Paul Industries is a US process equipment contractor for Belgium that engineers process systems for Belgian vaccine, biopharmaceutical and chemical plants, fabricates their skids, vessels, tanks and spools in the United States, ships them to Antwerp-Bruges, and installs, starts up and commissions them on site or supervises the plant’s own installers. From its headquarters at 256 Shore Drive, Kilmarnock, Virginia, Paul Industries works for plants in Flanders, Wallonia and Brussels, building each system to the Pressure Equipment Directive as Belgium’s Royal Decree of 11 July 2016 applies it, to the AREI/RGIE electrical regulation and to the EU GMP Guide that the FAMHP inspects against.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Belgian pressure law Royal Decree of 11 July 2016, transposing PED 2014/68/EU
Power 50 Hz; 3N 400 V and legacy 3×230 V networks
Electrical code AREI/RGIE, with inspection before commissioning
GMP regulator FAMHP, in PIC/S since 1997
Main port Antwerp-Bruges, about 12 days from New York
Reviewed November 2026

What does a US process equipment contractor for Belgium handle?

A US process equipment contractor for Belgium handles every stage between a Belgian plant’s process requirement and a qualified, running system: process and mechanical design, shop fabrication, factory testing, export packing, ocean freight to Antwerp, and installation, start-up, commissioning and qualification at the site. Paul Industries carries those stages under one contract with one schedule and one set of records.

Belgian sites buy a recognizable set of systems from Paul Industries: high-purity water systems generating purified water and WFI, clean steam generation and distribution, CIP and SIP skids, jacketed process tanks for formulation and buffer hold, pressure vessels for chemical service, sanitary process piping and the cleanrooms and utilities around sterile filling lines.

Three delivery routes are offered to Belgian plants. Supply with supervision: Paul Industries designs, builds, tests and ships the equipment and directs the plant’s installation contractor on site. Design-build: Paul also engineers the process area, utility connections and integration with existing systems. Full installation: Paul Industries places, connects, energizes, starts up and qualifies the system and turns it over with the complete record.

Which pharmaceutical companies in Belgium run the plants that buy process systems?

The pharmaceutical companies in Belgium that run large manufacturing plants include GSK, Pfizer, UCB and Janssen, alongside a dense layer of biotech firms, contract manufacturers and vaccine specialists in both Flanders and Wallonia. The pharmaceutical industry in Belgium exported about 79 billion euros of biopharmaceutical products in 2024, according to sector association figures, with the United States taking nearly a quarter of that. The plants named here are market facts showing where Belgian process demand sits.

Wallonia’s vaccine and biologics belt

Wallonia’s vaccine and biologics belt runs south of Brussels through Walloon Brabant and Namur province. GSK operates vaccine sites at Wavre, Rixensart and Gembloux, with Wavre producing vaccine adjuvants, and UCB has built biologics manufacturing at Braine-l’Alleud. The Gosselies biopark near Charleroi adds cell and gene therapy and biotech production. These plants buy WFI and clean steam systems, buffer and media preparation skids, CIP and SIP systems, and the utilities behind aseptic filling for sterile injectables.

Flanders: Puurs, Beerse, Geel and Ghent

Pharmaceutical companies in Flanders include Pfizer at Puurs, a large fill-finish and vaccine production site between Antwerp and Brussels, and Janssen, with development and production at Beerse and a chemical production plant at Geel. Together with Puurs, the Beerse and Geel sites place several major pharma companies in Antwerp province, while Ghent hosts biotech research and production around its university. Flemish plants buy formulation vessels, sanitary piping, water systems and solvent-handling equipment for active ingredient production.

Biotech companies in Belgium

Biotech companies in Belgium cluster around Ghent, Leuven, Brussels, Liege and Gosselies, ranging from antibody developers to cell therapy and vaccine start-ups moving from clinical to commercial scale. Pharma and biotech companies in Belgium buy the same building blocks at different sizes: single-use and stainless process skids, purified water and WFI, process tanks and clean utility piping for biotech manufacturing.

Belgian process clusters and what their plants buy
ClusterProduction focusSystems in demand
Walloon Brabant and Namur (Wavre, Rixensart, Gembloux, Braine-l’Alleud)Vaccines, adjuvants, biologicsWFI, clean steam, buffer and media skids, CIP and SIP
Charleroi and GosseliesBiotech, cell and gene therapyClean utilities, cleanroom systems, pilot skids
Antwerp province (Puurs, Beerse, Geel)Fill-finish, drug development, active ingredientsFormulation tanks, sanitary piping, solvent systems, purified water
Port of Antwerp-BrugesPetrochemicals, base and specialty chemicals, gasesPressure vessels, reactor modules, ATEX skids, process piping
Ghent and LeuvenBiotech, food and specialty chemicalsProcess skids, water treatment, process tanks

Chemical industry in Belgium: the Port of Antwerp-Bruges chemical cluster

The chemical industry in Belgium centers on the Port of Antwerp-Bruges chemical cluster, which the port describes as Europe’s largest integrated chemical cluster, with further chemical plants in Ghent, along the Albert Canal and in Wallonia around Feluy, Seneffe and Liege. The port owns and controls about 720 kilometres of pipelines, nine tenths of them serving chemical and petrochemical producers, so plants in the Antwerp petrochemical cluster exchange feedstocks and products by pipe rather than by truck.

The chemical companies Belgium hosts in that cluster buy pressure vessels, columns, reactor modules, heat exchangers, dosing and injection skids, and long runs of process piping, much of it for hazardous areas. Chemical plants in Belgium are also investing in hydrogen, carbon capture and electrified heat, which brings new pressure equipment and piping into existing units. Paul Industries designs and builds that equipment to the PED and ATEX directives and to each plant’s own piping and instrument specifications, for chemical manufacturing in and around the Port of Antwerp chemical cluster.

Which Belgian rules apply to pressure equipment, electrical work and GMP?

Belgian rules for a process system combine EU product directives transposed by royal decree with national regulations for use and installation: the Royal Decree of 11 July 2016 for pressure equipment, the well-being at work rules once the equipment is in service, the machinery rules, the AREI/RGIE for electrical installations, and EU GMP enforced by the FAMHP. The table sets out what each one asks of the equipment and its documents.

Belgian and EU rules for process equipment installed in Belgium
RuleScopeWhat the equipment and its records need
Royal Decree of 11 July 2016 (PED 2014/68/EU)Pressure equipment and assemblies rated over 0.5 barHazard category, the matching assessment module, CE mark, declaration of conformity and user instructions
Well-being at work rules (FPS Employment)Pressure equipment and work equipment in useOperating instructions, design and test data for in-service inspection
Machinery rules: Directive 2006/42/EC until the EU Machinery Regulation 2023/1230 applies on January 20, 2027Packaged units with pumps, agitators or other moving partsDocumented risk assessment, machinery technical file, declaration and CE mark
ATEX Directive 2014/34/EUAnything installed where flammable gas or dust can form an explosive mixtureGroup and category matched to the plant’s zones, marking and certificates
AREI/RGIEElectrical installations at the siteDiagrams and documents for the conformity inspection before commissioning
EU GMP Guide and Annex 1Manufacture of medicines and vaccinesQualified design, traceable materials, validated cleaning and sterilization, data integrity

Pressure equipment under the Royal Decree of 11 July 2016

The Royal Decree of 11 July 2016 transposes the PED into Belgian law for pressure equipment and assemblies with a maximum allowable pressure above 0.5 bar, replacing the 1999 decree that implemented the earlier directive. A vessel or skid for a Belgian plant is categorized by fluid group, pressure and volume, assessed under the module its category requires, CE marked and delivered with its EU declaration of conformity. Once the equipment is working, it falls under the FPS Employment, Labour and Social Dialogue and the well-being at work rules that govern in-service inspection. Paul Industries supplies the calculations, drawings, material certificates, weld and NDT records, test certificates and instructions that both stages rely on, with ASME Section VIII used as the design basis inside the PED route where the plant’s standards call for it.

AREI/RGIE and the electrical inspection before start-up

The AREI (in Dutch) or RGIE (in French) is Belgium’s General Regulation on Electrical Installations, and it requires a conformity inspection of a new installation or a major modification before it is first put into service, followed by periodic inspections, commonly every five years for industrial installations. A skid’s panel and field wiring join that installation, so the inspection draws on single-line diagrams, circuit schedules, protective device data and earthing details. Paul Industries prepares those documents in the format the Belgian inspection expects, so the electrical sign-off keeps pace with start-up.

Machinery, ATEX and the CE file for a Belgian skid

A packaged skid for a Belgian plant usually counts as machinery as well as pressure equipment, so its CE file joins two conformity routes: the PED assessment for the pressure parts and the machinery risk assessment for the assembly with its pumps, agitators and controls. Equipment delivered before January 20, 2027 follows the Machinery Directive; deliveries after that date follow the EU Machinery Regulation, which also allows digital instructions with a paper copy on request. Where a skid sits in a classified zone, the ATEX assessment adds a third strand. Paul Industries combines the three into one indexed technical file and one declaration set, so the Belgian plant’s safety and quality teams review a single package rather than three loose bundles.

Why Belgian plants order process systems from the United States

Belgian plants order process systems from the United States for capacity, schedule and engineering continuity. Several of the country’s largest sites belong to American groups whose global standards were written around ASME, ASME BPE and US automation platforms, and a US builder fluent in the PED route delivers equipment that satisfies both the group standard and Belgian law. When European fabrication shops are booked out, US shop capacity shortens lead times, and a single builder that designs, fabricates, tests and commissions keeps responsibility for performance in one place.

Voltage in Belgium: 3N 400 V and 3×230 V networks at 50 Hz

Voltage in Belgium is supplied at 50 Hz on two low-voltage systems: the 3N 400 V system with a neutral, which distribution operators now install, and an older 3×230 V system without a neutral that still covers about 80 percent of Brussels according to its grid operator, plus parts of other cities. Industrial plants usually take medium voltage and transform it to 400 V on site, but a smaller site on a 3×230 V supply needs motors, drives and control transformers matched to it.

Voltage and frequency in Belgium therefore get confirmed at the code review, from the plant’s own single-line diagram rather than from a national average. Motors for a US 60 Hz design would run about one sixth slower at 50 Hz, so pumps, agitators and fans are chosen from 50 Hz performance data and drives are configured for 50 Hz base speed. Panels are built to EN 60204-1 with IEC components, and equipment in classified zones of Antwerp chemical plants carries ATEX marking.

FAMHP GMP inspection and the documents a Belgian plant needs

The Federal Agency for Medicines and Health Products, known as FAMHP in English, AFMPS in French and FAGG in Dutch, is Belgium’s medicines regulator, and it joined PIC in September 1991 and the PIC Scheme in February 1997. An FAMHP inspection assesses Belgian manufacturing against the EU GMP Guide, including Annex 1 for sterile products, which covers most vaccine and injectable plants in the country.

For process equipment this means a contamination control strategy that reaches into the design, closed processing, validated sterilization of product-contact parts, qualified utilities and computerized systems with sound data integrity. Water systems follow the European Pharmacopoeia, product-contact stainless follows ASME BPE with weld maps, borescope inspection and surface finish records, and Paul Industries’ validation and commissioning work produces the URS, design qualification, FAT, SAT, IQ and OQ records that a Belgian quality unit files. Documents are issued in French for Walloon sites and Dutch for Flemish sites, with English versions for corporate engineering teams.

Containment and effluent systems for vaccine production

Vaccine and viral vector plants add containment requirements that reach beyond the clean utilities. Process waste that may carry live organisms is collected and inactivated before discharge, usually in heat-based batch or continuous kill systems, and vent filters, drain design and closed sampling keep the organism inside the process. Paul Industries designs and builds those effluent decontamination and containment systems alongside the process skids they serve, with cycle validation data and temperature mapping records for the plant’s biosafety and GMP files.

Shipping to Belgium from USA ports through Antwerp-Bruges

Shipping to Belgium from USA ports for process equipment means a direct sailing from the US East Coast to Antwerp-Bruges, about 12 days from New York on direct container routes, followed by a short road, barge or rail move to the plant, since Belgium’s main pharmaceutical and chemical sites sit within roughly a day’s trucking of the port. Zeebrugge, the port’s coastal section, adds roll-on roll-off and breakbulk options.

Antwerp handles containers, flat racks and heavy project cargo, and the Albert Canal and Scheldt waterways carry heavy items inland toward Limburg and Liege. Paul Industries designs the shipping envelope into the equipment: skids that fit a container are sized to its door limits, larger systems are split into modules at flanged joints, and crates are built from ISPM 15 heat-treated wood with preservation for a North Atlantic crossing and a damp port climate.

Customs, VAT and ET14000 for a Belgian import

Belgium charges no customs duty on US-origin industrial goods, because Regulation (EU) 2026/1455 set the EU rate for them at zero from July 1, 2026, running until December 31, 2029 unless extended, with origin judged under the EU’s non-preferential rules. Belgian import VAT is 21 percent. An ET14000 authorisation lets an importer, whether based in Belgium or abroad, avoid pre-financing that VAT at the border as long as it files periodic Belgian VAT returns.

Freight and customs checkpoints for a delivery to a Belgian plant
CheckpointWhat happensWho acts under DAP
US exportExport filing, crate inspection, loading on the vesselPaul Industries
Ocean legAbout 12 days New York to Antwerp-Bruges on a direct routePaul Industries carries freight and risk
Arrival in Antwerp-BrugesDischarge, terminal handling, transfer to road, barge or railPaul Industries
Import clearanceDeclaration, zero duty for US-origin industrial goods, VAT at 21 percent or ET14000 deferralThe Belgian plant (Paul under DDP)
Delivery to siteUnloading, receiving inspection against the packing listThe plant unloads; Paul supervises lifts on request

How does a Belgian project with Paul Industries proceed?

A Belgian project with Paul Industries proceeds through nine stages, and the first two settle the Belgian specifics: PED category, ATEX zones, AREI/RGIE interface, document language and supply system at the site. The table shows each stage and its record.

Project stages for a process system delivered to Belgium
StageBelgian points settledWhat the plant receives
1. Code basisRoyal Decree category, machinery basis, ATEX zones, AREI/RGIE documents, French or Dutch documentsCode basis memo and document list
2. DesignMetric and DN drawings, 3N 400 V or 3×230 V electrical design at 50 Hz, Ph. Eur. water specificationP&IDs, layouts, calculations, specifications
3. FabricationPED-route materials, qualified welding, sanitary finishesMaterial certificates, weld maps, NDT and finish records
4. FATWitnessed by the Belgian team in the shop or by videoSigned FAT report and closed punch list
5. Export and freightISPM 15 crating, sailing to Antwerp-Bruges, inland legCommercial invoice, packing list, bill of lading
6. Installation or supervisionPlant permit-to-work, method statements in French or DutchInstallation and tie-in records
7. Electrical inspection and start-upAREI/RGIE conformity inspection, energization, flushing and first runsInspection documents, start-up report
8. QualificationSAT, IQ and OQ to EU GMP, data for PQExecuted protocols and deviation reports
9. Handover and serviceTraining, spares for transatlantic lead times, service planAs-builts, manuals, turnover file

Who builds process systems for plants in Belgium?

Paul Industries builds process systems for plants in Belgium, from individual skids and pressure vessels to complete WFI, clean steam, CIP, tank and piping packages for vaccine, biopharmaceutical and chemical producers, and stays with each system through Antwerp delivery, start-up and qualification at the Belgian site. The plant works with one firm that designed, built, tested and commissions the equipment, so every question on a weld, a test or a setting has a single owner. Neighboring markets follow the same model, described on the Netherlands and Ireland pages, and the international projects page lists every country Paul serves.

What drives the cost of process equipment delivered to Belgium?

The delivered cost of process equipment for a Belgian plant turns on six items besides the equipment: freight, crating and preservation, PED, ATEX and electrical documentation, VAT handling under the chosen Incoterm, French or Dutch documentation, and the installation route. Paul Industries prices each as a separate line.

Freight. Antwerp-Bruges is a short inland haul from most Belgian plants, so the ocean leg and the choice between container and flat rack dominate. Crating. Heat-treated crates, desiccant and nitrogen protect polished internals through the crossing and any wait at the quay. Documentation. PED conformity work for higher categories, ATEX selection and AREI/RGIE inspection documents add engineering time. Taxes. Customs duty drops out for US-made industrial equipment under Regulation (EU) 2026/1455; import VAT at 21 percent is handled by the plant, often through ET14000, or included by Paul Industries under DDP. Language. Manuals and labels in French or Dutch are prepared for the site. Installation route. Supervising the plant’s contractor needs fewer Paul field hours than full installation, which keeps start-up and qualification with the builder. Prices are quoted in US dollars, as a budget figure first and a firm price once the design basis, site and Incoterm are agreed.

Paul Industries for Belgian vaccine, biopharmaceutical and chemical plants

Paul Industries, headquartered on Shore Drive in Kilmarnock, Virginia, delivers complete process systems to Belgian plants in Flanders, Wallonia and Brussels. It engineers the system, fabricates the skids, vessels, tanks and spools in the United States, proves them in a factory acceptance test, ships them through Antwerp-Bruges, and sets, starts up, commissions and qualifies them at the plant or directs the plant’s installers through each step. The equipment arrives built and documented to the Royal Decree of 11 July 2016, the AREI/RGIE and EU GMP, with weld records, as-builts and validation documents in the turnover file. Send your scope, site and preferred Incoterm to request a quote.

Standards referenced: EU Pressure Equipment Directive 2014/68/EU · Royal Decree of 11 July 2016 on pressure equipment · Codex on well-being at work · AREI/RGIE (General Regulation on Electrical Installations) · EU Machinery Directive 2006/42/EC · EU Machinery Regulation 2023/1230 · EU Low Voltage Directive 2014/35/EU · ATEX Directive 2014/34/EU · EN 60204-1 · EU GMP Guide (EudraLex Volume 4) and Annex 1 · PIC/S GMP Guide · European Pharmacopoeia · ASME Boiler and Pressure Vessel Code Section VIII · ASME BPE · Regulation (EU) 2026/1455 · Incoterms 2020 · ISPM 15

Frequently asked questions

Is Belgium 50 or 60 Hz, and which voltage do plants use?

Belgium runs at 50 Hz. Industrial plants mostly take medium voltage and distribute 400 V three-phase with neutral, while some older urban networks, especially in Brussels, still supply 3×230 V without a neutral. Paul Industries confirms the supply system from the plant’s single-line diagram during the code review and selects motors, drives and control transformers for that exact supply.

What is FAMHP, and what does it inspect at a vaccine plant?

FAMHP is the Federal Agency for Medicines and Health Products, Belgium’s medicines regulator, called AFMPS in French and FAGG in Dutch. At a vaccine plant it inspects against the EU GMP Guide and Annex 1, looking at contamination control, sterilization of product-contact equipment, utility qualification and data integrity. Paul Industries designs and documents process systems so that evidence is ready for the inspector.

Who builds WFI systems for vaccine plants in Wallonia?

Paul Industries builds WFI generation, storage and distribution systems for vaccine and biologics plants in Wallonia, including the Wavre, Rixensart, Gembloux and Braine-l’Alleud area, designed to the European Pharmacopoeia and EU GMP Annex 1. Systems are fabricated and tested in the United States, shipped to Antwerp-Bruges and installed, started up and qualified at the site with French documentation.

Which sailing route brings US equipment to Antwerp-Bruges, and how long is it?

A crated process skid takes about 12 days from New York to Antwerp-Bruges on a direct container route, with longer times on services that call at several ports first. Terminal handling, customs and the inland leg add a few days. Paul Industries books freight once the crate dimensions are final and times the factory acceptance test to meet a chosen sailing.

Can a US-built pressure vessel go into service at an Antwerp chemical plant?

A US-built pressure vessel goes into service at an Antwerp chemical plant once it has passed the PED conformity assessment that Belgium’s Royal Decree of 11 July 2016 requires for its category, carries CE marking and arrives with its EU declaration of conformity and instructions. ASME Section VIII remains usable as the design basis inside that route, and Paul Industries plans the route before ordering material.

What customs duty and VAT apply to US equipment imported into Belgium?

US-origin industrial goods enter the EU, and therefore Belgium, at zero customs duty under Regulation (EU) 2026/1455, effective July 1, 2026 and set to run to the end of 2029. Import VAT is charged at 21 percent. With an ET14000 authorisation the importer avoids paying that VAT at the border and settles it through its periodic Belgian VAT returns.

Which documents does the AREI/RGIE inspection need for a new skid?

The AREI/RGIE conformity inspection before first use draws on single-line diagrams, circuit and cable schedules, protective device ratings, earthing and bonding details and the location plans of the installation the skid connects to. Paul Industries prepares those documents with the panel design and hands them to the plant’s electrical team ahead of energization, so the inspection runs on schedule.

Are manuals supplied in French or Dutch for Belgian plants?

Manuals, labels and safety information are supplied in French for plants in Wallonia and in Dutch for plants in Flanders, and Brussels sites choose either language or both. German is used for plants in the eastern cantons. Paul Industries agrees the languages and document list at the code review and adds English versions where corporate engineering teams need them.

Does Paul Industries install equipment at Belgian plants?

Paul Industries installs equipment at Belgian plants under its full installation route, placing, connecting, starting up and qualifying the system on site. Under the supply-with-supervision route, the plant’s installation contractor handles the rigging, piping and wiring with Paul Industries in charge of the sequence, the checks and the first runs. On both routes, the firm that designed and tested the system leads its commissioning in Belgium.

Who supplies CIP and SIP skids to fill-finish plants near Puurs and Brussels?

Paul Industries supplies CIP and SIP skids to fill-finish and formulation plants in the Puurs, Mechelen and Brussels area, designed for the plant’s tank, line and filler circuits, with validated cycles, drainable sanitary piping and recipe control. Skids are built and tested in the United States, shipped to Antwerp-Bruges and commissioned and qualified at the plant.

Does equipment for Antwerp chemical plants need ATEX marking?

Equipment placed in an explosive atmosphere at an Antwerp chemical plant needs ATEX marking matching the zone and gas group the plant has classified, under Directive 2014/34/EU. Motors, instruments, junction boxes and some mechanical components on a skid are selected accordingly. Paul Industries takes the zone drawings at the code review and records every ATEX component in the turnover file.

Which Incoterm do Belgian plants use for a first order from the United States?

Belgian plants placing a first order from the United States often choose DAP to their site, with Paul Industries carrying freight cost and transit risk to the plant and the plant clearing import with its ET14000 authorisation. DDP suits buyers who want a landed price including VAT, and FCA suits plants that already run their own freight. Paul quotes the preferred rule and the alternatives side by side.

How do biotech plants in Ghent and Leuven scale from clinical to commercial equipment?

Biotech plants in Ghent and Leuven scale up by moving from pilot and clinical-scale skids to commercial systems with larger vessels, automated cleaning and validated utilities. Paul Industries designs the commercial equipment to keep process parameters comparable with the clinical scale, builds it in the United States to EU GMP and Ph. Eur. requirements, and qualifies it at the Belgian site.

Can a Belgian team attend the factory acceptance test?

A Belgian team attends the factory acceptance test in the US shop or follows it by live video, and many attend integrated sequence tests in person while watching routine checks remotely. Brussels time sits six hours ahead of New York for most of the year, which puts remote witness sessions in the Belgian afternoon. Paul Industries shares data and photographs as each step closes.

How is heavy equipment moved from Antwerp to plants near Liege or in Limburg?

Heavy equipment moves from Antwerp to plants near Liege or in Limburg by barge on the Albert Canal where a quay sits close to the site, or on public roads with an abnormal-load permit and a surveyed itinerary, depending on dimensions and mass. Paul Industries checks the route during design and builds large systems as modules where the route sets a limit.

What service do Belgian plants receive after handover?

After handover, Belgian plants receive scheduled service visits from Paul Industries, remote troubleshooting from the drawings, control programs and test records Paul holds, and spare parts shipped from the United States. The spares list is sized for transatlantic lead times, and Paul supplies records for in-service inspections of pressure equipment and periodic AREI/RGIE electrical inspections.

What do pharma and biotech plants in Belgium expect from a US equipment supplier?

Belgian pharma and biotech plants expect a US equipment supplier to deliver EU-compliant equipment, CE marked where the directives require it, with documentation in French or Dutch, GMP-ready validation records and support on site through qualification. Paul Industries works to those expectations as standard on every Belgian project, from the code review to the turnover file.

Planning a process system for a plant in Belgium?

Describe the process duty, the Belgian site and its supply system, the documentation language and the Incoterm you want, and Paul Industries returns the Belgian code basis, a delivery plan through Antwerp-Bruges and a budget range. Call 201-450-8280 or request a quote.