Paul Industries is a US process equipment contractor for Sweden that engineers and fabricates pressure vessels, process skids, bioprocess support systems and complete process lines for Swedish plants, tests them before export, ships them to Gothenburg, and installs and commissions them on site or supervises their installation. Each pressure part leaves the United States with its Pressure Equipment Directive documentation, a classification under the Swedish rules in AFS 2023:11, Swedish instructions, and electrical design for 50 Hz, 230/400 V supply. Paul Industries runs every Swedish project from its headquarters at 256 Shore Drive, Kilmarnock, Virginia, and prices it in US dollars.
Request a quote or call 201-450-8280
Why Swedish plants use a US process equipment contractor for Sweden
Swedish manufacturers use a US process equipment contractor for Sweden when they want one firm accountable for the process design, the fabricated equipment, the export and the start-up of a system that has to meet both EU product law and Swedish rules for equipment in use. Paul Industries delivers that scope for biologics plants, chemical producers, steel and hydrogen projects and food plants. The equipment includes code-built pressure vessels, bioreactor installation and support skids, water for injection and purified water systems, cleaning and sterilizing skids and the process piping that ties them into the building.
Three contract shapes are common. A supply-and-supervise contract has Paul build and test the equipment in the United States, deliver it, and lead the setting and start-up at the Swedish site. A design-build contract widens the scope to the utilities and layout of the process area. A complete installation contract leaves Paul in charge on site until the system is running and qualified. A wider list of the countries Paul serves sits on the international page; the sections here explain what Swedish law, power, logistics and inspection practice add.
Pharmaceutical companies in Sweden and the wider process market
Pharmaceutical companies in Sweden run some of Europe’s most active biologics sites, and their expansions drive demand for fill lines, water systems and clean utilities. AstraZeneca’s Sweden Biomanufacturing Center in Sodertalje opened in 2021, and in August 2024 the company committed an additional 135 million US dollars to grow it by about 2,700 square metres, a 50 percent increase in area, with new equipment for filling biological drugs into prefilled syringes and manufacturing planned to begin in the fourth quarter of 2027. The Sweden pharmaceutical industry also includes contract manufacturers and smaller Swedish pharma companies in Stockholm, Uppsala, Lund and Gothenburg.
Among biotech companies, Sweden is home to the Cytiva resin plants in Uppsala, which have roughly doubled their chromatography resin output with new factories, automation and a tank farm for solvent storage. Until the company’s Muskegon, Michigan, site, every Cytiva chromatography resin plant stood in Sweden. Biotech in Sweden therefore spans both medicine makers and the suppliers of bioprocess materials, and both buy solvent handling, purified water, clean steam and biotech process systems.
Heavy industry is the other half of the market. At Stenungsund, north of Gothenburg, a chemical cluster including Borealis, INEOS Inovyn, Nouryon and Perstorp makes ethylene derivatives, PVC, caustic soda, hydrochloric acid and hydrogen. In the north, the HYBRIT pilot plant in Lulea, run by SSAB, LKAB and Vattenfall, has made more than 5,000 tonnes of hydrogen-reduced sponge iron since 2020, a proving ground for hydrogen steel. Sweden also has Stegra building a hydrogen-based steel plant at Boden. Projects of that kind buy electrolyser utilities, gas handling, cooling water and chemical plant equipment built to strict pressure rules.
Swedish pressure equipment rules: from AFS 2017:3 to AFS 2023:11
Swedish pressure equipment rules split into two layers: the Pressure Equipment Directive governs design, manufacture and CE marking before equipment is placed on the market, and the Swedish Work Environment Authority’s provisions govern how the employer installs, inspects and uses it. Until the end of 2024 the use layer sat in AFS 2017:3, the provisions on use and inspection of pressurized devices. Since 1 January 2025 those rules, together with the older boiler rules in AFS 2006:4, form chapters of AFS 2023:11, the consolidated provisions on safe use of work equipment. The product layer moved at the same time, with AFS 2016:1 carried into AFS 2023:5 with largely the same content.
For a US manufacturer the product layer works as it does anywhere in the EU. Each pressure part is classified by fluid group and pressure under the directive, the matching conformity assessment module is followed, and the item ships with CE marking and an EU declaration of conformity. Swedish provisions add a language rule: the declaration is drawn up in or translated into Swedish, and the instructions and safety information that accompany the equipment are supplied in Swedish. Paul delivers the technical file, the declaration and the Swedish instructions together.
Class A and class B under AFS 2023:11
Swedish use rules sort pressure equipment into class A, class B or no class at all, using pressure multiplied by volume rather than the directive’s categories. A vessel must hold more than 2 litres at more than 0.5 bar before it can be classed. For a gas in the less hazardous fluid group 2a, a vessel above 200 bar-litres falls in class B and one above 1,000 bar-litres in class A; for the most hazardous group 1a gases the thresholds drop to 50 and 200 bar-litres. Separate tables cover boilers, piping and cisterns.
The class matters because an employer may pressurize class A or B equipment only after an accredited inspection body, a kontrollorgan, has judged that it meets the provisions. Pressurizing without that judgment brings a sanction fee of 15,000 to 300,000 Swedish kronor per device. Every class A and B device also needs a service-life journal that records its history, inspections, maintenance and repairs. Paul states the expected class of every vessel, line and cistern in the design documents and delivers the manufacturing data in the order the journal follows.
First inspection and recurring inspection intervals
The first inspection under AFS 2023:11 takes place before class A or B equipment is pressurized for the first time, and again whenever a stationary device is moved. The inspection body checks that the equipment suits its purpose, is undamaged and is placed correctly. Where devices are joined together at the site, the body also assesses the joining, unless the assembly is already covered by an EU declaration of conformity. Skids that Paul builds and assesses as a directive assembly arrive with that declaration, which narrows the work at the first inspection.
| Type of device | Basic interval | Design consequence |
|---|---|---|
| Vessels in refrigeration or heat pump plants | 1 year | Relief valves and level controls reachable without scaffolding |
| Vessels filled with air, nitrogen or noble gas | 4 years | Receivers sized and tagged for long, simple test cycles |
| Other pressure and vacuum vessels | 2 years | Isolation valves so one vessel tests while the line runs |
| Cisterns and piping joined to them | 3 years | Inspection access on tank tops and roof nozzles |
| Piping not joined to a cistern | 4 years | Supports and expansion points left open to view |
The operational test checks safety equipment and the system around the device, and the inspection body can extend the interval to a maximum of four years after two clean results. Class A equipment also needs internal and external examination: a four-year interval is possible when the pressure parts are not fired, more than five years of life remain, cracking risk is low and the environment is mild, and a two-year route applies otherwise. Paul designs manways, spool breaks and instrument isolation so those examinations take hours rather than days.
Machinery, ATEX and the 2027 machinery change
Machinery rules govern any skid with pumps, agitators and automatic controls. Equipment placed on the market now follows the Machinery Directive 2006/42/EC, and the Machinery Regulation (EU) 2023/1230 takes over on 20 January 2027, so the declaration for a skid shipped after that date cites the regulation. Control panels follow the Low Voltage and EMC directives, and devices for solvent rooms or hydrogen areas follow the ATEX Directive 2014/34/EU. Paul buys bought-out instruments, motors and valves in their European versions and files each declaration with the skid’s technical file.
Cold-climate design for plants in northern Sweden
Cold-climate design shapes equipment bound for Lulea, Boden and other northern sites, where winter brings long periods well below freezing and short daylight for outdoor work. Outdoor piping, relief lines, instrument impulse lines and safety showers need heat tracing and insulation sized for the site’s design minimum, and drains have to fall cleanly so no water stands in a dead leg. Paul designs heat tracing circuits, insulation thicknesses and enclosure heating together with the process design, specifies materials with impact properties suited to the low design temperature, and arranges outdoor skids so valves and instruments sit inside heated housings that operators reach without climbing in snow. Crates for winter delivery arrive with lifting points and setting plans that let the plant place the module quickly and close it up before the next cold spell.
Indoor process areas in the north often recover heat as well. Compressor cooling water, fermenter and electrolyser cooling loads and boiler blowdown carry useful energy, and a Swedish plant usually expects it to be returned to building heating or a process stream. Paul sizes heat exchangers and pressure-rated recovery loops into the utility design, classifies each new pressure part under the directive and AFS 2023:11, and documents it with the rest of the system.
What is the voltage in Sweden, and what does it change on a US skid?
The voltage in Sweden is 230 V phase to neutral and 400 V between phases at 50 Hz, the same as most of Europe. For an engineer comparing voltage in Sweden vs USA, the frequency is the bigger change: a centrifugal pump or fan selected at 60 Hz turns about one sixth slower on Swedish power, delivering less flow and much less head, so impellers, motor frames or drive settings are reselected for 50 Hz before fabrication. The 3 phase voltage in Sweden also differs from the 480 V common in US plants, which moves motor windings, heater elements and transformer taps.
Installation inside the plant follows SS 436 40 00, the Swedish standard for design and erection of low-voltage installations, whose fourth edition was issued in 2023 and replaced the 2017 edition from May 2024. Paul designs the panel feeders, cable sizing and protective earthing to the plant’s single-line diagram and the standard, uses IEC component ratings throughout, and tests the panel at 50 Hz where the shop supply permits before the skid is crated.
| Design item | US practice | Swedish plant | Paul’s approach |
|---|---|---|---|
| Supply frequency | 60 Hz | 50 Hz | Pumps and fans selected on 50 Hz curves |
| Three-phase voltage | 480 V | 400 V | Motors, heaters and drives rated for 400 V |
| Installation standard | NEC | SS 436 40 00 | Feeders and earthing designed to the Swedish rules |
| Pressure classification | ASME Section VIII design | PED category plus AFS class A or B | Both classifications shown in the documents |
| Units and language | Inches, psi, English | Millimetres, bar, Swedish instructions | Metric drawings and Swedish instructions from the first issue |
GMP inspection by the Swedish Medical Products Agency
The Swedish Medical Products Agency, Lakemedelsverket, grants manufacturing authorisations after assessing the applicant’s good manufacturing practice, including inspection of the sites where medicines will be made, and it inspects authorised manufacturers regularly afterwards. Its inspectors apply EU GMP, including Annex 1 for sterile products, and the European Pharmacopoeia sets water quality. A new fill line, WFI loop or buffer preparation skid in Sodertalje or Uppsala therefore needs specifications and qualification records that an EU inspector can follow from requirement to test result. Paul writes those documents to the plant’s quality system and executes IQ and OQ on site through validation and commissioning, with the same surface finish, weld and passivation records it supplies for pharmaceutical plants in the United States.
Shipping to Sweden from USA East Coast ports
Shipping to Sweden from USA East Coast ports normally ends at Gothenburg, the largest port in Scandinavia, which handled a record 934,000 TEU in 2025 and carries more than half of Sweden’s container traffic. Published forwarder figures for the crossing vary widely, from about two and a half weeks on fast routings to an average near seven weeks on lanes with several transfers, so the plan allows for the longer case. Paul books space once crate dimensions are frozen and ties the factory acceptance test to a confirmed departure.
Rail is the strength of the Gothenburg gateway: 529,000 TEU moved by train through the port in 2025, on shuttles that reach industrial towns inland and in the north. A shipping container from USA to Sweden can therefore stay on rail to a terminal near Sodertalje, Uppsala or Lulea, with a short truck leg to the plant. Out-of-gauge modules for a plant in Stenungsund or the Gothenburg region often go by road from the quay. Paul checks the crate heights and weights against the chosen inland route before the module design is frozen.
Customs, import VAT and Incoterms for a Swedish order
Swedish customs, Tullverket, handles clearance of US-built equipment, and the EU’s common tariff sets any duty. An importer first registers for an EORI number with Tullverket; at clearance, the 25 percent Swedish import VAT is levied on a base made of the goods’ customs value with duties added. A VAT-registered Swedish company reports that import VAT in its own VAT return rather than paying it at the border. Sweden keeps the krona, so Paul quotes in US dollars and leaves currency conversion to the buyer’s finance team.
Under Incoterms 2020, Swedish buyers who run their own logistics often take the equipment FCA at a US port. DAP to the Swedish site puts the ocean and inland legs and their risk on Paul, and DDP adds import clearance and VAT to the delivered price. Every crate is ISPM 15 heat-treated, marked to the packing list and preserved with sealed wrap and desiccant for a North Atlantic crossing in any season. Equipment for a group that also runs sites in Denmark or Germany often moves on the same North Sea services.
How does a Swedish project run with Paul Industries?
A Swedish project with Paul Industries follows nine steps, and the early ones settle the PED categories, the AFS classes, the Swedish documents and the inland route that the later steps depend on. The table shows each step and what it leaves behind for the Swedish plant.
| Step | Work carried out | Record for the Swedish plant |
|---|---|---|
| 1. Scope and classification | Process duty, utilities, PED categories, AFS 2023:11 class for each device | Classification register for vessels, piping and cisterns |
| 2. Engineering | P&IDs, layout, 50 Hz electrical design to SS 436 40 00 | Metric drawings with inspection access marked |
| 3. Fabrication in the United States | Orbital and manual welding, skid assembly, panel wiring and instrument fitting | Material certificates, weld maps, NDT reports |
| 4. Factory acceptance test | Pressure, function, alarm and sequence checks, attended in person or remotely | Signed test protocol for the technical file |
| 5. Export packing and freight | Preservation, ISPM 15 crates, sailing to Gothenburg, rail or road inland | Packing list, commercial invoice, origin certificate |
| 6. Site installation or supervision | Setting, tie-ins and connection, ready for the first inspection | Installation record for the kontrollorgan |
| 7. Start-up | Flushing, rotation checks, water runs, first product | Start-up log with tuned loop values |
| 8. Commissioning and qualification | Site acceptance, installation and operational qualification tied to the user requirements | Executed protocols for the GMP file |
| 9. Handover and service | Training, spares and the service plan | Swedish instructions and data for the service-life journal |
After handover Paul keeps the drawings, control program, test data and weld records for each Swedish system, so faults are diagnosed by video with the plant’s engineers and the correct spare ships on the first order. Service visits are timed to the plant’s recurring inspection dates, which lets one shutdown cover the inspection body’s examination, seal changes and calibration.
Who builds process systems for plants in Sweden?
Paul Industries builds process systems for plants in Sweden, from dosing skids and air receivers to complete WFI, clean steam, CIP, solvent handling and bioreactor support systems, and takes each one through factory testing, freight, installation, start-up and qualification on the Swedish site. The design work, the US fabrication, the paperwork for the directive and for AFS 2023:11, and the after-sales service all stay with Paul. Plants in Sodertalje, Uppsala, Stenungsund, Gothenburg, Lulea and Boden work with one contractor across the whole project.
What does shipping to Sweden from USA cost, and what else drives the project price?
The delivered cost of process equipment for a Swedish plant rests on five items besides the equipment: ocean and inland freight, export crating, PED and Swedish documentation work, import charges under the agreed Incoterm, and the installation scope. Each is priced as a separate line.
- Freight. A skid that fits a standard high cube box moves by sea and rail at container rates; an oversize module needs a flat rack and a road permit inland.
- Crating. Long polished vessels and tall columns need heavier crates and more preservation than compact carbon steel skids.
- Documentation. Category III and IV conformity work, AFS classification, the technical file and Swedish translation add engineering hours.
- Import charges. The buyer pays duty and 25 percent import VAT under FCA or DAP; Paul carries them under DDP.
- Installation scope. Supervision keeps Paul’s site hours lower, while complete installation puts start-up and qualification in Paul’s hands as well.
Paul issues a budget range from similar past work first, then a fixed price once the drawings, classes and delivery terms are agreed.
Paul Industries for Swedish process plants
Paul Industries, at 256 Shore Drive, Kilmarnock, Virginia, engineers, builds, tests, ships, installs and commissions process equipment for Swedish biologics, chemical, steel, hydrogen and food plants. Each system leaves the United States classified under the Pressure Equipment Directive and AFS 2023:11, wired for 50 Hz supply and documented in Swedish, and stays with Paul for qualification and service. Send the process duty, the plant location and the Incoterm you prefer to request a quote.
Standards referenced: Pressure Equipment Directive 2014/68/EU · AFS 2023:11 (use and inspection of pressure equipment) · AFS 2023:5 (product rules for pressure equipment, formerly AFS 2016:1) · Machinery Directive 2006/42/EC · Machinery Regulation (EU) 2023/1230 · Low Voltage Directive 2014/35/EU · EMC Directive 2014/30/EU · ATEX Directive 2014/34/EU · SS 436 40 00 · EN 13445 · EU GMP Annex 1 · European Pharmacopoeia · Incoterms 2020 · ISPM 15
Frequently asked questions
Which pharmaceutical companies in Sweden are expanding biologics production?
AstraZeneca is expanding its Sweden Biomanufacturing Center in Sodertalje with an additional 135 million US dollar investment, adding about 2,700 square metres and new equipment for filling biologics into prefilled syringes, with production planned from late 2027. Cytiva has roughly doubled resin capacity in Uppsala. Paul Industries builds the water systems, CIP skids and clean utilities that projects of that kind need.
What replaced AFS 2017:3?
AFS 2017:3, the Swedish provisions on use and inspection of pressurized devices, ceased on 1 January 2025. Its content now sits in chapters of AFS 2023:11, together with the former boiler provisions from AFS 2006:4. The class A and class B system, the first inspection and the recurring inspections continue under the new numbering. Paul Industries documents new equipment against AFS 2023:11 so the classification and journal data are ready at delivery.
What is the voltage in Sweden for industrial equipment?
Swedish mains power is 230 V phase to neutral and 400 V between phases, at 50 Hz. Industrial sites often take supply at higher voltage and transform it down on site, so the plant’s single-line diagram decides the feeder for a new skid. Paul Industries designs motors, drives, heaters and control panels for the 400 V, 50 Hz supply and the Swedish installation standard.
How long is shipping to Sweden from USA ports?
Forwarder data for the US East Coast to Gothenburg ranges from about two and a half weeks on fast routings to around seven weeks on routings with several transfers. Rail or road inland, customs clearance and the season add to that. Paul Industries reserves vessel space when the crate list is final and lines up the acceptance test with that booking.
What drives shipping to Sweden from USA cost for a large skid?
Freight cost for a large skid depends on whether it fits a high cube container or needs a flat rack, the number of transfers on the routing, the inland leg by rail or road, and the crate weight. Oversize modules add road permits and escort costs inland. Paul Industries designs skids to fit standard containers where the process allows and states freight as its own line in the quote.
Does a pressure vessel need inspection before first use in Sweden?
A class A or B vessel needs a first inspection by an accredited inspection body before it is pressurized for the first time, and again if it is moved. The body checks that the vessel suits its purpose, is undamaged and is correctly placed. Paul Industries delivers the classification, technical file and installation records the body needs, and schedules the inspection between setting and start-up.
Are Swedish instructions required for pressure equipment?
Swedish product provisions require the instructions and safety information that accompany pressure equipment to be supplied in Swedish, and the EU declaration of conformity to be drawn up in or translated into Swedish. Paul Industries prepares the instructions in Swedish and English, covering installation, start-up, operation, maintenance and safety, and delivers them with the turnover package.
Do bioprocess suppliers in Uppsala buy US-built tank farms and solvent systems?
Bioprocess manufacturers in Sweden, including the resin plants in Uppsala, buy solvent handling systems, tank farms, purified water and CIP equipment from suppliers in Europe and North America and choose on design, documentation and delivery. A US-built system is accepted once it meets the Pressure Equipment Directive, AFS 2023:11 and the plant’s own standards. Paul Industries builds to all three and commissions on site.
Who builds process equipment for chemical plants in Stenungsund?
Paul Industries designs, fabricates, ships and installs pressure vessels, heat exchangers, process skids and piping for chemical plants in Sweden, including the Stenungsund cluster north of Gothenburg. Each pressure part is classified under the Pressure Equipment Directive and the Swedish class A and B system, with ATEX devices for classified areas. Paul installs the equipment or supervises its installation and starts it up.
Can Paul Industries supply hydrogen and gas handling skids to projects near Lulea and Boden?
Paul Industries builds gas handling, cooling water, compressed gas and utility skids for hydrogen and steel projects in northern Sweden, including the Lulea and Boden areas. Hydrogen is a hazardous fluid, so vessel classes, relief design and ATEX zoning get close attention. The equipment ships to Gothenburg, moves north by rail or road, and is installed and started up on site by Paul or under Paul’s supervision.
Voltage in Sweden vs USA: how much does a 60 Hz pump lose at 50 Hz?
A centrifugal pump turns about one sixth slower at 50 Hz than at 60 Hz, which cuts flow in proportion to speed and head by roughly the square of the speed ratio. A pump selected for a US duty therefore falls short in Sweden unless the impeller, motor or drive is changed. Paul Industries selects pumps on 50 Hz curves for Swedish projects and confirms the duty at the factory acceptance test.
How often are class A pressure vessels examined in Sweden?
Class A vessels need operational tests, typically every two years for process vessels, plus internal and external examination. A four-year examination interval applies when the vessel is not fired, has more than five years of life left, low cracking risk and a mild environment; otherwise a two-year route applies. Paul Industries designs manways and isolation so those examinations run with short shutdowns.
Who pays Swedish import VAT on equipment from the United States?
The importer pays 25 percent import VAT on the customs value plus duties, and a VAT-registered Swedish company reports it in its own VAT return. Under FCA, CIF or DAP terms the Swedish buyer is the importer. Under DDP Paul Industries carries clearance, duty and VAT and shows them as separate lines in the delivered price.
Can Swedish engineers attend the factory acceptance test in the United States?
Engineers from Swedish plants come to the US test bay, watch over a camera link, or split the test between the two. With Swedish working hours starting while the US East Coast sleeps, Paul Industries places witnessed test points early in the American day. The signed protocol goes into the technical file and becomes the reference for the site acceptance test in Sweden.
What does the service-life journal need from the manufacturer?
The service-life journal for class A and B equipment records the device’s history, inspections, maintenance and repairs, and it starts with manufacturing data: design conditions, materials, weld and test records and the classification. Paul Industries supplies those records in a structured package at handover, so the plant’s journal is complete before the first inspection body visit.
Which Swedish port and route suit a plant in Uppsala or Sodertalje?
Equipment for Uppsala or Sodertalje usually lands in Gothenburg and moves inland by rail shuttle or truck, since the port runs regular rail services to inland terminals. Oversize crates go by road from the quay. Paul Industries checks the heaviest and largest crate against the inland route before the module design is fixed and names the port and route in the shipping plan.
Which details should a Swedish plant send for a first price?
A useful first package holds the process duty, the P&IDs or a written outline of the process, the plant address, available utilities, house engineering standards, GMP grade if any, the delivery term and the chosen installation scope. Paul answers with the expected AFS classes, a freight plan and a budget range in US dollars, and fixes the price when the scope is frozen.
Planning a process system for a plant in Sweden?
Send the process duty, the Swedish site and the delivery term you want, and Paul Industries will come back with the PED and AFS classification, the freight route and an opening price. Call 201-450-8280 or request a quote.
