Paul Industries is a biofuels plant contractor that designs, fabricates, installs, starts up, repairs and maintains the tanks, piping, steam, cooling and gas-handling systems at ethanol, biodiesel, renewable diesel, biogas and renewable natural gas plants. Fermenters and digesters, distillation and evaporator piping, boilers, cooling towers, pumps and biogas upgrading skids are built to ASME and API codes and documented for process safety. Paul Industries works on new plants, expansions, shutdowns and routine maintenance, with supply-only, design-build and complete installation routes.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Coverage Every US state, plus biofuel plants abroad
US ethanol plants 189 plants, about 18.4 billion gallons a year of capacity (EIA, January 2026)
Farm digesters About 400 operating on US livestock farms (EPA AgSTAR, June 2024)
Pipeline RNG Upgraded to 90% methane or more; injected gas usually 96 to 98% (EPA)
Reviewed November 2026

What does a biofuels plant contractor build and maintain?

A biofuels plant contractor builds and maintains the mechanical side of plants that turn crops, fats, manure, food waste and landfill gas into fuel: tanks and vessels, process and utility piping, heat exchangers, pumps, boilers, cooling towers, gas conditioning skids and the structural steel that carries them. Process licensors and ethanol plant manufacturers set the process design; the mechanical contractor makes it real on the site and keeps it running for the next twenty years.

Each plant type leans on different equipment. A corn ethanol plant is a fermentation and distillation plant with a large steam and cooling load. A biodiesel plant is a chemical reaction plant handling methanol. A biogas plant is a set of heated, mixed tanks producing a wet, corrosive gas, and an RNG plant cleans that gas until it can enter a natural gas pipeline. The table maps the systems Paul Industries delivers to each.

Biofuel and RNG plant types and the mechanical systems Paul Industries delivers
Plant typeCore processMechanical systems
Dry-grind ethanolMilling, cooking, fermentation, distillation, dehydrationSlurry and cook tanks, fermenters, beer well, distillation and evaporator piping, boilers, cooling tower, CIP, tank farm
BiodieselTransesterification of fats and oils with methanolReactors, settling and wash tanks, methanol recovery, glycerin handling, heated feedstock storage
Renewable dieselFeedstock pretreatment and hydrotreatingPretreatment tanks and piping, exchangers, utility systems, tank farm and loading
Anaerobic digesterHeated digestion of manure, food waste or sludgeDigester tanks, mixing, heating loops and boilers, gas collection piping, flares, digestate handling
RNG upgradingRemoving water, H2S, CO2 and other contaminants from biogasGas conditioning and upgrading skids, compressors, gas piping, metering and pipeline interconnect

Who builds and repairs process systems for ethanol, biodiesel and RNG facilities?

Paul Industries builds and repairs process systems for ethanol, biodiesel, renewable diesel, biogas and RNG facilities, from a single fermenter repair to a full mechanical package for a plant expansion. Owners, developers and EPC teams bring Paul Industries a process design, an equipment list or a problem on a running plant, and get back fabricated tanks and spools, installed and tested systems, or a planned repair with the records attached.

Ethanol plant contractors and ethanol plant builders are measured by uptime after the job, because a plant that grinds corn around the clock loses revenue every hour it is down. Paul Industries plans new tie-ins, ethanol plant expansion work and debottlenecking projects to fit scheduled outages, prefabricates spools and skids, and tests systems as they close so startup is short. The process piping and tank fabrication pages describe the methods behind that work in general terms.

How does an ethanol plant work? The corn ethanol plant process, step by step

A dry-grind corn ethanol plant works by milling corn, cooking the starch into a mash, converting it to sugar with enzymes, fermenting that sugar with yeast, and distilling and drying the alcohol into fuel ethanol. According to the OSHA Technical Manual, liquefaction runs at about 180 to 220 degrees Fahrenheit with alpha-amylase, glucoamylase is added as the mash cools to about 86 degrees, and fermentation produces a beer of about 8 to 12 percent ethanol by weight. Distillation brings the alcohol to about 190 proof and molecular sieves dry it to over 99 percent, before about 2 percent denaturant is added.

The ethanol plant process also makes co-products that carry their own equipment: distillers grains from the stillage, corn distillers oil, and carbon dioxide from fermentation. Argonne National Laboratory reports yields of about 2.8 to 2.9 gallons of denatured ethanol per bushel, and a 2019 Argonne survey found plants using about 2.65 gallons of fresh water per gallon of ethanol. The EIA counted 189 fuel ethanol plants in the United States with about 18.4 billion gallons a year of capacity on January 1, 2026, and Iowa had the most capacity in its 2025 survey.

Dry-grind ethanol process areas and the mechanical work in each
Process areaTypical conditionsMechanical work Paul Industries performs
Milling and slurryHammer mills, corn flour mixed with water and recycled process waterSlurry tank and piping, conveyors and dust control tie-ins, pump replacement
Cooking and liquefactionAbout 180 to 220 F with alpha-amylaseJet cooker and steam piping, cook tubes, liquefaction tanks, exchangers
FermentationYeast and glucoamylase, about 86 F at the start, roughly 40 to 72 hoursFermenters, coolers and recirculation piping, agitators, CO2 scrubber, CIP
Distillation and dehydrationBeer columns to about 190 proof, molecular sieves to over 99%Column and reboiler piping, condensers, sieve beds and valves, steam and condensate
Stillage and co-productsCentrifuges, evaporators, dryers, oil recoveryEvaporator piping and cleaning, tank work, dryer ductwork tie-ins
Storage and loadoutEthanol, denaturant, flash point of ethanol 55 FAPI 650 tank work, transfer piping, bonding and grounding, loading arms

Fermentation tank fabrication, repair and cleaning

A fermentation tank in an ethanol plant is a large agitated vessel that runs in batches, and the OSHA Technical Manual describes fermenters typically working in groups of three, with one filling, one fermenting and one emptying. Each one carries agitators, recirculation coolers to remove the heat of fermentation, CIP spray devices, vents to a CO2 scrubber and level and temperature instruments. Bacterial contamination is one of the costs a fermenter can impose on a plant, so drainable piping, cleanable internals and working CIP coverage matter as much as wall thickness.

Paul Industries fabricates new fermenters and beer wells, adds nozzles and manways, repairs corroded shells and floors, rebuilds coolers and replaces recirculation piping and valves. Fermenter cleaning, scale removal and inspection openings are planned with hydro blasting and industrial tank cleaning, and the entry follows permit-required confined space rules under OSHA 29 CFR 1910.146, because a fermenter that has held CO2 can hold a deadly atmosphere long after it is drained. Brewery and distillery fermenters, which share the principles at a smaller scale, are covered on the distilling and brewing page.

Ethanol plant maintenance and ethanol plant shutdown planning

Ethanol plant maintenance is organized around planned shutdowns, with running repairs in between, because evaporators, distillation columns, exchangers and fermenters foul steadily and most cleaning and inspection needs the system open. An ethanol plant shutdown typically carries hydroblasting of evaporators and exchangers, tank and column inspections, valve and pump replacement, boiler and cooling tower work, and the tie-ins for any expansion waiting for a window.

The ethanol plant boiler is a major piece of pressure equipment on site, and its construction is governed by ASME Section I, with repairs and alterations under the National Board Inspection Code. Paul Industries repairs boilers, replaces tubes and refractory interfaces, rebuilds burners and economizer piping, and services steam and condensate systems, as described on boiler repair and steam piping. The ethanol plant cooling tower carries the condenser and fermentation cooling load and sees heavy fouling, so Paul Industries rebuilds fill, drift eliminators, fans and gearboxes during the same window, as set out on cooling tower repair.

Process safety shapes the plan. OSHA’s Process Safety Management standard covers processes holding 10,000 pounds or more of a flammable liquid, and the OSHA Technical Manual notes that ethanol in process vessels counts toward that threshold, while atmospheric storage tanks below the boiling point fall under an exemption. Ethanol has a flash point of about 55 degrees Fahrenheit, which makes it an NFPA Class IB flammable liquid, so hot work, line breaks and tank entries are permitted and isolated with care. Paul Industries carries that planning into every shutdown, along with shutdown and turnaround services methods for sequencing the work.

Biodiesel plant and renewable diesel plant work

A biodiesel plant makes fuel by transesterification, reacting fats and oils with methanol and a catalyst, usually sodium or potassium hydroxide, to produce methyl esters and a glycerin co-product. The plant needs heated feedstock tanks for oils and animal fats, reactors and settling tanks, methanol recovery and storage, glycerin handling, water wash or dry polishing, and finished fuel storage tested against ASTM D6751. Methanol is a flammable liquid that changes how the plant is laid out, vented and grounded.

A renewable diesel plant takes a different route: feedstock pretreatment followed by hydrotreating, producing a fuel that meets the same ASTM D975 specification as petroleum diesel. EIA data put US renewable diesel and other biofuels capacity at about 4.97 billion gallons a year at 19 plants on January 1, 2026, against about 1.97 billion gallons a year at 45 biodiesel plants; renewable diesel capacity overtook biodiesel in 2023. Several large renewable diesel plants are converted petroleum refineries, where the work looks like the projects on the oil and gas page.

For biodiesel plant construction or a biodiesel plant setup on an existing industrial site, Paul Industries fabricates and installs tanks, reactors and piping to the process package that biodiesel plant manufacturers and licensors provide, and adds the utilities, heat tracing and controls around them. For running plants, Paul Industries repairs heat exchangers, replaces corroded piping and keeps feedstock heating and transfer systems working through winter.

Biogas plant and anaerobic digester facility construction

A biogas plant is a facility that feeds organic material such as manure, food waste or wastewater sludge into sealed, heated tanks where bacteria break it down without oxygen, producing a gas that is mostly methane and carbon dioxide and a liquid digestate. An anaerobic digester facility is the same thing named by its main equipment. The American Biogas Council counted 2,585 biogas systems operating in the United States at the end of 2025, at wastewater plants, farms, landfills and stand-alone food waste sites, and EPA AgSTAR counted about 400 digesters on livestock farms as of June 2024, most of them on dairies.

Biogas plant construction is heavy mechanical and civil work: the digester tank itself, gas-tight covers or roofs, mixing systems, heating loops with boilers or engine heat recovery, gas collection and condensate piping, flares, pumps for feed and digestate, and the controls that tie them together. Paul Industries carries the anaerobic digester construction scope from tank and piping fabrication through installation, pressure and leak testing and startup, and provides anaerobic digester services afterward: heat exchanger cleaning, pump and mixer repair, gas piping repairs and condensate trap maintenance. Biogas plant manufacturing of tanks, skids and piping spools is done before the site work starts, so field time is shorter.

How does an anaerobic digester work?

Feedstock is pumped into a sealed tank kept at a steady temperature, where several groups of bacteria work in sequence: some break complex material into sugars and fatty acids, others convert those to acetic acid, and methane-forming bacteria turn that into methane and carbon dioxide. EPA AgSTAR gives mesophilic operation as about 86 to 104 degrees Fahrenheit and thermophilic as about 122 to 140 degrees. The material stays in the tank for its retention time, then leaves as digestate while gas is drawn off the top. An industrial biogas plant treating food or beverage waste works the same way, with feedstock receiving and depackaging added at the front.

Anaerobic digester types compared (EPA AgSTAR and Kansas State University data)
Digester typeFeed solidsRetention timeTypical use
Covered lagoonAbout 0.5 to 3%About 40 to 60 daysFlushed manure in warmer climates; unheated
Complete mixAbout 3 to 10%15 days or moreDairy and swine manure, food waste co-digestion; heated and mixed
Plug flowAbout 11 to 13%15 days or moreScraped dairy manure; long heated channel with little mixing

The anaerobic digester types in the table set very different mechanical scopes. A complete mix anaerobic digester is a heated, mixed tank, usually concrete or welded or bolted steel, with mixers, heat exchangers and a gas-holding cover. A plug flow anaerobic digester is a long, heated channel fed with thick scraped manure, where the heating pipe runs along the walls. Covered lagoons carry little mechanical equipment but need a very large gas collection cover. Choosing an anaerobic digester for dairy farms starts with how the barn handles manure, because that sets the solids content and therefore the digester technology.

Anaerobic digester design and site selection for biogas plant projects

Anaerobic digester design starts with the feedstock: its volume, solids content and variability, and any contaminants such as sand in dairy manure or packaging in food waste. The design of anaerobic digester heating and mixing then follows from retention time, temperature and tank shape, and the gas system is sized for peak production with condensate removal at every low point. An anaerobic digester tank needs a foundation, insulation and a cover rated for gas pressure and snow load, and its heating piping must be reachable for maintenance.

Site selection for biogas plant projects weighs feedstock haul distance, distance to a gas pipeline or power interconnect, room for digestate storage and setbacks, access for trucks, and the permits the site will need. Choosing an anaerobic digestion biogas plant site near an existing dairy, food plant or wastewater plant reduces both feedstock transport and the length of new gas line. Paul Industries reviews layouts at this stage so the mechanical systems fit the site the developer chooses, and anaerobic digester technology choices are matched to the equipment Paul Industries will install.

RNG plant construction: biogas upgrading to biomethane and pipeline injection

An RNG plant takes raw biogas, which the EPA describes as roughly 45 to 75 percent methane with the rest mostly carbon dioxide plus water vapor and hydrogen sulfide, and cleans it into renewable natural gas of at least 90 percent methane, usually 96 to 98 percent for pipeline injection. Biogas upgrading to biomethane runs in stages: moisture removal, hydrogen sulfide removal, siloxane removal for landfill and wastewater gas, carbon dioxide removal, then compression, quality analysis and metering at the pipeline interconnect.

The American Biogas Council counted 659 biogas facilities upgrading to RNG in December 2025, up from 217 in 2020. Every RNG facility is a gas processing plant in miniature, and an RNG facility construction scope covers gas conditioning skids, compressors, the biogas upgrading system itself, interconnecting piping, flares, controls and the pipeline tie-in. Paul Industries sets and pipes the biogas upgrading equipment, fabricates the gas and condensate piping, installs compressors and their cooling, and tests the systems before gas flows. Pipeline interconnects and any line the operator regulates fall under federal gas pipeline safety rules in 49 CFR Part 192, alongside the utility’s gas quality tariff.

Biogas upgrading technologies and methane recovery (EPA LMOP, 2024)
Biogas upgrading technologyHow it removes CO2Methane recoveryMechanical scope
Membrane separation, single passPressurized gas passes membranes that let CO2 through faster than methaneAbout 65 to 80%Compressors, membrane skids, tail gas piping to a flare or oxidizer
Membrane separation, multi-passSeveral membrane stages with recycleAbout 96 to 99%Added stages, recycle compression, more interstage piping
Pressure swing adsorptionAdsorbent beds hold CO2 under pressure and release it when depressurizedAbout 95 to 98%Vessel trains, switching valves, compressors, tail gas handling
Amine scrubbingA chemical solvent absorbs CO2 and is regenerated with heatOver 99%Absorber and stripper columns, reboiler heat, solvent pumps and piping
Water scrubbingWater absorbs CO2 under pressure and is regeneratedOver 99%Columns, water recirculation pumps, compression, drying

Biogas upgrading technologies differ in power use, heat demand, methane slip and maintenance, so the choice affects the mechanical scope as much as the gas quality. Landfill gas often needs nitrogen and oxygen removal as well, by cryogenic distillation, pressure swing adsorption or membranes. A renewable natural gas plant built at a dairy cluster, a landfill or a wastewater plant shares the same upgrading sequence; what differs is the contaminants in the raw gas and the distance to the pipeline. Paul Industries installs each renewable natural gas facility to the technology supplier’s process package and the pipeline operator’s requirements.

Codes and standards for ethanol, biodiesel, biogas and RNG plants

Ethanol, biodiesel, biogas and RNG plants share a set of safety codes and fuel standards that decide how mechanical work is designed, tested and documented. OSHA PSM at 29 CFR 1910.119 covers processes with 10,000 pounds or more of flammable liquid or gas, and OSHA has explained that tanks used for mixing, blending, heating or filtration are process tanks rather than exempt storage. OSHA 29 CFR 1910.106 and NFPA 30 cover flammable liquid storage and handling, and 29 CFR 1910.146 covers entry into tanks and digesters.

ASME B31.3 governs process piping, ASME Section I governs boilers, ASME Section VIII governs pressure vessels such as adsorber beds and receivers, and API 650 and API 653 cover welded atmospheric storage tanks and their inspection. NFPA 820 covers fire protection at wastewater treatment plants, including their digesters, and 49 CFR Part 192 covers gas pipelines. On the fuel side, biodiesel blend stock meets ASTM D6751, renewable diesel meets ASTM D975, and the EPA Renewable Fuel Standard assigns RIN codes: D6 for conventional corn starch ethanol, D4 for biomass-based diesel, D3 for RNG from landfills, wastewater digesters and farm digesters, and D5 for biogas from other waste digesters.

How much does an ethanol plant cost, and what drives the price of biogas plant projects?

Ethanol plant cost is usually expressed per gallon of annual capacity. A March 2026 farmdoc daily analysis at the University of Illinois models a representative 100 million gallon a year Iowa dry mill at $2.11 per gallon of annual capacity, a figure from an Iowa State model of a plant built in 2007, so current ethanol plant construction cost runs higher with inflation and site conditions. Expansions and retrofits are priced by scope rather than by gallon: the tanks, piping, utilities and shutdown time each project needs.

The cost of anaerobic digester projects varies with herd size and digester type. A Kansas State University review of EPA AgSTAR data put dairy digester installations at about $200,000 to $2,000,000, with plug flow systems ranging from about $180 per cow at a 10,000-cow dairy to $1,200 per cow at a 170-cow dairy, complete mix systems at about $500 to $2,600 per cow, and a dairy median of about $550 per head. For upgrading, EPA’s 2024 RNG guide cites about $7 per MMBtu for very large projects to $25 per MMBtu for small ones, and California pipeline interconnections averaging $1.5 million to $3 million per site. Those figures date from the studies named. For current work, Paul Industries prices the mechanical package against similar recent scope first, then commits to a fixed number when the process design and site layout are settled.

Biofuel and RNG plants from Kilmarnock, Virginia to plants abroad

Paul Industries is headquartered at 256 Shore Drive in Kilmarnock, Virginia, and takes biofuel and RNG plant work along the East Coast, across all 50 states and at plants outside the United States. Most US ethanol capacity sits in the Corn Belt, led by Iowa, while the East Coast fuel region had two ethanol plants in the EIA’s 2026 count, in New York and Pennsylvania. Dairy digesters operate in Pennsylvania, New York and Vermont, and landfill and wastewater RNG projects run from New England to the Carolinas.

Abroad, Brazil’s Center-South produced about 35 billion liters of ethanol in the 2024/25 harvest, and Germany counted more than 9,600 biogas and biomethane plants at the end of 2025. Overseas projects are built to ASME and API codes, or to national codes the owner names, with skids and spools shop-built and tested before export; the international page describes that work. The chemical manufacturing hub covers related tank and acid piping work, and every sector Paul Industries serves is listed on the industries page.

Ethanol, biodiesel and RNG plant work from Paul Industries

As a single contractor, Paul Industries designs, fabricates, supplies, installs, tests, starts up, services, repairs and maintains fermenters, digesters, process and gas piping, boilers, cooling towers, pumps, exchangers and biogas upgrading systems as a biofuels plant contractor for ethanol, biodiesel, renewable diesel, biogas and RNG plants. Choose supply-only tanks, spools and skids, a design-build package, or complete installation with startup and turnover records. Ethanol plant automation and controls for skids and packaged systems can be added to the same contract. Send the process package, equipment list or work list and the outage window, and request a quote.

Standards referenced: OSHA Process Safety Management, 29 CFR 1910.119 · OSHA 29 CFR 1910.106 flammable liquids · OSHA 29 CFR 1910.146 permit-required confined spaces · NFPA 30 · NFPA 820 · ASME B31.3 Process Piping · ASME Section I · ASME Section VIII · National Board Inspection Code · API 650 · API 653 · 49 CFR Part 192 · EPA Renewable Fuel Standard · ASTM D6751 · ASTM D975

Frequently asked questions

Who builds anaerobic digesters and RNG upgrading plants?

Paul Industries builds anaerobic digesters and RNG upgrading plants, fabricating and installing digester tanks, heating and mixing systems, gas collection piping, flares, conditioning skids, compressors and the piping to the pipeline interconnect. The work follows the technology supplier’s process package and is pressure tested and documented before gas flows. Send the process flow diagram, site plan and schedule to scope the mechanical package.

Who does ethanol plant shutdown work and fermentation tank repair?

Paul Industries carries out ethanol plant shutdown work and fermentation tank repair: fermenter shell and floor repairs, nozzle additions, cooler and recirculation piping replacement, evaporator and exchanger hydroblasting, valve and pump replacement, boiler and cooling tower repairs and expansion tie-ins. Work is planned before the outage, with materials staged and permits ready, so the plant restarts on schedule.

How many ethanol plants are in the US?

The EIA counted 189 fuel ethanol plants in the United States on January 1, 2026, with about 18.4 billion gallons a year of nameplate capacity. A year earlier it counted 191 plants. Iowa had the most capacity in the EIA’s 2025 state survey, with 42 plants and about 5 billion gallons a year, followed by Nebraska.

How much water does an ethanol plant use?

A 2019 Argonne National Laboratory survey of dry-grind plants, using 2017 data, found an average of about 2.65 gallons of fresh water per gallon of ethanol, well below the levels of the early 2000s. Cooling tower condition, blowdown control and condensate recovery are among the levers plants use to bring that figure down further.

Are ethanol plants safe?

Ethanol plants handle a flammable liquid with a flash point of about 55 degrees Fahrenheit, grain dust and carbon dioxide from fermentation, so safety depends on design and procedures. OSHA’s process safety management standard applies to ethanol process units above 10,000 pounds, and tank entry is permit-required confined space work. Paul Industries plans hot work, line breaks and entries to the plant’s permits on every job.

How is biogas upgraded to RNG?

Biogas is upgraded in stages: water is removed, hydrogen sulfide is scrubbed or adsorbed, siloxanes are removed where present, and carbon dioxide is separated by membranes, pressure swing adsorption, amine scrubbing or water scrubbing. Landfill gas may also need nitrogen and oxygen removal. The product, at least 90 percent methane and usually 96 to 98 percent for pipeline gas, is compressed, analyzed and metered into the pipeline.

Is biogas the same as renewable natural gas?

Biogas is the raw gas from a digester or landfill, roughly 45 to 75 percent methane with carbon dioxide, water vapor and hydrogen sulfide. Renewable natural gas, also called biomethane, is biogas that has been cleaned and upgraded until it can replace pipeline natural gas, at least 90 percent methane. An upgrading system is the equipment that turns one into the other.

How are anaerobic digesters heated?

Most digesters are heated with hot water loops, either through heat exchangers on recirculated sludge or through piping inside or along the tank walls, supplied by a boiler or by heat recovered from an engine running on the biogas. Mesophilic digesters run at about 86 to 104 degrees Fahrenheit. Paul Industries installs and repairs the boilers, exchangers, pumps and heating piping.

Can anaerobic digesters explode?

Biogas is flammable, so a digester, its gas piping and its gas storage need the protections any fuel gas system needs: pressure and vacuum relief, flame arresters where specified, flares for excess gas, gas detection, electrical classification and careful hot work control. Fire protection codes such as NFPA 820 cover digesters at wastewater plants. Paul Industries builds and tests gas systems to the design and code requirements.

What are anaerobic digesters made of?

Digester tanks are usually reinforced concrete or welded or bolted steel, with gas-tight covers made of steel, concrete or flexible membranes; covered lagoons use earthen basins with synthetic covers. Gas piping is commonly stainless steel or plastic suited to wet, corrosive gas, with condensate drains at low points. Material choice depends on hydrogen sulfide levels, temperature and the cover design.

How much does it cost to build a biodiesel plant?

Biodiesel plant cost depends on capacity, the feedstocks it must handle, pretreatment needs for high free fatty acid oils, methanol recovery, and whether existing tanks and utilities can be reused. Pretreatment and feedstock flexibility add the most cost. Paul Industries prices the mechanical package from the process design and equipment list, giving a budget range first and a firm price once the design is fixed.

What does an ethanol plant expansion involve mechanically?

An expansion usually adds fermenters, enlarges distillation, evaporation and drying capacity, and upgrades boilers, cooling towers, the tank farm and grain handling to match. Most tie-ins must be made during planned shutdowns. Paul Industries prefabricates tanks, spools and skids, installs new equipment while the plant runs, and makes the tie-ins in the outage window.

Does Paul Industries work on biogas and RNG projects in New York and Pennsylvania?

Yes. Paul Industries takes biogas and RNG project work in New York, Pennsylvania, Vermont and across the East Coast, including dairy digesters, food waste digesters and landfill and wastewater upgrading plants. The scope covers digester tanks, heating and gas piping, upgrading and compression skids and interconnect piping, tested and documented for the owner and the pipeline operator.

Does Paul Industries build biofuel plant systems in Virginia and the Carolinas?

Yes. Paul Industries is headquartered in Kilmarnock, Virginia, and takes biofuel and biogas plant work across Virginia, Maryland, Delaware and North and South Carolina, from fermenter and tank repairs to new digester and RNG mechanical packages. Food processing, poultry and dairy waste streams in the region feed digesters, and Paul Industries builds the tanks, piping and gas systems those projects need.

Can Paul Industries supply equipment for biofuel and biogas plants abroad?

Yes. Paul Industries builds and ships tanks, piping spools and skids for biofuel and biogas plants outside the United States, for example in Canada, Mexico and Brazil, to ASME and API codes or the national codes a buyer specifies. Building and testing packages in the shop before they ship keeps site work short. Send the specification, site location and schedule.

What is a biogas plant used for?

A biogas plant turns manure, food waste, crop residues or wastewater sludge into fuel gas and a nutrient-rich digestate. The gas is burned in boilers or engines for heat and power on site, flared, or upgraded into renewable natural gas for pipeline injection or vehicle fuel. Digestate is spread on fields or separated into liquids and solids for bedding or compost.

What maintenance does an anaerobic digester need?

Digesters need regular attention to mixers, feed and recirculation pumps, heat exchangers, which foul with sludge, gas piping condensate traps and pressure relief devices. Grit and sand build up over years and require periodic cleanout. Paul Industries repairs and services those systems on a schedule or after a failure, and plans cleanouts with gas-free procedures and confined space controls.

What ethanol plant automation work does Paul Industries handle?

Paul Industries installs and loops instruments, control valves and analyzers, and programs controllers for skids and packaged systems such as CIP, chemical feed and upgrading skids, then integrates them with the plant control system. Instrument work is done alongside the piping, so transmitters, sample points and valves are placed where they can be maintained.

What records does a biofuel or RNG plant receive after mechanical work?

The turnover package includes material test reports, welding procedure and welder qualification records, weld maps, examination reports, pressure test records, relief device data, as-built drawings and equipment manuals. Those records support the plant’s process safety program, insurance and boiler inspections, and the pipeline operator’s acceptance of an RNG interconnect.

Planning work at an ethanol, biodiesel, biogas or RNG plant?

Send the process package or equipment list, the site location and the shutdown or construction window. Call 201-450-8280 or request a quote.