Mechanical insulation is the engineered layer of insulation, vapor retarder and jacket on piping, tanks, vessels, equipment and ductwork, and Paul Industries specifies, supplies, installs, jackets, repairs and replaces it nationwide. Crews take it on as part of a piping job or as a standalone scope in all 50 states, with same-day emergency response when a failed jacket, soaked section or leak needs attention now. This page is written for plant engineers, facility managers and general contractors: what the system does, how materials differ, how thick it has to be, where corrosion starts, and how to judge the crew doing the work.

What is mechanical insulation?

It is a complete thermal system applied to mechanical services to control heat flow, surface temperature, condensation and noise. The material is only one part: a working system also includes fitting covers, supports that carry the load without crushing the insulation, a vapor retarder on cold lines, and a jacket that keeps weather, washdown and abrasion out. The term separates this work from the walls and roofs of a building envelope. The National Insulation Association groups service temperatures into low (-100 to 60 F), medium (61 to 600 F) and high (601 to 1,500 F) bands, which is a useful first filter when reading a specification. Industrial mechanical insulation on process lines can span all three bands within a single plant, while commercial HVAC work sits mostly in the low and medium bands.

Job the system doesWhat it controlsTypical design basis
EnergyHeat loss from hot lines and heat gain into cold onesASHRAE 90.1 or IECC minimums, ASTM C680 calculations; well-designed systems cut loss or gain by 90 to 98 percent
CondensationKeeps the outer surface above the dew point of the surrounding airDesign ambient and relative humidity; 90 percent is a common basis for outdoor or vented spaces
Freeze protectionSlows cooling of still or slow-moving waterHours to freezing at design low; heat tracing where insulation and flow are insufficient
Personnel protectionTouch temperature of hot surfaces140 F outer surface as standard industry practice, evaluated with ASTM C1055 and C1057
Process temperatureTemperature drop along a line or in a vesselAllowable drop between source and point of use
NoiseSound breaking out of pipe and duct wallsAbsorptive insulation with a mass-filled jacket; insertion loss measured to ASTM E1222
Fire and smokeSurface burning and rated assembliesASTM E84 limits, commonly 25/50 on ducts and 25/450 on pipe; ASTM E119 or E1529 for rated assemblies

The energy case is easy to size. Department of Energy tables put 100 feet of bare 4-inch steam line at 150 psig at about 850 million Btu a year, on the basis of horizontal steel pipe in still 75 F air running all year. A 90 percent reduction saves about 765 million Btu, or roughly $7,650 a year at the $8 per million Btu fuel price and 80 percent boiler efficiency used in the DOE example. Numbers like these are why insulation surveys belong in any energy-saving program.

Types of industrial pipe insulation

The main options are mineral wool, fiberglass, calcium silicate, cellular glass, elastomeric foam, polyisocyanurate, phenolic foam and flexible aerogel, and they differ mainly in temperature limit, moisture behavior, strength and cost. The temperature figures below are the limits published for each ASTM material specification; individual products may be narrower, so the data sheet for the exact grade is what gets checked.

MaterialASTM specPublished service rangeWhere it fitsWatch for
Mineral woolC547 (pipe), C553, C612Pipe Types II and III to 1,200 F, Type V to 1,400 FSteam, hot process lines, fire-exposed areas, acoustic wrapsAbsorbs water if the jacket fails; compresses under foot traffic
FiberglassC547 Type ITo 850 FHot water, low-pressure steam, indoor chilled water with a sealed retarderRelies entirely on its facing when run cold
Calcium silicateC53380 to 1,200 F (Types I and IA), to 1,700 F (Type II)High-temperature piping and equipment where the surface takes loads or knocksRigid, heavier, and needs a sound jacket against water
Cellular glassC552-450 to 800 FCryogenic, below-ambient and wet-location service; load-bearing supportsBrittle; joints must be sealed and sections protected from impact
Elastomeric foamC534-297 to 220 F (Grade 1), to 350 F (Grade 2), to 250 F (Grade 3)Chilled water, glycol, refrigerant lines, small bore, tight routingOutdoors it needs a weatherable jacket or coating
PolyisocyanurateC591-70 to 300 F (Grade 1), -297 to 300 F (Grade 2)Cold process lines and large-bore chilled water where thickness mattersDepends on a continuous vapor retarder
Phenolic foamC1126-290 to 257 FBelow-ambient lines and HVAC mains needing low conductivityMoisture raises conductivity quickly; keep the retarder intact
Flexible aerogelC1728-321 to 1,200 FTight clearances, retrofits, congested pipe racksHigher material cost; below-ambient use still calls for a retarder

Industrial insulation types fall into fibrous products such as mineral wool and fiberglass, cellular products such as cellular glass and the foams, and granular products such as calcium silicate. That split predicts behavior in the field: fibrous materials let vapor pass and are light and forgiving; cellular glass is impermeable; granular block takes load. Choosing an industrial insulation material starts with the highest and lowest temperature the line will ever see, including steam-out, sterilization, regeneration and upset conditions, because a line that normally runs at 40 F may be steamed at 250 F twice a year.

Tanks, vessels and heat exchangers follow the same material logic with different hardware. Large flat or curved surfaces use board, block or blanket held by banding, studs or a support ring, and manways and nozzles get their own removable covers. Paul insulates process tanks and vessels of every kind, whoever built them, and fits covers on heat exchangers so that heads can come off for cleaning without destroying the insulation around them.

High temperature industrial insulation

This class of work means service above about 600 F, and it usually relies on calcium silicate, mineral wool or flexible aerogel, applied in more than one layer under a metal jacket. Layers are staggered so that no joint runs straight from the hot surface to the jacket. Hot pipe grows, so rigid systems get contraction joints packed with compressible fiber, and the outer layer is banded so it can move without opening gaps. Thickness on these lines is calculated twice, once for surface temperature and once for heat loss, and whichever demands more material governs.

Two field details catch owners out. Organic binders in some fibrous products burn off during first heat-up, releasing smoke and odor, so the first firing is planned and the space ventilated. Aluminum jacketing softens and melts in a serious fire, so stainless jacketing is chosen for fire-exposed areas and for corrosive atmospheres. Metal jackets also run hotter to the touch than their insulation thickness suggests because bright metal sheds heat poorly by radiation, which the surface temperature calculation has to account for.

Chilled water and steam pipe insulation differences

Steam insulation is built to keep heat in and to let any moisture dry outward, while chilled water insulation is built to keep humid air out, because vapor is constantly driven toward the cold pipe. That single difference changes material, joint details and how a failure shows up. Sizing, routing and pipe materials for those systems are covered on the chilled water systems and steam piping pages; the table below stays on the insulation itself.

ItemSteam and condensateChilled water and glycol
Direction of the problemHeat flows out; surface can burnHeat and water vapor flow in; surface can sweat
Usual materialsMineral wool, calcium silicate, fiberglass on lower pressures, aerogel in tight spotsElastomeric, cellular glass, polyisocyanurate, phenolic, faced fiberglass indoors
Thickness driverEnergy code, payback, 140 F touch limitDew point at design humidity, then energy code
Critical detailRemovable covers on valves and traps; contraction joints; drain-away of leaksUnbroken retarder, vapor stops, insulated hanger inserts
What failure looks likeHot spots on thermography, wet sections at leaking valvesDripping, stained ceilings, ice on low-temperature glycol lines, rust at hangers
Corrosion exposureLines cycling through the wet range, condensate returns, idle standby linesContinuous if the retarder is breached

Glycol loops running below freezing raise the stakes further: on glycol cooling systems and process chiller loops a small breach grows into an ice collar that lifts the jacket and spreads the damage along the line. Plants comparing steam pipe insulation contractors should ask how leaks will be kept from soaking new work, and plants comparing chilled water pipe insulation contractors should ask to see the hanger and valve details before the first section goes on. Data halls add their own constraint, since a drip above a white space is an outage risk; Paul carries the same cold-service details through data center cooling systems.

Jacketing and vapor retarders

A jacket protects insulation from weather, impact and washdown, while a vapor retarder limits water vapor reaching a cold pipe, and a below-ambient line needs both functions covered. The lower the operating temperature, the more critical the retarder becomes. Flexible retarders under ASTM C1136 are intended for surface temperatures of -20 to 150 F, and reported permeance runs from about 0.02 perm for films down to near zero for multi-ply laminates, with vapor-retarder mastics ranging from 0.5 perm to below 0.01.

FinishReferenceGood forLimits to plan around
Aluminum jacketASTM C1729Outdoor and general plant piping at moderate costChemical attack in some atmospheres; low fire resistance
Stainless jacketASTM C1767Fire-exposed, corrosive and high-abuse areasHigher cost; hot to the touch
PVC jacket and fitting coversASTM C921Indoor piping, washdown areas, USDA and FDA-regulated plantsTemperature and sunlight limits by product
Laminated facings (ASJ, FSK)ASTM C1136Concealed and indoor pipe, and as a retarder under another jacketEasily torn; seams and butt strips must be sealed
Mastic and reinforcing fabricASTM C647 guideIrregular shapes, field repairs, weather barriersCure time, thickness control, permeance varies by type

Metal jackets are usually ordered with a factory moisture barrier on the inner face to reduce crevice and galvanic attack. Laps are placed to shed water, with circumferential laps facing downhill and longitudinal seams on the lower side of horizontal runs. Every penetration through a jacket is flashed or sealed, since a single open seam at the top of a line will feed water to everything beneath it.

Removable blankets for valves and flanges

Removable blankets are sewn or fitted insulating pads that cover valves, flanges and other irregular parts so they can be opened for maintenance and closed again without new material. DOE describes pads with noncombustible inner and outer covers, held by laced wire or buckled straps, and designed for temperatures up to 1,600 F; some include acoustic barriers. Its tables credit an insulating cover on a 6-inch valve at 300 F with saving about 3,300 Btu per hour, and that kind of gain repeats at every uninsulated valve in a plant. Paul measures, supplies and fits them, tags each pad to its location, and returns them to the right valve after outages.

Insulation thickness and energy codes

ASHRAE 90.1 sets minimum pipe insulation thickness in two tables, Table 6.8.3-1 for heating and hot-water systems and Table 6.8.3-2 for cooling systems, by fluid operating temperature and pipe size. Thickness rises with temperature difference and pipe diameter. As examples from the 2010 edition, steam above 350 F called for 5 inches on pipe 1 inch and larger, hydronic hot water for 2 inches at 1-1/2 inches and larger, and chilled water at 40 to 60 F for 1 inch at all sizes. Later editions may revise these figures and states adopt different editions, so the governing table is always confirmed for the project address. The IECC carries its own commercial table, and many states amend either document.

Those numbers assume a stated conductivity range. A material outside it is corrected with the standard’s formula, T = r[(1 + t/r)^(K/k) – 1], where r is the pipe’s actual outside radius, t is the table thickness, K is the alternate material’s conductivity and k is the upper value of the table range. In practice this is why a 4-inch chilled line in cellular glass may need 1-1/2 inches where fiberglass would need 1.

Code minimums are a floor. The chilled water value above was set for energy and takes no account of condensation, which may need much more: the NIA design guide shows a 40 F surface in an 80 F room needing about 0.1 inch at 30 percent relative humidity and about 6 inches at 95 percent. Thickness is therefore run separately for each job the insulation does, and the largest answer wins. ASTM C680 is the recognized heat-transfer calculation behind those runs, and economic thickness is best treated as a minimum. Actual pipe insulation dimensions are set by ASTM C585, so nominal thickness and pipe size have to be matched to real inside and outside diameters when ordering.

When is pipe insulation required?

Pipe insulation is required wherever an adopted energy code, the project specification or a safety, condensation, freeze or process limit calls for it, which in practice covers most hot and cold mechanical piping. The first test is the energy code, which applies to building heating, hot-water and cooling piping. DOE’s working rule for industrial plants is broader: anything over 120 F should be covered. Exceptions vary by jurisdiction; factory piping inside rated room fan coils and unit ventilators is a common one, and California’s Title 24 exempts fluid in a 60 to 105 F band.

Beyond the code book, pipe insulation requirements come from what happens if the line stays bare. A hot line within reach of a walkway needs burn protection even when the code ignores it. A cold line over electrical gear or finished ceilings needs condensation control at any temperature below the room dew point. Outdoor water lines need a freeze plan: insulation alone buys limited time, since a 2-inch line with 1 inch of insulation and no flow at -18 F reaches freezing in about 1.1 hours. Where that is too short, Paul pairs the insulation with heat tracing sized to replace the heat lost through it.

Corrosion under insulation: causes, screening and coatings

Corrosion under insulation happens when water gets into the system and stays against the metal, and it is hard to catch because the jacket hides it. Carbon steel is generally described as susceptible from about 10 to 350 F, and austenitic stainless from about 120 to 350 F, where chlorides and tensile stress can produce external stress corrosion cracking. Lines that cycle in and out of those ranges and lines left idle are often worse than lines running steadily hot, because they keep rewetting.

Prevention sits in four places. Coat the steel first: under insulation, the coating is the real barrier, and immersion-grade systems are selected by temperature, such as phenolic epoxies to about 300 F and novolac epoxies to about 400 F. Keep chlorides off stainless by specifying insulation that meets ASTM C795. Keep water out with sealed penetrations and well-lapped jackets. Then inspect on a plan: API RP 583 and AMPP SP0198, formerly a NACE standard, describe ranking lines by likelihood and consequence.

Screening narrows the search before anything is stripped. Infrared thermography and neutron backscatter find wet insulation; radiography and pulsed eddy current estimate wall loss through it; visual examination and ultrasonic thickness readings then confirm the finding at small windows or removed sections. Hygienic stainless lines have their own routine, set out in the sanitary tubing inspection schedule. Moisture also wrecks performance on its own: one published laboratory study found fiberglass conductivity rising as much as threefold at about 12 percent moisture by volume.

Mechanical insulation installation sequence

Insulation goes on last, after pressure testing and coating, because every step before it is far more expensive to redo once the pipe is covered. Paul runs the sequence below on new work and on replacement sections alike, using the MICA National Commercial and Industrial Insulation Standards as a common reference for details where a specification is silent.

StepWorkCheck before moving on
1. SpecificationSet material, thickness, jacket and details per service classTemperatures include upset and cleaning conditions
2. ReleaseConfirm pipe, welds and hydrostatic testing are completeTest records signed; joints are not covered early
3. SurfaceClean, dry, coated where specified; heat tracing installed and testedCoating cure and tracing continuity recorded
4. SupportsFit load-bearing inserts and saddles at hangers and guidesInsert length and density match shoe and pipe load
5. Pipe sectionsInstall sections tight, joints staggered, multiple layers offsetNo voids, compressed spots or open butt joints
6. FittingsFit preformed or mitered covers to ASTM C450 dimensions; removable pads at valvesStems, gauges, drains and tags stay accessible
7. RetarderSeal seams and laps on cold lines; install vapor stops at flanges, valves and terminationsUnbroken coverage, including every hanger
8. JacketApply jacket, bands and flashing with laps shedding waterSealed penetrations; no fasteners piercing a retarder
9. TurnoverIdentify lines, photograph details, hand over recordsWalkdown punch list closed; thermography on hot start-up where specified

Mechanical pipe insulation most often fails at the hanger, where a clamp sits directly on the pipe and bridges the thermal layer, or where soft insulation crushes under the load. Rigid inserts of sufficient density under a protective shield solve both. When Paul is also installing the process piping and plant utilities, shoes, hangers and clearances are laid out for the finished insulation diameter from the start, which avoids the familiar problem of lines routed too close together to wrap.

Insulation repair and shutdown coordination

Repair starts by fixing whatever wet the insulation, then removing every damaged section back to dry material, examining the metal, and rebuilding the system to the original specification. On older plants the first step is sampling: OSHA treats thermal system insulation installed before 1981 as presumed asbestos-containing until testing shows otherwise (29 CFR 1926.1101), so Paul has suspect material tested before anyone disturbs it. New insulation over an active leak fails quickly, and the causes are usually familiar: leaking valves, tube leaks and drips from equipment above. DOE also notes that insulation is frequently taken off during repairs and never put back, so bare sections accumulate over a plant’s life; a yearly walkdown under a preventive maintenance program catches them.

Most removal and replacement fits best inside an outage, when scaffolding is up and lines are cold. Paul works insulation into the same schedule as shutdown and turnaround services: strip ahead of inspection and hot work, hold the line open for coating and testing, then close it up before start-up so a cold line can’t sweat onto newly energized equipment. Hot lines can often be reinsulated while running, within the temperature limits of the materials and adhesives chosen and with burn protection for the crew.

Sanitary and cleanroom insulation requirements

Insulation in sanitary and cleanroom areas has to be smooth, sealed, cleanable and free of shed fibers, and on stainless lines it must also meet low-chloride limits. PVC jackets are widely used where USDA and FDA approval applies and frequent washdown is expected. Stainless jackets suit rooms cleaned with aggressive agents, provided seams are sealed so that wash water can’t get inside. In classified rooms, closed-cell or fully encapsulated products are favored over exposed fibrous materials, and melamine foam is used in some pharmaceutical, food-grade and clean room applications.

Hygienic piping also adds practical constraints. Insulation must leave clamp connections reachable and hold the tube’s slope, so supports are detailed with the finished diameter in mind. Hot purified water, water for injection and clean steam all run inside the stainless cracking range, so each batch of insulation should carry documentation showing it meets ASTM C795. Cleaning agents are checked against the jacket and sealant before selection, because disinfectants can attack some plastics and mastics.

How to choose among mechanical insulation contractors

The most useful test is whether the crew can show the details for your service conditions, cold or hot, before pricing the job, because thickness on paper means little if hangers and valves are done badly. The same questions apply to pipe insulation companies, mechanical insulation companies and larger industrial insulation companies alike.

AskWhat a strong answer includes
How was thickness chosen?Separate energy, condensation and burn calculations, with the design ambient stated
What goes on stainless?ASTM C795 material with documentation for each lot
How is the retarder kept continuous?Written details for hangers, valves, flanges and terminations
Who confirms the pipe is ready?A release step tied to test and coating records
How is corrosion handled on replacement?Metal examined, findings photographed, coating and repair planned in the same scope
What will be handed over?Material data, as-built notes, photographs and a pad schedule for valves
Can the outage be supported?Crew sizing, scaffold access and hold points built into the shutdown schedule

Pipe insulation contractors who also understand the system beneath the jacket spot problems an inspection misses, such as a guide about to tear a jacket or a line short of clearance. Keeping pipe and insulation under one industrial mechanical contractor also keeps hold points and schedule with one responsible party. Mechanical insulation work is usually priced from a takeoff of linear feet by size and thickness, with fittings, valves, access and jacket type driving most of the variation, so a detailed takeoff is the fairest way to compare bids.

Insulation scope from Paul Industries

Paul’s mechanical insulation services run from specification through closeout: surveys and thickness calculations, material supply, pipe, tank, vessel, equipment and duct insulation, jackets and retarders, removable pads, coating under insulation, thermography, corrosion repair, and replacement during outages or on running lines. Work is available in all 50 states with same-day emergency response, on hot and cold systems, for new construction and existing plants. To price a job, request a quote with your line list, service temperatures and the condition of what is there today.

Standards referenced: ASHRAE 90.1 · IECC · ASTM C533 · ASTM C547 · ASTM C552 · ASTM C534 · ASTM C591 · ASTM C1126 · ASTM C1728 · ASTM C795 · ASTM C1136 · ASTM C1729 · ASTM C1767 · ASTM C921 · ASTM C647 · ASTM C680 · ASTM C1055 · ASTM C1057 · ASTM C585 · ASTM C450 · ASTM E84 · API RP 583 · AMPP SP0198 · MICA National Commercial and Industrial Insulation Standards

Frequently asked questions

What does a mechanical insulation contractor do?

Takes off the systems to be covered, confirms material and thickness against the specification and code, then installs insulation, retarder, jacket and removable covers on pipe, ducts and equipment. On existing plants the work also includes stripping damaged sections, examining the metal below and rebuilding to the original design.

What is industrial insulation used for?

It keeps process and utility systems at the right temperature, reduces fuel and cooling costs, keeps workers from contacting hot surfaces, prevents sweating on cold lines, delays freezing and lowers noise. In most plants several of these goals apply on the same line, and the most demanding one sets the design.

How do I choose a pipe insulation company for an operating plant?

Ask for its approach to work around running equipment: hot-work rules, scaffold access, burn protection, how open sections are protected at the end of a shift, and how wet insulation or corrosion findings get reported during the job.

What should an industrial insulation company provide at turnover?

Material data sheets by line, thickness and jacket records, documentation of low-chloride material on stainless, photographs of key details, a schedule of removable pads and any findings about pipe condition, so maintenance crews can restore the system correctly later.

What systems do industrial pipe insulation contractors cover?

Plant piping and the equipment attached to it, including steam, condensate, chilled water, glycol, process, hot oil and utility lines, along with tanks and exchangers. Paul Industries does this work with its piping crews or as a standalone scope.

What do industrial insulation contractors need before starting?

A line list with sizes and temperatures, the insulation specification, access and permit rules, test release status, and any coating requirements. A walkdown then catches clearance problems, missing supports and uninsulated valves that drawings tend to omit.

Do piping insulation contractors handle tanks and ductwork too?

Paul covers both on the same job. Duct work uses wrap, board or liner chosen for condensation, noise and fire ratings, and tanks use board, block or blanket with banding and supports designed around nozzles and manways.

What is the difference between a pipe insulation contractor and a mechanical contractor?

The first title describes the work on the outside of the system, and the second usually covers the pipe and equipment themselves. Paul Industries does both, which means supports, clearances, test release and insulation are all planned together by one crew.

What do mechanical pipe insulation contractors check on a chilled line after installation?

Sealed longitudinal seams and butt joints, vapor stops at each termination, intact facing at every hanger, sound fitting covers and no fastener holes through the retarder. A warm humid day under load is the most revealing test, because any weak spot shows up as a damp patch.

What are pipe insulation services for existing buildings?

Typical jobs are replacing damaged or wet sections, covering bare valves and fittings, upgrading thickness during a retrofit, curing condensation problems above ceilings and restoring insulation removed for repairs. Most of it can be phased by zone so occupied areas stay in use.

How long does pipe insulation last?

Service life depends far more on keeping water out than on age. Well-jacketed insulation in a dry indoor space can last for much of a building's life, while outdoor or washdown systems depend on jacket and sealant upkeep, so periodic inspection is what decides replacement.

What is economic insulation thickness?

It is the thickness at which the cost of adding more material balances the value of the energy saved over the chosen study period, using the plant's fuel price, operating hours and installed labor rates. It often exceeds code minimums on hot lines running year-round.

What is a vapor stop in cold pipe insulation?

A sealed barrier bonding the insulation's retarder to the pipe surface at intervals and at terminations. It confines any breach to one section, so moisture entering at a damaged spot can't travel the length of the line.

Does stainless steel pipe need special insulation?

Yes. Stainless is insulated with material meeting ASTM C795, which limits leachable chlorides relative to inhibiting silicates and sodium, and its specification is checked lot by lot. Many owners also add a protective coating on warm lines and keep sealants and tapes under the same chloride control.

Should flanges and valves be insulated on steam lines?

Yes, in nearly all cases, using removable pads so the joints stay accessible. Valve bodies and flanged joints have a large surface area for their length, and leaving them bare gives up a share of what the pipe insulation saves. Flanges prone to leaking can be fitted with drained covers or inspection ports.

What temperature requires personnel protection insulation?

Plants commonly apply the 140 F outer surface limit to anything within reach of normal work, and DOE advises covering surfaces above 120 F. Where only touch protection is needed and heat loss is wanted, such as on some exhaust lines, standoff guards or cages can be used instead.

Can wet pipe insulation be dried and reused?

Closed-cell materials may recover after the source is fixed, but fibrous and block insulation that stayed wet usually has lost thickness or facing and is best replaced. Any wet section is also a reason to examine the pipe underneath before it is covered again.

Why do cold lines keep dripping after new insulation?

Usually the vapor retarder is broken somewhere upstream, often at a hanger, valve or termination, or thickness was set by the energy table instead of the room's dew point. Humidity higher than the design value is the other common cause, and a small increase can demand much more thickness.

Is removable insulation worth it on equipment opened often?

Yes. Exchanger heads, strainers, turbine casings and frequently serviced valves are the places where fixed insulation gets torn off and rarely returns, so a fitted pad usually repays itself by staying in place across repeated maintenance cycles.

Who installs mechanical insulation on industrial piping?

Paul Industries installs mechanical insulation on pipe, tanks, vessels, equipment and duct, on hot and cold systems, in running plants or during outages. The work starts with a survey and thickness calculation, then takes in jackets, vapor retarders, removable pads for valves and flanges, coating under insulation, thermography and corrosion repair.

How much does mechanical insulation cost?

Mechanical insulation pricing follows the line list rather than a flat rate per foot. The real drivers are pipe size and required thickness, the material chosen for the service temperature, the jacket or vapor retarder, the count of valves, flanges and fittings that need cut or removable pieces, and access, including scaffold and tear-out of wet or damaged insulation.