As a data center mechanical contractor in Texas, Paul Industries builds chiller plants, cooling tower and dry cooler yards, chilled water and condenser water mains, coolant distribution unit piping and prefabricated pipe racks for campuses in Dallas-Fort Worth, Central Texas, Houston and West Texas. A Texas campus in 2026 is scheduled around more than steel and equipment deliveries: ERCOT’s large-load process, state permit decisions and the Comptroller’s tax rules all reach the mechanical package. Paul Industries supplies equipment, builds design-build mechanical packages and delivers complete installations from yard to rack.
Request a quote or call 201-450-8280
How a data center mechanical contractor in Texas plans around ERCOT, TCEQ and the Comptroller
A data center mechanical contractor in Texas plans the cooling plant, piping and yard around three state institutions as well as the design: ERCOT, which decides when a large load can energize; the Texas Commission on Environmental Quality, which authorizes standby generators and water permits; and the Comptroller, whose sales tax exemption for qualifying data centers covers cooling systems. Each of those changed in 2025 and 2026, and each moves dates on the mechanical schedule.
The mechanical scope itself is the same one described on the national data center mechanical contractors page: chillers, towers or dry coolers, pumps, chilled water and condenser piping, CDU loops, prefabricated spools and racks, testing and startup. The sections below cover what is different in Texas, from the 2025 large-load law to the codes, utilities and regions that shape each package.
Why build here: for a data center, Texas offers power, land and its own grid
For a data center, Texas offers industrial power below the national average, large parcels of land, and a grid operator, ERCOT, that runs about 90 percent of the state’s electric load inside Texas. EIA figures for 2024 put Texas industrial power at 6.12 cents per kilowatt-hour, well under the 8.13 cent national figure, and ERCOT reports that about 70 percent of the large loads asking to connect are data centers, with requests running to hundreds of gigawatts.
That demand is why data center construction in Texas now runs into rules written specifically for it. The scale also changes the mechanical work: campuses are planned as many identical buildings, so the first building’s plant, piping and racks become the template for every one that follows, and prefabrication pays back across the whole campus.
Where are data centers being built in Texas?
Data centers are being built in Texas in five broad areas: Dallas-Fort Worth and its suburbs, the Austin and San Antonio corridor, greater Houston, the West Texas plains around Abilene and the Permian Basin, and the Panhandle. Data centers in North Texas, from Garland, Plano and Richardson to Fort Worth, Midlothian and Red Oak, form the state’s largest cluster, while San Antonio, Austin, Round Rock and Taylor host colocation and research halls and data centers in Houston, Texas serve energy, healthcare and enterprise users along the Gulf Coast.
| Region | Grid and utilities | Mechanical emphasis |
|---|---|---|
| Dallas-Fort Worth | ERCOT; Oncor and other wires companies | Large chilled water plants, free cooling for winter, freeze protection, multi-building phasing |
| Austin, Taylor and San Antonio | ERCOT; Austin Energy and CPS Energy as municipal utilities, plus co-ops | Hybrid tower and dry cooler plants hedged against drought rules; dense research and GPU rows |
| Houston and the Gulf Coast | ERCOT; CenterPoint Energy | Humidity control, wind and flood design for yards, generator coverage of the cooling load |
| Abilene, Midland and West Texas | ERCOT; AEP Texas, TNMP, co-ops | Closed-loop liquid cooling and dry cooler yards with small makeup water |
| El Paso and much of the Panhandle | Outside ERCOT; the serving utility’s own interconnection rules | Dry climate equipment selection; strongest freeze design in the state on the high plains |
Data center construction: Dallas and the DFW suburbs
Data center construction Dallas owners face combines a large-campus scale with the city-by-city code patchwork of North Texas: Dallas itself adopted the 2021 International Building and Mechanical Codes with amendments effective May 12, 2023, and each surrounding city adopts its own edition. Data center construction DFW-wide also means winter design, because North Texas freezes hard enough to split unprotected dry cooler coils and tower makeup lines.
Data center construction: Houston and the coast
Data center construction Houston developers undertake brings humidity, storms and the Uniform Mechanical Code that the city adopted with amendments in January 2024. Yard equipment sits above flood elevations and is anchored for wind, and the cooling plant is placed on generator power in full, since a Gulf storm can keep utility power off for days.
Data center construction: West Texas and the plains
Data center construction West Texas campuses favor is built around water. Dry air helps dry coolers and adiabatic assist, and large campuses there use closed-loop, non-evaporative liquid cooling, so the mechanical package is dominated by yard piping, dry cooler arrays, CDU skids and glycol systems rather than towers.
Texas data center legislation and directives that reach the mechanical schedule
Texas data center legislation and executive directives since 2025 reach the mechanical schedule because they decide when a campus can connect, which permits it can obtain, and what it must report about water and backup power. Senate Bill 6 set the framework in 2025, the Public Utility Commission adopted its interconnection rule in September 2026, and the governor issued a series of directives in August and September 2026.
| Rule or directive | What it does | Effect on the mechanical package |
|---|---|---|
| SB 6 (2025) | Large loads above 75 MW: disclosure, study fee of at least $100,000, backup generation reporting, curtailment for loads connected after December 31, 2025 | Cooling restart sequences on generator power; CDU pumps on uninterruptible power; integrated curtailment tests |
| PUCT rule, Project 58481 (September 18, 2026) | Standard interconnection terms for loads of 75 MW or more; flat $100,000 study fee | Realistic cooling load figures needed early in the interconnection request |
| ERCOT Batch Zero pause (August 2026) | Classification and study paused; data centers of 75 MW or more held from energizing until verification | Mechanical completion may precede permanent power; commissioning planned on temporary power |
| TWDB directive (September 14, 2026) | Enforcement of water-use reporting by major users, including data centers | Metering of tower makeup and blowdown designed in; water budget documented |
| TCEQ directive (September 21, 2026) | Halt on permits sought by data centers until ERCOT and TWDB audits are complete | Generator and water permits become critical-path dates; mechanical work sequenced to keep moving |
Paul Industries tracks those dates with the owner and builds the mechanical schedule so that work that needs no permit or energization, such as prefabrication, underground and yard piping, equipment setting and pressure testing, proceeds while the state processes run. When dates move, the sequence moves with them rather than leaving finished equipment idle.
Tax incentives for data centers in Texas and the mechanical equipment list
Tax incentives for data centers in Texas center on a state sales and use tax exemption for qualifying data centers, and the Comptroller lists cooling systems, electrical systems, emergency generators, racks and the mechanical systems needed to operate them among eligible items. A qualifying data center needs at least 100,000 square feet used by a single occupant, a commitment of $200 million in capital investment within five years and 20 qualifying jobs in the county; a qualifying large data center project needs 250,000 square feet, $500 million and 40 jobs.
The exemption covers the state’s 6.25 percent sales and use tax, while city and county sales taxes still apply, and it runs 10, 15 or 20 years depending on the program and investment. For the mechanical contractor, the practical effect is documentation: equipment and materials that qualify are invoiced and recorded so the owner can support the exemption at the Comptroller’s five-year audit. Paul Industries separates qualifying equipment on its schedules of values and keeps the records the owner’s tax filings rely on.
Utilities, grids and the date a Texas campus gets permanent power
The utility serving a Texas campus sets the path to permanent power: inside ERCOT’s competitive areas, Oncor, CenterPoint Energy, AEP Texas and TNMP own the wires, municipal utilities such as Austin Energy and CPS Energy serve their own territories, electric cooperatives serve much of rural Texas, and El Paso, much of the Panhandle and parts of East Texas lie outside ERCOT altogether. Each has its own process and timetable, layered under ERCOT’s large-load rules for sites inside its grid.
The mechanical schedule follows that date. Chillers and pumps need permanent power to run at full load, so a campus whose energization slips will finish mechanical installation and testing on construction power and wait for the integrated test. The testing approach used in that situation is described on data center commissioning in Texas.
Campuses built beside existing power plants follow a further step. SB 6 requires notice to ERCOT before a new large load is net metered with a stand-alone generator registered as of September 1, 2025; ERCOT studies the arrangement and reports within 120 days, and the Public Utility Commission then has 60 days to approve, deny or attach conditions. For the mechanical package, a co-located site often brings shared infrastructure into the design, such as raw water supply, fuel gas service and heat rejection close to the plant boundary, and Paul Industries lays out those interfaces with the owner so the cooling plant is ready whichever way the approval goes.
Codes, licensing rules and wage law on a Texas mechanical package
Codes and licensing rules on a Texas data center mechanical package come mostly from cities and state licensing law rather than a statewide building code: Texas law makes the International Building Code the municipal commercial building code but leaves editions and amendments to each city, while the Texas Department of Licensing and Regulation regulates air conditioning and refrigeration contracting under Occupations Code Chapter 1302 and boilers under Health and Safety Code Chapter 755.
| Requirement | Source | What it means for the work |
|---|---|---|
| Building and mechanical code | City adoption; state municipal law (section 214.216) names the IBC as the commercial building code | Dallas works under the 2021 IMC, Houston under the 2021 UMC; editions and amendments vary elsewhere |
| Air conditioning and refrigeration contracting | Occupations Code Chapter 1302, TDLR | Class A environmental endorsement covers equipment of any size; Class B is limited to 25 tons of cooling |
| Boilers | Health and Safety Code Chapter 755, TDLR Boiler program | State certificate inspection on a 12, 24 or 36 month cycle set by boiler type, wherever a boiler is part of the plant |
| Energy code | IECC under Health and Safety Code 388.003, with city amendments | Economizer, fan power and commissioning requirements depend on the adopted edition |
| Wages | Government Code Chapter 2258 applies to public works | Privately funded data centers carry no state prevailing wage schedule |
| Piping | ASME B31.9 or B31.3 by owner specification | Weld examination and pressure test criteria follow the specified code |
Phasing data center construction in Texas on the mechanical side
Phasing data center construction in Texas on the mechanical side starts with the yard and underground mains, because the central plant and the large-bore piping that serves every building take the longest to build and must be in place before the first hall can be tested. Halls then follow in sequence, each tied into valved, capped branches left on the mains for that purpose, so later buildings connect without shutting down the plant serving live halls.
Prefabrication carries most of the Texas schedule. Pipe rack modules, pump skids, CDU manifolds and spool sections built off site to a repeating design are delivered in the order the halls need them, which cuts field welding and keeps quality consistent across a campus of identical buildings. Paul Industries builds the prefabrication plan from the engineer’s drawings once the design is fixed for the first building, and repeats it with revisions captured for each later phase. Each prefabricated piece carries a tag that ties it to its drawing, weld records and pressure test, so it goes into the right place in any later phase and the owner’s turnover file traces every spool back to its inspection. Prefabricated spools and racks are covered further on process piping in Texas and the welding behind them on industrial welding services in Texas.
Water metering and drought rules in the mechanical design
Water metering and drought rules belong in the mechanical design of a Texas campus because the state now expects large users to report what they draw, and a mid-September 2026 directive told the Water Development Board to make data centers and other big water users file those reports. A cooling plant that evaporates water in towers draws continuously, and the owner needs to know how much goes to makeup, how much leaves as blowdown, and how much is lost to drift.
Paul Industries designs metering into the plant from the start: makeup meters at each tower or tower cell, blowdown meters at the discharge, meters on any reclaimed water supply, and connections from all of them to the building management system so reports come from recorded data rather than estimates. Where a city’s drought plan can restrict water use, the mechanical design gives the owner a second mode, such as dry coolers or adiabatic units that carry the load at reduced water draw, and the controls sequence for switching between them. Sites served by reclaimed water get separate, labeled piping and backflow protection to the serving utility’s requirements.
Standby generation, fuel and gas piping on Texas campuses
Standby generation on a Texas campus reaches the mechanical scope because SB 6 requires large loads to disclose on-site generation able to serve at least half of their demand, and because some campuses back up their halls with natural gas generation as well as diesel engines. The operator of the large campus at Abilene, for example, described gas turbines that serve as backup power in place of a diesel fleet in its 2025 fact sheet.
For the mechanical contractor, that means fuel systems: natural gas piping from the utility meter to turbines or engines, sized for full simultaneous load and tested to its code, and diesel supply and return piping between storage tanks and day tanks where engines burn diesel. It also means the cooling plant’s own load on that generation, because chillers, pumps and tower fans all draw from the same generators during a curtailment. Paul Industries builds the fuel piping with the rest of the mechanical package and documents its tests with the cooling plant records, so one turnover covers both.
Protecting installed equipment on Texas sites before startup
Protecting installed equipment on a Texas site before startup is a real schedule item in 2026, because chillers, pumps and CDUs may sit set and piped for months while energization or permits catch up. Each environment brings its own risk: blowing dust on the West Texas plains clogs coils and open piping ends, Gulf Coast humidity corrodes unprotected electrical components and bare steel, summer sun degrades exposed insulation and gaskets, and a winter freeze can split a water-filled test section that was left undrained.
Paul Industries keeps equipment under the manufacturers’ storage and preservation instructions until startup: capped pipe ends, desiccant and heaters in electrical enclosures, periodic shaft rotation on pumps and fans, drained or glycol-filled test sections over winter, and documented inspections that keep warranties intact. Chillers held for long periods get the manufacturer’s holding charge and pressure checks, motors are meggered before first start, and CDU and pump seals are inspected for drying. When energization arrives, the plant starts from a known condition rather than a surprise, and the storage log becomes part of the turnover file, showing the owner and the equipment manufacturers how each machine was kept from setting to startup.
What does a Texas data center mechanical package cost?
A Texas data center mechanical package costs what its capacity, redundancy, heat rejection type and phasing make it cost: the tonnage of chillers or dry coolers, the length and diameter of the mains, the number of CDUs and manifolds, freeze and storm protection, and how much is prefabricated. In 2026, schedule risk from energization and permit dates is also a cost driver, because idle equipment and resequenced work both cost money.
Two Texas factors pull the other way. Industrial power cheaper than the national average shortens nothing on the installed cost but reduces operating cost, and the state sales tax exemption, available to qualifying sites that commit at least $200 million in investment, removes the state’s 6.25 percent tax from qualifying equipment. Paul Industries prices the mechanical package from the drawings and equipment list, beginning with a budget figure based on comparable Texas campuses and moving to a fixed price when the design is complete.
Who installs chiller plants and piping for Texas data centers?
Paul Industries installs chiller plants and piping for Texas data centers, setting chillers, towers and dry coolers, building chilled water and condenser water mains, piping CDUs and row manifolds, fabricating spools and racks, and testing and starting the plant. Owners comparing data center construction companies in Texas for the mechanical package look for one contractor who carries the yard, the mains and the hall together; Paul Industries is that contractor; headquartered at 256 Shore Drive, Kilmarnock, Virginia, it takes Texas data center work statewide as well as across the 50 states.
Among data center contractors in Texas, Paul Industries’ scope reaches past the hall into the plant equipment itself, covered on data center cooling in Texas, data center liquid cooling in Texas and chiller repair in Texas. The same mechanical work is delivered in Paul Industries’ headquarters state on data center mechanical contractor in Virginia and in another fast-growing market on data center mechanical contractor in Georgia.
Paul Industries on Texas data center campuses
Paul Industries delivers mechanical packages for Texas data center campuses, from a single hall expansion to a multi-building site with a central plant, prefabricated racks and liquid cooling. Send the drawings or basis of design, the phasing plan, the target energization date, the serving utility and the site location. Call 201-450-8280 or request a quote. More Texas services are on the Texas page and the neighboring states on the Southwest page.
Standards referenced: Texas SB 6 (2025), Utilities Code 37.0561, 39.169 and 39.170 · PUCT large-load interconnection rule, Project 58481 · Texas Tax Code 151.359 and 151.3595 (qualifying data centers) · Texas Occupations Code Chapter 1302 (air conditioning and refrigeration) · Texas Health and Safety Code Chapter 755 (boilers) · Texas Government Code Chapter 2258 (public works wages) · International Building Code as the municipal commercial code (Texas section 214.216) and city-adopted mechanical codes · ASME B31.9 · ASME B31.3
Frequently asked questions
Which contractor builds data center mechanical systems in Garland, Plano, Midlothian and Red Oak?
Paul Industries builds data center mechanical systems across North Texas, including Garland, Plano, Richardson, Allen, Fort Worth, Midlothian and Red Oak. Each city adopts its own code edition, so Paul Industries confirms the adopted mechanical code before procedures are written, and designs yards for North Texas freezes as well as July heat.
Who builds data center mechanical packages in Houston, Katy and Baytown?
Paul Industries builds data center mechanical packages in Houston, Katy, the Energy Corridor, Pasadena and Baytown. Houston works under the 2021 Uniform Mechanical Code with city amendments, and Gulf Coast yards are designed for wind, flood elevation and humidity, with generator coverage of the full cooling load for storm outages.
Who installs data center cooling plants in San Antonio, Austin and Taylor?
Paul Industries installs chiller plants, dry cooler yards and CDU piping for data centers in San Antonio, Austin, Round Rock, San Marcos and Taylor. Central Texas sites balance efficient towers against drought rules, and municipal utilities such as CPS Energy and Austin Energy set energization steps inside ERCOT.
Does Paul Industries build mechanical packages for campuses in Abilene, Amarillo and El Paso?
Yes. Paul Industries builds mechanical packages for campuses on the West Texas plains, the Panhandle and El Paso. Those sites lean on dry coolers and closed-loop liquid cooling to save water, need strong freeze protection on the high plains, and in El Paso and much of the Panhandle interconnect outside ERCOT under the serving utility’s rules.
Who is building data centers in Texas?
Hyperscale cloud operators, colocation developers, research institutions and large single-tenant computing campuses are all building data centers in Texas, and ERCOT reports that about 70 percent of large loads asking to connect are data centers. On the mechanical side, Paul Industries builds the chiller plants, yards, mains and CDU piping those campuses need.
Are data centers banned in Texas?
Texas has no statewide ban. In 2026 the state did pause key approvals: ERCOT held energization of data centers of 75 megawatts or more pending its verification, and the governor directed TCEQ to halt permits sought by data centers until ERCOT and Water Development Board audits finish. Construction continues on sites with their approvals in hand.
Do data centers in Texas pay taxes on cooling equipment?
Qualifying data centers approved by the Comptroller are exempt from the state’s 6.25 percent sales and use tax on eligible items, which the Comptroller says include cooling systems, electrical systems, emergency generators and racks. City and county sales taxes still apply, and property taxes are a separate matter. Sites outside the program pay sales tax on mechanical equipment in the normal way.
How many data centers are under construction in Texas, and how does that affect mechanical schedules?
Data centers under construction in Texas span every major metro and the West Texas plains, with ERCOT tracking hundreds of large-load requests. For mechanical schedules, the volume means long equipment lead times for chillers, switchgear-dependent startups and energization queues, so Paul Industries orders long-lead equipment early and sequences work that needs no permanent power first.
What does the SB 6 study fee mean for a Texas data center owner?
SB 6 requires a study fee of at least $100,000 for a large-load interconnection, and the PUCT’s September 2026 rule set a flat $100,000. The fee itself is small next to the campus cost, but the request needs credible load figures, including cooling load at full build-out, which Paul Industries estimates from the mechanical basis of design.
Do Texas data center mechanical contracts carry prevailing wage rates?
Texas prevailing wage law in Government Code Chapter 2258 applies to public works paid for with public money. Privately funded data centers carry no state prevailing wage schedule, although public or federally funded components of a project can bring their own wage rules, which the contract documents state.
Which TDLR license class covers large data center chillers?
Texas regulates air conditioning and refrigeration contracting under Occupations Code Chapter 1302 through TDLR. The Class A environmental air conditioning endorsement covers equipment of any size or capacity, while Class B is limited to 25 tons of cooling and 1.5 million Btu per hour of heating, so data center chiller work falls in Class A territory.
Can a Texas data center choose its electric utility?
The site’s location decides. Inside ERCOT’s competitive areas, the wires utility is fixed by territory, such as Oncor, CenterPoint, AEP Texas or TNMP, while the retail supplier is chosen. Municipal utilities and cooperatives serve their own territories, and areas outside ERCOT follow their utility’s own rules. The utility sets energization steps the mechanical schedule follows.
How does Paul Industries keep work moving when a Texas permit or energization date slips?
Paul Industries resequences around the date: prefabrication, underground and yard piping, equipment setting, pressure testing and flushing proceed without permits for generators or permanent power, while startups and integrated tests move to follow the new date. The owner sees the revised sequence and its cost effect before work changes.
Is design-build available for a Texas data center mechanical package?
Yes. Paul Industries offers design-build mechanical packages, design-assist on owner-engineered projects, complete installation to issued drawings, and supply of equipment and prefabricated spools. Design-build suits owners who want the plant, yard and hall piping under one contract with a single schedule.
Can new buildings be added to a live Texas campus without shutting down its cooling?
Yes, when the mains were built with valved, capped branches for future buildings. Where they were not, Paul Industries adds connections with hot taps or line stops under a written method of procedure, confirming redundancy on the plant before each step and testing the new branch before it opens to the live loop.
What drawings and schedules start a Texas data center mechanical estimate?
The estimate starts from the drawings or basis of design, the phasing plan, equipment schedules, the target energization date, the serving utility and the site address. Paul Industries returns a budget figure based on comparable Texas campuses and then a fixed price when the design is final.
Does a Texas data center cooling plant need water meters for state reporting?
Metering is the practical way to meet the reporting the Texas Water Development Board is now enforcing for major water users, including data centers. Paul Industries installs makeup, blowdown and reclaimed water meters on cooling plants and connects them to the building management system, so the owner reports measured figures for each tower and supply.
Does Paul Industries install natural gas and diesel piping for data center generators in Texas?
Yes. Paul Industries installs natural gas piping to turbines and engines and diesel supply and return piping between storage and day tanks, sized for full simultaneous load and tested to the applicable code. The fuel piping is documented with the cooling plant records, so the owner holds one set of turnover records for both.