes on the technical loop, water chemistry trended against the commissioning baseline, cooling tower inspection and Legionella sampling under the water management plan, plate heat exchanger inspection and cleaning, pump and valve service, and leak checks on branches serving the white space.

The intervals come from the equipment makers and the water management plan, and the records belong with the commissioning package so any change in water quality can be traced to a date. Paul Industries provides this as preventive maintenance on systems we built and on systems others built, so the crew testing the loop knows how it was cleaned.

What Paul Industries does

Paul Industries is a nationwide cGMP process-equipment and sanitary-piping contractor, and our data center work is the facility and water side of the building. We build high-purity water systems including reverse osmosis, deionization, softening and filtration; fabricate and install stainless and carbon steel process and chilled water piping with orbital and manual welding; set process chillers, heat exchangers, pumps and process and storage tanks; run plant utilities; clean, flush and passivate new stainless systems; build effluent pretreatment; and provide millwright and rigging, commissioning support, service contracts and engineering and design. We are not an IT or server vendor, not a cooling equipment manufacturer and not a colocation operator. Request a quote, or see the industries we serve.

Standards referenced: ASME B31.3 · ASME BPVC · ASTM A380 · ASTM A967 · NSF/ANSI 61

Frequently asked questions

Does AI increase data center water use?

It can. AI hardware runs at rack densities that air cannot cool, so the heat goes into liquid loops, and Berkeley Lab expects average water usage effectiveness across U.S. data centers to rise from about 0.36 to between 0.45 and 0.48 liters per kilowatt-hour by 2028. Whether a given AI site consumes much water still depends on its heat rejection: evaporative towers consume it, dry coolers largely do not.

What is the difference between single phase and two phase immersion cooling?

In single phase immersion cooling the dielectric fluid stays liquid and is pumped through a heat exchanger that passes the heat to facility water. In two phase immersion cooling the fluid boils on the hot components and condenses on a coil above the tank. Many two phase fluids are fluorinated, so PFAS rules now affect fluid choice. Either way, the facility side is a water-to-fluid heat exchanger connection.

Dry cooler vs cooling tower: which uses less water?

A dry cooler uses essentially no water because it rejects heat through a sealed coil and fans. A cooling tower evaporates water to cool the loop, so it consumes water continuously, but it reaches lower temperatures and usually uses less electricity. Warm-water liquid cooling is what lets many sites choose dry coolers, sometimes with adiabatic assist for the hottest hours.

What is adiabatic cooling in a data center?

Adiabatic cooling pre-cools the air entering a dry cooler by evaporating water on pads or through sprays, only when outdoor temperatures are high. It uses far less water than a cooling tower over a year, but the water it does use needs treatment, drainage and Legionella management, and hard water scales the pads and nozzles quickly.

What chemicals are used in cooling tower water treatment?

A typical program combines a scale inhibitor such as a phosphonate or polymer, a corrosion inhibitor including an azole where copper is present, an oxidizing biocide such as chlorine or bromine often alternated with a non-oxidizing biocide, and a dispersant. The dose is set to the cycles of concentration the makeup water supports, with blowdown controlled on conductivity.

Where does data center wastewater go?

Mostly to the sanitary sewer. Cooling tower blowdown and reverse osmosis reject carry concentrated minerals and residual treatment chemicals, and they are discharged under the local utility's permit, which applies the federal pretreatment rules in 40 CFR Part 403 and local limits. Pretreatment before discharge is usually pH adjustment, solids removal and neutralization of residual biocide where required.

What is a waterside economizer?

A waterside economizer is a plate heat exchanger between the condenser water and chilled water loops. In cold weather the cooling tower or dry cooler can produce chilled water through it with the chillers off, saving compressor energy. Its plate pack fouls over time, so inspection and cleaning belong in the maintenance plan.

Why is glycol used in data center cooling loops?

Glycol protects loops that run outdoors, such as dry cooler circuits, from freezing. It must be inhibited industrial propylene or ethylene glycol, never automotive antifreeze, and its concentration should match the freeze protection actually required, because glycol reduces heat transfer. Strength, pH and inhibitor reserve are tested periodically.

Does Paul Industries build data centers?

We build the mechanical and water side of them. Paul Industries works as the industrial mechanical contractor for chilled water, condenser water and technical cooling loop piping, water treatment systems, pumps, heat exchangers, prefabricated spools and skids, flushing and passivation, commissioning support and maintenance, alongside the general contractor or design-builder that holds the prime contract.

What does a data center maintenance service cover for cooling systems?

On the water side: inhibitor and glycol testing, filter and strainer changes on the technical loop, water chemistry trended against the commissioning baseline, cooling tower inspection and Legionella sampling under the water management plan, plate heat exchanger inspection and cleaning, pump and valve service, and leak checks on branches serving the white space.

What are the five levels of data center commissioning?

They are commonly described as Level 1 factory or vendor verification, Level 2 installation verification and site acceptance, Level 3 pre-functional checks and startup, Level 4 functional performance testing of each system, and Level 5 integrated systems testing with everything running together under load. Labels vary between owners, so scope is written against the owner's commissioning plan.

What does a coolant distribution unit do in a data center?

A coolant distribution unit separates the facility water system from the technical cooling system that serves the IT equipment. It holds the pumps, the heat exchanger between the two loops, filtration and controls. The unit comes from its manufacturer; the piping, valves, strainers, instrumentation and the flush of the connected loop are installation work.

How is a data center cooling tower treated?

By running the cycles of concentration the makeup water supports, chemical treatment matched to that water to control scale and corrosion, side-stream filtration for suspended solids, blowdown to hold concentration, and a written water management program for Legionella under ASHRAE Standard 188. Piping that drains fully and has no stagnant dead legs matters as much as the chemistry.

Which commissioning levels involve the water and piping contractor?

Mostly Levels 2 through 4: installation verification and pressure test records at Level 2, flushing, passivation, fill and first chemistry at Level 3, and flow, differential pressure and balancing at Level 4. The contractor then supports Level 5 integrated testing by holding water quality and correcting what the integrated test exposes.

What is data center water treatment?

Data center water treatment is the chemistry and equipment that keeps two different water systems fit for service: the facility water system that rejects heat through a cooling tower, chiller or dry cooler, and the closed technical cooling loop that carries fluid to cold plates or rear-door heat exchangers. The facility side needs inhibitor, biocide and blowdown control. The closed side needs high-purity fill water, a matched inhibitor and fine filtration.

What is the difference between the facility water system and the technical cooling system?

The facility water system is the building side: condenser water, chilled water or a dry cooler circuit, open to the atmosphere in any evaporative design. The technical cooling system is the closed secondary loop on the IT side. A coolant distribution unit transfers heat between them through a plate heat exchanger while keeping the two volumes of water separate, so each can be treated to its own standard.

Why does a closed loop liquid cooling data center need high-purity water?

Because a closed loop liquid cooling data center has no blowdown, so whatever enters stays in. Dissolved ions raise conductivity and drive galvanic corrosion between the copper, stainless and sometimes aluminum in the same circuit. Chlorides and sulfates pit stainless and attack copper. Particulate blocks cold plate channels. The loop is small, permanent and unforgiving, which makes it a high-purity water problem rather than a plumbing problem.

What does ASHRAE TC 9.9 say about liquid cooling water?

ASHRAE Technical Committee 9.9 defines facility water supply classes W17, W27, W32, W40, W45 and W+, named for the upper supply temperature in degrees Celsius; earlier editions called them W1 to W5. They are temperature bands, from chilled water up to warm water operation needing no mechanical chiller. Water quality for the technical cooling loop is addressed separately, and the recurring parameters are pH, conductivity, chlorides, sulfates, total particulate and bacteria. Treat the equipment maker's stated limits as the binding numbers for your loop.

What happens to data center cooling water?

It depends on the cooling design, and people asking what happens to data center cooling water usually have an evaporative plant in mind. There, most water leaves as vapor from the cooling tower and the rest leaves as blowdown to the sewer. In a closed loop plant the water stays in the system and only leaves through leaks, maintenance drain-downs and scheduled fluid changes.

Can data center cooling water be reused?

Yes, with treatment. Cooling tower blowdown can be recovered and partly reused after filtration and chemical treatment. Reclaimed municipal and other non-potable water can serve as makeup given heavier pretreatment and tighter biological control, since reuse water brings nutrients, ammonia and solids. Air handler condensate can be captured as makeup. Each route is a designed system with its own pretreatment, monitoring and discharge permit implications.

How much water does a data center use for cooling?

Nationally, Lawrence Berkeley National Laboratory estimated direct U.S. data center water consumption at about 66 billion liters in 2023, roughly 17.4 billion gallons. Per site it varies by cooling approach and climate more than by size, from millions of gallons a day at the largest evaporative campuses to very little on dry coolers, so published figures for one site mean little at another. The metric to ask for is water usage effectiveness, in liters per kilowatt-hour of IT energy. Evaporative heat rejection dominates data center cooling water consumption; closed loop and dry cooling move the number toward zero while usually raising electrical energy use instead.

What is closed loop data center cooling water usage?

When operators compare closed loop data center cooling water usage with evaporative usage, the difference is structural. A closed loop never evaporates and never blows down, so after the initial fill its consumption is limited to leaks, maintenance drain-downs and periodic fluid replacement. The tradeoff is that heat still has to be rejected, usually with more fan and compressor energy than an evaporative tower would need.

Does a new liquid cooling loop have to be flushed and passivated before servers are connected?

Yes. A new loop contains weld scale, cutting oil, thread sealant, flux residue and construction grit. The sequence is pressure test, degrease, high velocity flush, chemical cleaning or pickling where weld scale exists, passivation of the stainless portions per ASTM A380 and ASTM A967, final flush with treated water, then filter changes until particle count and chemistry hold. Skip it and the cold plates filter the pipework for you.

What is direct to chip liquid cooling and how does it differ from immersion?

In a direct to chip liquid cooling data center, fluid runs through cold plates bonded to the processors while air still cools memory, drives and power supplies. In immersion, whole servers sit in a dielectric fluid that is cooled by a water coil or external exchanger. Direct to chip keeps conventional servers and adds a water loop; immersion changes the hardware but removes most airflow.

Who installs the piping for a direct liquid cooling data center?

The mechanical contractor, not the IT vendor. For a direct liquid cooling data center that means facility water piping, the closed technical loop, coolant distribution unit connections, filtration and pump assemblies, pressure testing, and the clean, flush and passivation before handover. Paul Industries does that scope, including shop fabrication of spools and skids so field work inside a live building stays short.

What should I look for in liquid cooling data center companies?

Separate the categories first. Searches for liquid cooling data center companies return cooling hardware makers, chemical treatment suppliers and mechanical contractors, and you need all three roles filled but by the right parties. From the contractor, require welding qualifications, a written clean and passivation procedure with acceptance criteria, demonstrated high-purity water experience, in-house fabrication, and contractual acceptance of the equipment maker's water quality limits.

What does data center cooling water treatment involve on the tower side?

Tower-side data center cooling water treatment is built around cycles of concentration. You dose scale and corrosion inhibitor to the cycles actually held, control blowdown on conductivity, add side-stream filtration so airborne dirt does not become basin sludge, run a biocide program against biofilm, and manage Legionella risk under a written water management plan of the kind ASHRAE Standard 188 describes.

Is reverse osmosis or softening the right makeup treatment?

It depends on the feed water. Softening is the usual answer for hard municipal water, since removing calcium and magnesium lets a tower hold more cycles without carbonate scale. Reverse osmosis is justified where dissolved solids, silica or chlorides cap the cycles regardless of hardness, and for closed loop fill water. Well water with iron or manganese needs oxidation and filtration before either one.

What does a data center chilled water system need from a contractor?

A data center chilled water system is a closed circuit with a large water volume against carbon steel, so it needs a corrosion inhibitor with a monitored reserve, clean fill water, air and dirt separation, and makeup that does not drag in oxygen. The contractor scope is pipe fabrication and installation, chiller and pump setting, heat exchangers, pressure testing, flushing, chemical commissioning and the service intervals afterward.

What documentation should a data center piping contractor hand over?

Ask any data center piping contractor for a weld map and weld records identifying welder and procedure, pressure test records, a flushing report with velocity and duration, cleaning and passivation records with method and verification, particle count or filter change logs, baseline water chemistry with the inhibitor and its concentration, equipment submittals, and the maintenance intervals for filters, inhibitor testing and heat exchanger inspection.

Can this work be done in an occupied, operating facility?

Yes, and most of it is. The method is prefabrication: build and test spools, pump skids and filtration assemblies in the shop so field time is short and hot work inside the building is minimized, then tie in during agreed windows with isolation and testing planned in advance. Phased commissioning beside live halls is the normal condition on this kind of project, not the exception.

Related: Industries We Serve · High-Purity Water System Installation (USP, WFI, RO/DI) · Process Chiller Installation & Service · Sanitary Heat Exchanger Installation & Service · Plant Utilities: Steam, Heating, Chilled Water & Ice Builders · Process Piping · Request a quote · Plate Heat Exchanger