Paul Industries performs data center commissioning in Maryland for cooling plants, liquid cooling loops, pumps and piping, carrying each system from factory witness tests through flushing, pressure testing, startup, functional testing and integrated systems testing, and assembling the records that county inspectors, the Chief Boiler Inspector and owners need at turnover. A Maryland job lines those tests up with the 2021 codes in the Maryland Building Performance Standards, state permits for generators and fuel, and annual energy benchmarking that starts the year after the building opens. As an East Coast contractor based at its Kilmarnock, Virginia headquarters on Shore Drive, Paul Industries commissions systems across Maryland, throughout the 50 states and overseas.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Building code 2021 I-codes under the MBPS; the 2024 update was withdrawn October 16, 2026
Energy code report 2021 IECC preliminary commissioning report due before final inspection
Benchmarking Maryland BEPS: buildings of 35,000 sq ft or more report by June 1 each year
Summer test window Wet bulb above 75 F only about 369 hours a year at BWI (NOAA)
Reviewed November 2026

Data center commissioning in Maryland: who needs to see what

Data center commissioning in Maryland answers to four audiences at once: the county or city building official who issues the certificate of occupancy, state agencies that permit pressure vessels, generators and fuel storage, the utility that energizes the service, and the owner who will run the hall for twenty years. Each wants different evidence, and a commissioning plan that ignores one of them stalls the schedule at the end, when the hall is built and waiting.

The building official looks for code inspections and, under the energy code, a preliminary commissioning report before final inspection. The Chief Boiler Inspector’s process covers pressure vessels on the plant. The Maryland Department of the Environment permits emergency generators and the fuel stored for them. The owner wants proof that the design intent was met, signed test records, and a baseline for the benchmarking that Maryland law now requires of large buildings. Paul Industries builds the data center commissioning plan around all four from the first meeting, so the test sequence produces each record as it goes.

What are the Maryland Building Performance Standards?

The Maryland Building Performance Standards (MBPS) are the state’s building code: the International Building Code, International Residential Code and International Energy Conservation Code as adopted and modified by the Department of Labor, then enforced by counties and municipalities. The current standards are the 2021 editions. Counties and municipalities must enforce each new MBPS within 12 months of state implementation; Harford County, for example, set May 29, 2024 as the effective date of its 2021 codes.

The state began moving to the 2024 editions in 2026. The proposal was published in the Maryland Register on June 26, 2026, drew public comment and a July hearing, and was then withdrawn in its entirety over concerns about its energy provisions, with the Notice of Withdrawal published on October 16, 2026. A Maryland data center permitted now is therefore designed, inspected and commissioned to the 2021 codes, and that will hold until a new proposal completes the process.

Baltimore City publishes its own Building, Fire and Related Codes. The 2024 Edition adopts the 2021 International Building, Mechanical, Energy Conservation and Plumbing Codes, effective for permit applications filed on or after May 22, 2024 under Ordinance 24-341. Owners in the city should expect the same 2021 code base, administered through the city’s own permit and inspection process.

Energy code commissioning requirements under the 2021 IECC

The 2021 International Energy Conservation Code, which is the Maryland energy code today, requires mechanical systems commissioning and a preliminary commissioning report before the final inspection that leads to a certificate of occupancy. That report lists the functional performance test results and any deferred tests that need particular weather, so a hall finishing in winter can record its summer tests as deferred rather than holding the certificate.

Data centers carry an extra layer. Section C403.1.2 of the 2021 IECC sends data center systems to ASHRAE 90.4, Sections 6 and 8, with the code’s own values for the mechanical load component, the measure of how much cooling plant energy the design spends per unit of IT load. Commissioning confirms that what was built matches the efficiency the design claimed: measured pump and fan power, chiller performance at part load, economizer changeover points and control sequences that keep the plant on its most efficient path.

Paul Industries carries out the mechanical side of those tests, with calibrated instruments and signed sheets, and assembles the data the commissioning authority needs to complete the energy code reports. Those Maryland energy code requirements sit alongside, rather than in place of, the owner’s own data center commissioning requirements for redundancy and failure response.

How the data center commissioning process runs on a Maryland job

The data center commissioning process on a Maryland job begins at design review and ends a full year after turnover, when the last deferred seasonal tests are complete and the first benchmarking report has gone to the state. In between, the work follows the construction sequence: equipment submittals are checked against the design intent, factory tests are witnessed, installation is verified, systems are started, and then each system and finally the whole facility is tested against its sequences of operations.

Maryland adds checkpoints to that flow. Pressure vessel paperwork enters at submittal rather than at startup, the oil permit sits ahead of the first fuel delivery, county inspections bracket the pressure tests, and the preliminary commissioning report has to be ready before the final inspection. Paul Industries keeps one issues log across all of them, so a defect found during a functional test is tracked to closure alongside the inspection and permit items rather than in a separate list.

Writing the data center commissioning plan for a Maryland project

A data center commissioning plan for a Maryland project names the systems in scope, the level each will reach, the test procedures, the people who witness each test and the records each test produces, and it ties every one of those to the construction schedule. On phased campus buildings the plan repeats for every block of IT load, with the tests that touch live systems marked for extra isolation steps.

The Maryland version of the plan carries a few lines that a generic template leaves out: the MDE generator permit conditions on testing, the oil permit date, the certificate inspection dates for pressure vessels, the county’s inspection sequence, the noise limits that apply at the property line, and the seasonal tests expected to be deferred. Paul Industries drafts the mechanical sections of the plan with those lines filled in, so the plan reads as a schedule the site can follow rather than a list of good intentions.

How do the 5 levels of data center commissioning map onto a Maryland permit?

The 5 levels of data center commissioning run from factory testing to integrated systems testing, and on a Maryland project each level lines up with a different inspection or permit milestone. Data center commissioning levels are the industry’s shorthand for that sequence, and the table below shows where Maryland’s agencies enter it.

Commissioning levels and the Maryland milestones that ride on them
LevelWhat is testedMaryland milestone tied to itRecords produced
Level 1: factory witnessChillers, CDUs, pump skids and switchgear at the factoryPressure vessel data reports and nameplates checked before shipmentFactory test reports, manufacturer data reports
Level 2: delivery and installation checksEquipment received, set and piped to drawingsCounty rough-in inspections; certificate inspection of pressure vesselsReceiving logs, installation checklists, inspection sign-offs
Level 3: startupFlushing, pressure tests, first runs of pumps, chillers and towersHydronic test witnessed where the county requires it; MDE oil permit in place before generator fuel is storedTest sheets, flushing logs, startup reports
Level 4: functional performance testingEach system against its sequence of operationsResults feed the 2021 IECC preliminary commissioning reportFunctional test scripts, issues log
Level 5: integrated systems testingWhole facility under load bank heat with utility failures simulatedGenerator runs under the MDE air permit; final inspection and certificate of occupancyIST report, trend data, deferred test list

Level 5 data center commissioning is where Maryland’s agencies converge, because the integrated test runs generators, fuel systems, cooling plants and controls together, and each of those is under a different permit. Paul Industries schedules level 5 runs with the permit conditions in hand, so test duration, generator hours and night work stay inside them.

Pressure vessels on the cooling plant and the Chief Boiler Inspector

Pressure vessels on a Maryland cooling plant, such as expansion tanks, air separators, buffer tanks and some heat exchangers, fall under the Maryland Boiler and Pressure Vessel Safety Act unless an exemption in the Act applies. The Act requires each covered vessel to be registered and to hold a certificate of inspection issued under the Chief Boiler Inspector before it is operated, and certificate inspections of new installations are part of that process.

The vessel’s manufacturer’s data report, nameplate and National Board registration are what the inspector checks, so those documents belong in the Level 1 and Level 2 records rather than in a turnover binder assembled after startup. Paul Industries collects them as equipment arrives and schedules the certificate inspection ahead of the startup date. Vessels fabricated for the project are covered on pressure vessel fabrication in Maryland.

Generators, fuel and air permits during integrated testing

Integrated testing on a Maryland campus runs the emergency generators, and those generators operate under air quality permits issued by the Maryland Department of the Environment. A March 2026 MDE permit for 99 diesel generators at a Frederick data center limited them to emergencies plus testing and maintenance, barred demand response, and called for an oil permit of its own ahead of any on-site diesel storage. For commissioning, that means the oil permit has to be in hand before the first fuel delivery for generator tests, and the test plan has to fit within the permit’s conditions on testing.

Noise adds a second limit. COMAR 26.02.03 caps sound at residential property at 55 dBA at night, and generator banks, load banks and cooling towers running together during a night-time integrated test can exceed that where homes border the site. Paul Industries plans the loudest tests for daytime hours wherever the schedule allows and confirms sound at the property line during the first run.

Testing cooling plants against Maryland weather

Maryland weather limits when some cooling tests can prove anything, because a cooling tower only shows its capacity on a humid day and freeze protection only shows its worth on a cold night. NOAA’s hourly records at BWI for 2021 through 2024 give a sense of how narrow those windows are.

Seasonal test windows at BWI (NOAA hourly observations, 2021 to 2024 average)
TestWeather it needsHours per year at BWIWhen it usually happens
Cooling tower capacity near designWet bulb above 75 FAbout 369Mid-summer; deferred if the hall finishes in cooler months
Air-cooled chiller and dry cooler peak capacityDry bulb above 90 FAbout 166July and August afternoons
Full water-side economizer operationWet bulb at or below 45 FAbout 3,281Late autumn through early spring
Freeze protection and basin heatersDry bulb at or below 32 FAbout 624December through February

The 2021 IECC lets these tests be listed as deferred in the preliminary commissioning report, so the certificate of occupancy does not wait for July. Paul Industries returns for the deferred tests in the right season, runs them against the same scripts, and adds the results to the final report. For the plant design behind these tests, see data center cooling in Maryland.

Maryland Building Energy Performance Standards and what commissioning hands the operator

Maryland Building Energy Performance Standards, created by the Climate Solutions Now Act of 2022, require covered buildings of 35,000 square feet or more to benchmark energy use in ENERGY STAR Portfolio Manager by June 1 each year and to reach net-zero direct greenhouse gas emissions by 2040. Exemptions exist for several building types and situations, but the Maryland Department of the Environment requires owners to apply for them through its BEPS Portal rather than treating them as automatic, and the 2025 amendments expanded the exclusion for backup generators.

Commissioning is where good benchmarking starts. Utility meters, submeters on the cooling plant and generator fuel, and the trend logs that feed Portfolio Manager are all installed and checked during construction, and a meter that was never verified produces a year of data nobody trusts. Paul Industries checks meter wiring, scaling and trend logging during functional testing, so the first June 1 report rests on readings that were proven at turnover.

Montgomery County runs its own program as well. Its Building Energy Performance Standards law covers commercial and multifamily buildings of 25,000 gross square feet and larger, with site energy use intensity standards set by building type after a benchmarking baseline. A data room inside a larger Montgomery County building affects that building’s energy intensity, which makes verified efficiency at commissioning worth more there.

A data center commissioning checklist for a Maryland turnover

A data center commissioning checklist for a Maryland turnover adds state and county records to the usual test documents, and missing any one of them can hold the certificate of occupancy or the first benchmarking report. The list below is the set Paul Industries assembles on the mechanical side.

Mechanical turnover records on a Maryland data center
RecordWhy Maryland needs itWhen it is produced
Pressure test and flushing records for every loopCounty mechanical inspection; owner’s warranty and operationsLevel 3
Pressure vessel data reports and certificates of inspectionMaryland Boiler and Pressure Vessel Safety ActLevels 1 to 3
Functional performance test results2021 IECC preliminary commissioning reportLevel 4
Deferred test list with planned seasonAllows the certificate of occupancy before summer or winter testsLevel 4 and 5
Integrated systems test report and trend dataOwner acceptance; generator test hours logged against the MDE permitLevel 5
Meter and submeter verificationMaryland BEPS benchmarking each June 1; Montgomery County BEPS where it appliesLevel 4
As-built piping drawings, valve tags and coolant analysisOperations, future tie-ins and liquid cooling maintenanceTurnover

Commissioning schedules during the county pauses and the large-load registry

County pauses on new data center applications in 2026 changed which Maryland projects reach commissioning, not how commissioning is done. Maryland data center law moved in the same year, and Maryland data center regulations now reach a commissioning schedule through generator permits, fuel permits, energization and registration. Frederick County’s executive order of July 1, 2026 paused new applications while letting approved projects continue, and a companion order requires developers to show registration with the Public Service Commission’s large-load registry, which the Utility RELIEF Act of 2026 directed the commission to create. Approved campuses, expansions inside existing buildings and liquid cooling retrofits keep moving, and they bring a steady flow of hyperscale data center commissioning and smaller phased turnovers.

Phased energization shapes the data center commissioning schedule on those projects. Each block of IT load is commissioned as its power arrives, with integrated tests repeated for every block, while earlier blocks stay live. Paul Industries plans isolation, temporary connections and retesting so that each new block proves itself without putting operating halls at risk. Owners adding dense racks to a live hall can read about data center liquid cooling in Maryland.

What does data center commissioning in Maryland cost?

Data center commissioning in Maryland is priced on the number of systems and levels in scope, the hours of load bank and generator testing, the number of phases and the season in which tests fall, rather than on a fixed percentage of construction cost. Load bank energy is one measurable part. At Maryland’s 2025 average commercial price of 14.72 cents per kilowatt-hour, one megawatt of load bank heat for 24 hours on utility power uses about $3,530 of electricity; generator-powered tests trade that for diesel under the MDE permit’s limits. Larger accounts pay tariff rates that differ from the average, so the owner’s own rate gives the real figure.

Repeat testing for each phase, deferred seasonal tests, night work for noise limits and escorted access on federal sites all add hours. Paul Industries prices each level and phase separately, so the owner sees exactly what each part of the data center commissioning process costs and can decide which levels to carry for each block.

Two choices made early save the most money later. Installing test ports, flushing connections and load bank tie-in points during construction avoids cutting into finished piping at the commissioning stage, and agreeing the test scripts before equipment is ordered lets factory tests catch faults while they are still the manufacturer’s to fix. Paul Industries builds both into its piping drawings and submittals on Maryland projects.

Who performs data center commissioning in Maryland?

Paul Industries performs the mechanical side of data center commissioning in Maryland: flushing and cleaning loops, pressure testing to the 2021 International Mechanical Code and the ASME piping codes, starting chillers, towers, pumps and CDUs, running functional and integrated tests, and assembling the records each agency and the owner need. Among data center commissioning companies working in the state, Paul Industries combines installation knowledge with testing, so every test is run with full knowledge of where each valve, sensor and isolation point sits.

Paul Industries delivers data center commissioning services in Maryland on new campus buildings, expansions and retrofits, either as part of a cooling or mechanical contract or as a standalone scope on systems already installed. Related work appears on data center mechanical contractors in Maryland, and regulated process commissioning for pharmaceutical and biotech plants is covered on validation and commissioning in Maryland. The national method and data center commissioning standards are set out on data center commissioning, with hydrostatic testing detailed separately. For the headquarters state, see data center commissioning in Virginia, and for a neighboring market, data center commissioning in New Jersey.

Paul Industries commissioning work for Maryland data halls

Headquartered on Shore Drive in Kilmarnock, Virginia, Paul Industries commissions data center cooling and mechanical systems across Maryland, including Frederick County campuses, Hagerstown, the I-270 corridor, Prince George’s County, Baltimore, Columbia, Annapolis and the Eastern Shore. The company flushes, tests, starts up and proves chilled water plants, liquid cooling loops, pumps and heat rejection, hands over the records Maryland’s codes and agencies ask for, and commissions plants in every one of the 50 states and internationally as well. Send the drawings, the commissioning plan if one exists and the phasing schedule, then call 201-450-8280 or request a quote.

Standards referenced: Maryland Building Performance Standards (2021 IBC, IRC and IECC), COMAR 09.12.51 · 2021 International Energy Conservation Code, Sections C403.1.2 and C408 · ASHRAE 90.4 · ASHRAE Guideline 0 and ASHRAE Standard 202 (commissioning process) · 2021 International Mechanical Code · ASME B31.9 and ASME B31.3 · Maryland Boiler and Pressure Vessel Safety Act · Maryland Building Energy Performance Standards (Climate Solutions Now Act of 2022) · COMAR 26.02.03 (noise) and COMAR 26.11 (air quality)

Frequently asked questions

Does Paul Industries flush, test and start up cooling plants for data halls in Baltimore and Howard County?

Yes. Paul Industries commissions cooling plants, pumps and liquid cooling loops for data halls in Baltimore City, Baltimore County, Columbia and the rest of Howard County. In Baltimore City the work follows the city’s 2024 Edition codes, which adopt the 2021 International Codes, and in the counties it follows the Maryland Building Performance Standards as each county enforces them.

Who handles data center commissioning on Frederick County campus buildings?

Paul Industries handles the mechanical commissioning for Frederick County campus buildings, from flushing and pressure testing through integrated systems tests with generators under the MDE air permit. Campus buildings are usually commissioned block by block as power arrives, so the test plan repeats for each block while earlier blocks stay live.

Does Paul Industries offer data center commissioning services along the I-270 corridor and in Prince George's County?

Yes. Research, federal and enterprise data rooms in Rockville, Gaithersburg, Germantown, College Park and Greenbelt are commissioned the same way as larger halls, scaled to the systems installed. Many sit in buildings covered by benchmarking rules, so Paul Industries verifies meters and trend logs as part of functional testing.

Which building code edition applies to a Maryland data center permitted in late 2026?

The 2021 International Building, Residential and Energy Conservation Codes, as adopted in the Maryland Building Performance Standards. A move to the 2024 editions was proposed in June 2026 and withdrawn in its entirety, with the withdrawal notice published October 16, 2026, so the 2021 codes remain the basis for design, inspection and commissioning.

Does Baltimore City use its own building code for data centers?

Baltimore City administers its own Building, Fire and Related Codes. The 2024 Edition, under Ordinance 24-341, adopts the 2021 International Building, Mechanical, Energy Conservation and Plumbing Codes for permit applications filed on or after May 22, 2024. The code base matches the state’s, while permits and inspections run through the city.

What is the preliminary commissioning report under the Maryland energy code?

Under the 2021 IECC, the preliminary commissioning report is completed before the final inspection that leads to a certificate of occupancy. It records functional performance test results and lists deferred tests that need particular weather. Paul Industries supplies the mechanical test data that report draws on and returns later to complete the deferred tests.

Does Maryland BEPS apply to a data center building?

Maryland’s Building Energy Performance Standards cover buildings of 35,000 square feet or more, excluding parking, unless an exemption applies, and MDE requires owners to apply for exemptions through its BEPS Portal. Owners check their building on MDE’s covered buildings list. Covered buildings benchmark by June 1 each year, which depends on meters verified at commissioning.

What is IST in data center commissioning, and how is it run on a Maryland campus?

IST, integrated systems testing, is level 5: the whole facility runs under load bank heat while utility failures, generator starts and equipment faults are simulated. On a Maryland campus the generators run under MDE air permit conditions, and night-time runs must respect noise limits at homes beside the site. Paul Industries runs the mechanical side and records plant response throughout.

When do cooling tower capacity tests have to wait for summer in Maryland?

A tower only shows near-design capacity when the wet bulb is high, and BWI averaged about 369 hours a year above a 75 degree wet bulb from 2021 to 2024. A hall finishing between autumn and spring records the tower test as deferred in the preliminary commissioning report, and Paul Industries runs it the following July or August.

Do generator runs during commissioning need MDE approval?

The generators themselves are permitted by MDE, and recent permits restrict them to emergencies plus testing and maintenance. Commissioning runs fall under testing, so the test plan is written to the permit’s conditions and hours are logged. Paul Industries reviews the permit before scheduling integrated tests.

Must diesel be permitted before it is delivered for commissioning tests?

Yes. MDE’s March 2026 generator permit for a Frederick data center states that a separate oil permit is required before diesel fuel is stored on site. Fuel for commissioning tests counts, so the oil permit goes on the critical path ahead of the first generator run, and Paul Industries tracks it in the commissioning schedule.

Does a Maryland pressure vessel need a certificate before the cooling plant starts?

Covered pressure vessels on a cooling plant must be registered and hold a certificate of inspection issued under the Chief Boiler Inspector before they operate, unless the Maryland Boiler and Pressure Vessel Safety Act exempts them. Paul Industries collects data reports and nameplate records on delivery and books the certificate inspection ahead of startup.

Can generator and load bank tests run at night near homes in Maryland?

COMAR 26.02.03 limits sound at residential property to 55 dBA at night and 65 dBA by day. Generator banks and load banks can exceed the night limit where homes border a campus, so the loudest tests are scheduled in daytime wherever possible, with sound checked at the property line during the first run. Paul Industries builds those limits into the test plan.

How much does the energy for a load bank test cost in Maryland?

At Maryland’s 2025 average commercial price of 14.72 cents per kilowatt-hour, one megawatt of load bank heat for 24 hours on utility power uses about $3,530 of electricity. A large hall’s actual tariff will differ, and generator-powered tests use diesel instead. Paul Industries estimates test energy from the owner’s rate and the planned test hours.

Which data center commissioning levels should a small Maryland data room carry?

A small data room in a Maryland office or laboratory building usually carries levels 3 and 4 in full, with startup, flushing, pressure testing and functional tests on every system, plus a scaled integrated test that fails the main power feed and checks how cooling recovers. Factory witness tests are often limited to the CDU or chiller. Paul Industries proposes the levels to match the room’s risk and budget.

Does Montgomery County's BEPS law change commissioning for a data room there?

Montgomery County’s law covers commercial and multifamily buildings of 25,000 gross square feet and larger and sets site energy use intensity standards by building type. A data room raises its building’s energy intensity, so verified cooling efficiency and accurate submetering at commissioning matter more there. Paul Industries checks both during functional testing.

How does the Frederick County data center pause affect commissioning schedules?

The July 2026 executive order paused new applications but let approved projects continue, so commissioning on approved campus buildings proceeds on its own schedule. A companion order asks developers to show registration with the PSC large-load registry. Paul Industries plans each phase’s tests around its energization date.

Which records should a Maryland operator keep after commissioning for BEPS and audits?

Keep the pressure test and flushing records, pressure vessel certificates, functional and integrated test reports, the deferred test list and results, meter verification records, generator test logs kept against the MDE permit, and as-built drawings with valve tags. Paul Industries delivers those in an indexed turnover package.

Which plans and schedules should accompany a Maryland commissioning request?

Send the mechanical drawings, the sequences of operations, the owner’s commissioning plan if one exists, the phasing and energization schedule, the generator and fuel permits, and the target levels for each phase. Paul Industries then prices each level and phase separately and returns a test schedule tied to the construction plan.

Commissioning a data hall anywhere in Maryland?

Send the mechanical drawings, sequences of operations, phasing schedule and permits. Call 201-450-8280 or request a quote.