Paul Industries is a data center mechanical contractor in Georgia, building chiller plants, closed-loop and liquid cooling systems, yard and data hall piping, CDU loops and generator fuel systems for campuses in metro Atlanta, Douglas, Newton and Butts counties and along the coast near Savannah. Georgia data centers are planned around three limits that shape the mechanical design: water in a drought-prone basin, power delivered under Georgia Power’s large-load rules, and a sales tax exemption that sets what counts as equipment. Paul Industries designs, prefabricates, supplies, installs, tests and starts up the mechanical scope, and services it after turnover.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Market Metro Atlanta: second in North American data center construction capacity (CBRE, 2026)
Equipment tax exemption O.C.G.A. 48-8-3(68.1), through December 31, 2031
Large-load power Georgia Power customers over 100 MW: contracts up to 15 years (PSC, 2025)
Cooling water Closed loop 5,000 to 50,000 gal/day vs evaporative up to 9 million (metro Atlanta, 2026)
Reviewed November 2026

What a data center mechanical contractor in Georgia builds

A data center mechanical contractor in Georgia builds the systems that move heat from the IT load to the outdoors: chillers, dry coolers and towers in the yard, chilled water and condenser water mains, data hall distribution, coolant distribution units and the secondary loops that feed direct liquid cooling, plus the fuel, water and drainage systems around the plant. On a Georgia campus the same contractor also lives with the state’s permits, inspections and water rules from the first yard pour to the last balancing report.

On many Georgia campuses the owner buys the long-lead equipment, chillers, dry coolers, CDUs and generators, and the mechanical contractor receives, sets, connects, tests and starts it, alongside the piping, pumps, valves, supports, insulation and instrumentation the contractor furnishes. Controls points, power connections and fire protection meet the mechanical scope at defined interfaces, and those interfaces are where schedules slip if they are left vague. Paul Industries writes each interface into the scope at the start: who sets the sensor, who lands the wire, who proves the sequence, and which test record closes the item, so every party on the campus works from the same list.

The general picture of the trade, from design inputs to weld examination, is on the national data center mechanical contractors page, and the sector view on data centers. This page goes into Georgia: where data centers in Georgia are going, how water and power shape the cooling plant, the exemption and code rules that touch the mechanical budget, and how the work is phased through a Georgia summer.

Where are data centers in Georgia, and where are new ones going?

Data centers in Georgia are concentrated in metro Atlanta, which the Metropolitan North Georgia Water Planning District, citing CBRE, ranked second in North America for data center construction capacity in 2026, with new campuses spreading south and east into larger tracts of land and toward the coast. Data centers in metro Atlanta began on the west side, and that corridor still carries some of the state’s oldest hyperscale sites. A map of data centers in Georgia shows the pattern plainly: a dense ring around the city, a band of newer campuses to the south and east, and a few very large coastal plans.

Data centers in Atlanta proper are mostly colocation and enterprise buildings on smaller urban sites, with rooftop or podium heat rejection, while the suburban counties take the campus-scale builds. The two kinds of site ask different things of the mechanical contractor: dense urban sites reward prefabrication and crane planning, and suburban campuses reward yard design that leaves room for buildings five or ten years out.

Google data centers in Georgia include the Douglas County campus, built in 2007, which cools with recycled municipal wastewater treated at a sidestream plant run with the Douglasville-Douglas County Water and Sewer Authority. Amazon Web Services announced about $11 billion for Butts and Douglas counties in January 2025. Meta broke ground in 2018 at Stanton Springs in Newton County, near Covington and Social Circle. On the coast, OpenAI’s Project Camellia in Effingham County is planned for 3.2 gigawatts of Georgia Power supply delivered in phases from 2028 to 2032. These are market facts about where hyperscale data centers in Georgia have landed; each region brings its own mechanical conditions.

Georgia data center regions and what each means for the mechanical scope
RegionPattern of developmentMechanical consequence
West metro: Douglas, Fulton and CobbEstablished campuses and expansions beside operating hallsTie-ins to live loops, work under method of procedure, reclaimed water treatment on towers
East metro: Newton, Rockdale and WaltonLarge greenfield tracts and multi-building campusesCentral plants and yard mains sized for later buildings, long buried runs
South metro: Butts, Henry, Fayette and SpaldingNew campuses on larger parcels away from the coreWater and power arrive in phases, so plants are staged to match
Coastal: Effingham, Bryan and ChathamGigawatt-scale plans near the Port of SavannahSalt air on outdoor equipment, high water table, hurricane wind loads on yard equipment
Columbus, Augusta, Macon, Rome and DaltonSingle buildings and enterprise sitesSmaller plants, often air-cooled chillers or packaged units with economizers

New data centers in Georgia and the shift to closed loops

New data centers in Georgia are being designed with far less evaporation than the first generation, because water has become the constraint that planners, counties and utilities ask about first. The water planning district reported in 2026 that metro Atlanta proposals had requested as much as 9 million gallons a day for evaporative cooling, while closed-loop designs typically asked for 5,000 to 50,000 gallons a day, and that developments were shifting to closed loops. That shift moves the mechanical scope toward air-cooled chillers, dry coolers with adiabatic assist, larger heat rejection yards and more glycol, and it raises the electrical load the cooling plant puts on the substation.

How drought and water permits shape Georgia cooling plants

Drought and water permits shape Georgia cooling plants because metro Atlanta has one of the smallest surface water supplies of any large American metro, and the state’s environmental regulator, the EPD, moved all of Georgia to a Level 1 drought response in late April 2026. A campus that draws more than a monthly average of 100,000 gallons a day of surface water directly needs an EPD withdrawal permit; a campus on a city or county system draws under that utility’s permit, and the utility decides how much it can supply.

For the mechanical contractor, the water decision changes the equipment list, the yard layout and the commissioning plan. Evaporative towers need makeup, blowdown, chemical treatment and drift control; dry coolers need more surface area and fan power; adiabatic systems need a smaller, intermittent water supply and its own treatment. Where a campus uses reclaimed water, as Google’s Douglas County site does, the tower water chemistry is tighter and the makeup system carries filtration and disinfection of its own, which Paul Industries builds and connects alongside cooling tower water treatment. Reporting on the Effingham County project in 2026 put its planned water use at about 30,000 gallons a day, a figure only a closed-loop design reaches.

Heat rejection choices for a Georgia data center and their trade-offs
ApproachWater useEnergy and spaceGeorgia consideration
Water-cooled chillers with open towersHighest; evaporation plus blowdownLowest chiller energy, compact yardHardest to permit in a drought year; reclaimed water possible where a utility supplies it
Air-cooled chillers with free cooling coilsClose to noneHigher energy on July afternoons, larger yardFree cooling hours concentrate in winter months; summer peaks set the size
Closed-loop dry coolers with adiabatic assistIntermittent, on peak days onlyMore fans and surface areaPads or sprays run during humid heat, when evaporation helps least
Direct liquid cooling with warm-water loopsLow, depending on heat rejectionWarmer supply raises dry cooler hoursCDU and secondary loop cleanliness become the critical installation tasks

Georgia Power data center rules and the mechanical schedule

Georgia Power data center rules affect the mechanical schedule because power, not steel, now sets the order in which halls come online. In January 2025 the Georgia Public Service Commission approved rules for new Georgia Power customers above 100 megawatts that allow contracts of up to 15 years, minimum bills, and recovery of the utility’s costs to serve the customer if a contract ends early, with each contract filed with the Commission at least 30 days before it takes effect. In December 2025 the Commission approved about 9,885 megawatts of new Georgia Power resources, most of it for large customers such as data centers.

The mechanical plan follows the power plan. When megawatts arrive in blocks, the central plant is built so that chillers, pumps and heat rejection can be commissioned in the same blocks, with headers, valves and blind flanges in place for the units that follow. Georgia’s Territorial Electric Service Act adds a choice that shapes early design: a new premises with a connected load of 900 kilowatts or more, serving one consumer through one meter outside a city’s limits, has a one-time choice of electric supplier, which can be Georgia Power or the electric membership corporation serving the area. The supplier decision sets the substation timetable, and the substation timetable sets when chillers can be started under load. At 7.21 cents per kilowatt-hour for industrial customers in 2024, below the national 8.13 cents reported by the EIA, Georgia power keeps cooling energy affordable; it still matters to the owner, but delivery dates usually matter more to the schedule.

Are data centers tax exempt in Georgia?

Data centers in Georgia are not exempt from tax as a whole, but qualifying high-technology data centers can buy their equipment free of state sales and use tax under O.C.G.A. 48-8-3(68.1), and the Department of Revenue’s Rule 560-12-2-.117 lists emergency backup generators, air handling units, cooling towers and energy storage among the qualifying hardware. Real property is excluded, so the boundary between equipment and the building runs straight through the mechanical scope.

The Georgia data center sales tax exemption has survived two challenges. In May 2024 Governor Kemp vetoed a bill that would have paused it, and in the 2026 session bills to repeal it or end it early failed. The rule ties the exemption to a seven-year investment period ending no later than December 31, 2031, and to investment and job thresholds that depend on county population.

Investment and job thresholds for the Georgia exemption (applications on or after May 9, 2022)
County populationQualifying aggregate expendituresAverage new quality jobs
More than 50,000$250 million25
30,001 to 50,000$75 million10
30,000 or fewer$25 million5

For the mechanical budget, the practical step is a clean split. Paul Industries prices chillers, towers, air handlers, CDUs, pumps, generators and their controls as equipment lines, and embedded piping, supports, insulation and labor as installation lines, so the owner’s tax team can classify each line against the rule without unpicking a lump sum after the fact.

Which Georgia codes and permits apply to the mechanical scope?

The Georgia codes and permits on a data center’s mechanical scope start with the Georgia State Minimum Standard Mechanical Code, adopted from the 2024 edition of the International Mechanical Code with state amendments and in force from January 1, 2026, with county and city building departments issuing permits and inspecting. Plumbing, gas and fire codes follow the same state minimum standard system, and the state fire safety rules adopt NFPA standards, including NFPA 30 for the diesel fuel that backup generators store.

Several state programs reach particular parts of the plant. Georgia’s conditioned air law gives Class I contractors a scope of five tons of cooling and 175,000 BTU per hour of heating, leaving data center plants in the unrestricted Class II scope. The Boiler and Pressure Vessel Safety Act, administered by the Office of Insurance and Safety Fire Commissioner, covers vessels above its exemptions, so large expansion tanks, air and dirt separators and generator-side vessels are checked against the exemption list before installation; covered vessels need an installation permit and are inspected every three years. Generator fuel stored underground falls under the EPD’s underground storage tank program. Georgia has no state prevailing wage law, so wage schedules apply only where federal funding brings in the Davis-Bacon Act.

Chilled water piping inside the building is commonly built to ASME B31.9 and process-grade CDU and secondary loops to the owner’s specification, often ASME B31.3 practice, with welding procedures and examination recorded for turnover. The welding side is described on industrial welding services in Georgia and the piping side on process piping in Georgia.

Generator fuel, water and drainage systems around a Georgia plant

Generator fuel, water and drainage systems around a Georgia data center plant are mechanical work as much as the chillers are, and each answers to its own Georgia rule. Diesel storage for backup generators follows the state fire safety standards, which adopt NFPA 30 for flammable and combustible liquids, and tanks placed underground come under the EPD’s underground storage tank program for registration, leak detection and operator training. Above-ground belly tanks and day tanks need secondary containment, venting, overfill protection and fuel polishing loops that keep stored diesel usable through years of standby.

Water and drainage follow the cooling choice. A tower plant needs makeup metering, blowdown routed to sanitary sewer under the receiving utility’s limits, and chemical feed containment; a closed-loop plant needs glycol fill, storage and recovery so a drained loop is not lost to the sewer. Storm water from the yard and condensate from air handlers are collected and, on water-limited sites, condensate is often recovered as tower or adiabatic makeup. Paul Industries builds these systems with the plant, tests them with the plant and records them in the same turnover package.

How is data center construction in Georgia phased on the mechanical side?

Data center construction in Georgia is phased on the mechanical side around power blocks, water supply and the summer: yard mains and the central plant shell go in first, chillers and heat rejection follow the substation, and data hall distribution and CDU loops are completed hall by hall as IT load is committed. Atlanta’s July normals of a 90 degree high and a 72 degree low also shape when outdoor work is efficient, so crane picks, yard welding and pressure tests are planned around afternoon heat and thunderstorms.

Prefabrication carries much of the schedule. Pipe racks, pump skids, valve stations and CDU headers are prefabricated off site in controlled conditions, then set, connected and tested in the field, which reduces outdoor welding in the hottest weeks and keeps hall work moving between rain days. Drought adds a step few owners expect: hydrostatic testing and flushing a campus loop takes large volumes of water, so the test plan sets out the source, the sequence for reusing test water between sections, and the discharge route before the first section is filled.

Mechanical phases on a Georgia data center campus
PhaseMechanical workGeorgia-specific planning point
Site and yardBuried mains, sleeves, yard supports, fuel and water servicesWater source and EPD or utility limits settled before cooling choice is frozen
Central plantChillers, pumps, heat rejection, headers sized for later blocksStart-up dates matched to the power contract’s delivery blocks
Data hall distributionMains, branches, CRAH and fan wall connections, CDU loopsPrefabricated modules reduce summer field welding
Testing and flushingHydrostatic tests, flushing, cleanliness verificationTest water sourced and reused between sections in drought conditions
Commissioning and turnoverFunctional tests, integrated systems tests, recordsPressure vessel and permit inspections closed before load is accepted

Expansion beside operating halls is a phase of its own on Georgia’s older campuses. New chillers and mains are tied into live loops through hot taps or isolation valves installed during earlier shutdowns, each tie-in runs under a written method of procedure, and the operating team watches loop pressure and temperature through every step. Commissioning ties the phases together, and the Georgia process is set out on data center commissioning in Georgia. Air and chilled water distribution design is covered on data center cooling systems in Georgia, and CDU and cold plate loops on data center liquid cooling in Georgia.

Who installs data center mechanical systems in Georgia?

Paul Industries installs data center mechanical systems in Georgia, taking central plants, yard and hall piping, CDU and liquid cooling loops, generator fuel systems and the service that follows, on campuses from Douglas, Fulton and Newton counties to Butts County, Columbus, Augusta and the Savannah coast. Headquartered at 256 Shore Drive in Kilmarnock, Virginia, Paul Industries is an East Coast contractor that works across Georgia and the Southeast, in all 50 states and at plants outside the United States.

Owners comparing data center mechanical contractors in Georgia, or data center contractors in Georgia more broadly, can take the mechanical scope three ways from Paul Industries: supply-only prefabricated racks, skids and spools; a design-build package from heat rejection to the rack; or complete installation of an engineer’s design. The same approach runs on campuses in its headquarters state, described on data center mechanical contractor in Virginia, and next door in the North Carolina data center mechanical contractor page. Chillers already in service on Georgia campuses are maintained under chiller repair in Georgia.

What does data center mechanical work in Georgia cost?

Data center mechanical work in Georgia costs what its scope, cooling choice and schedule demand, and no published figure applies across campuses. The main drivers are the heat rejection approach, the redundancy level, the share of liquid cooling, the length of yard mains, the amount of prefabrication, the number of phases and how tightly power delivery compresses each one.

Georgia adds its own items. A closed-loop or air-cooled plant costs more in equipment and electrical service and less in water infrastructure; reclaimed water brings treatment equipment; coastal sites need corrosion-resistant coatings and wind anchorage on yard equipment; and the exemption split changes how the budget should be organized. Paul Industries gives a budget range from comparable scope once the cooling concept and block sizes are known, then a firm price when drawings and the phasing plan are fixed.

Data center mechanical work from Paul Industries in Georgia

Paul Industries designs, prefabricates, supplies, installs, tests, starts up and services data center mechanical systems across Georgia, from metro Atlanta’s established corridors to the new campuses south of the city and on the coast. To price a campus phase, send the cooling concept, block sizes, one-line and P&ID drawings, the water source and the power delivery dates. Call 201-450-8280 or request a quote. Other Paul Industries services for Georgia plants and campuses are gathered on the Georgia page.

Standards referenced: O.C.G.A. 48-8-3(68.1) and Rule 560-12-2-.117 (high-technology data center equipment) · Georgia State Minimum Standard Mechanical Code (2024 IMC with Georgia amendments) · O.C.G.A. 43-14 (conditioned air contractors) · Georgia Boiler and Pressure Vessel Safety Act, O.C.G.A. 25-15-10 et seq., and Rules 120-3-26 · Georgia State Minimum Fire Safety Standards, Rules 120-3-3 (NFPA 30) · Georgia EPD Underground Storage Tank rules, Chapter 391-3-15 · Georgia EPD water withdrawal rule 391-3-6-.07 · Georgia Territorial Electric Service Act · ASME B31.9 · ASME B31.3 · ASHRAE TC 9.9 thermal guidelines

Frequently asked questions

Which contractor builds data center mechanical systems in Douglas County, Lithia Springs and Douglasville?

Paul Industries builds data center mechanical systems in Douglas County, including Lithia Springs and Douglasville, where some of Georgia’s longest-running campuses expand beside operating halls. Work there is largely tie-ins to live chilled water and condenser loops under written methods of procedure, plus new plants for added buildings. Paul Industries prefabricates headers and valve stations off site so each live connection takes the shortest possible window.

Does Paul Industries take data center mechanical work near Covington, Social Circle and Newton County?

Paul Industries takes data center mechanical work near Covington, Social Circle and across Newton, Walton and Rockdale counties, where large tracts host multi-building campuses. Those campuses need central plants and yard mains sized for buildings that come later, with valves and capped branches in place so each new hall connects without draining the loop. Send the master plan and block schedule to start pricing.

Who handles data center construction in Atlanta on the mechanical side?

Paul Industries handles the mechanical side of data center construction in Atlanta and across Fulton, Cobb, DeKalb and Gwinnett counties: chiller plants, chilled water mains, data hall piping, CDU loops and fuel systems. Urban sites tend to be tighter, with rooftop heat rejection, shorter yard runs and more crane planning, so prefabricated modules and careful sequencing carry more of the schedule than on suburban campuses.

Does Paul Industries build data center plants near Savannah, Effingham and Bryan counties?

Paul Industries builds data center plants near Savannah and in Effingham, Bryan and Chatham counties. Coastal sites bring salt air, a high water table and hurricane wind loads, so yard equipment needs coatings suited to marine air, anchorage designed for wind, and buried piping planned around groundwater. Those items are priced into the mechanical package from the start rather than added after design.

Who is building data centers in Georgia in 2026?

The companies building data centers in Georgia in 2026 include hyperscale operators such as Amazon Web Services in Butts and Douglas counties, Meta at Stanton Springs in Newton County, Google in Douglas County and OpenAI’s Project Camellia in Effingham County, along with colocation developers around metro Atlanta. Paul Industries builds the mechanical systems for campuses of this kind, and the operators are named here as market facts.

Are data centers tax exempt in Georgia, and does the exemption cover cooling equipment?

Qualifying high-technology data centers buy equipment free of Georgia sales and use tax under O.C.G.A. 48-8-3(68.1). The Department of Revenue rule lists emergency backup generators, air handling units, cooling towers and energy storage among qualifying hardware and excludes real property. The exemption runs through December 31, 2031, after repeal bills failed in the 2026 session. Paul Industries splits equipment and installation lines so each can be classified.

How many data centers under construction in Georgia use closed-loop cooling?

The state publishes no count by cooling type, but the Metropolitan North Georgia Water Planning District reported in 2026 that metro Atlanta developments were shifting to closed-loop cooling, with typical requests of 5,000 to 50,000 gallons a day against as much as 9 million for evaporative designs. Among data centers under construction in Georgia, closed loops and dry coolers are now the expected starting point for a water-limited site.

What does Georgia Power's 100 megawatt rule mean for chiller staging?

Georgia Power’s large-load rule for customers above 100 megawatts brings contracts of up to 15 years and minimum bills, and power is often delivered in blocks. Chiller staging follows those blocks: the plant is built with headers, valves and pads for later units, and each block of chillers, pumps and heat rejection is commissioned when its power arrives, so the owner pays for running capacity only as load grows.

Can a Georgia data center choose between Georgia Power and an EMC?

A Georgia data center can choose its electric supplier once when it is a new premises with a connected load of 900 kilowatts or more, serving one consumer through one meter outside a city’s limits, under the Territorial Electric Service Act. The choice is between Georgia Power and the electric membership corporation serving the area. It matters to the mechanical schedule because the supplier sets the substation timetable that chiller start-up depends on.

Does a data center in Georgia need an EPD water withdrawal permit?

A data center in Georgia needs an EPD withdrawal permit when it draws more than a monthly average of 100,000 gallons a day directly from surface water. Most campuses buy water from a city or county system instead, which holds the permit and decides how much it can supply. The answer affects whether evaporative towers are possible at all, so it is settled before the cooling plant is designed.

How do data center contractors in Georgia handle hydrostatic testing during a drought?

Data center contractors in Georgia handle hydrostatic testing during a drought by planning the water as carefully as the pressure. Paul Industries sets out the water source, the order in which sections are tested so test water can be moved and reused, the treatment needed to keep it clean, and the approved discharge route, all before the first section is filled. Flushing volumes are planned the same way.

Are expansion tanks and air separators inspected under Georgia's pressure vessel law?

Expansion tanks, air and dirt separators and similar vessels on a Georgia data center fall under the Boiler and Pressure Vessel Safety Act when they exceed its exemptions, such as the limit of five cubic feet at 250 psig or working pressures of 15 psig or less. Covered vessels need an installation permit and a triennial inspection. Paul Industries checks each vessel against the exemption list during submittals.

Do Georgia data center mechanical contracts carry state wage rates?

Georgia has no state prevailing wage law, so a privately funded data center’s mechanical contract carries no state wage schedule. Federal Davis-Bacon rates apply only where federal funding is involved, which is uncommon for private data centers. Labor pricing on a Georgia campus therefore follows the project’s own schedule, shift pattern and prefabrication plan, which Paul Industries sets out in its proposal.

How do Georgia summers affect mechanical installation on a data center campus?

Georgia summers affect mechanical installation through heat, humidity and afternoon thunderstorms, with Atlanta’s July normals at a 90 degree high and a 72 degree low. Paul Industries shifts outdoor welding, crane picks and yard pressure testing toward mornings, protects open piping from storm water, and moves as much fabrication as possible off site, so hot afternoons are spent on indoor hall work rather than exposed yard work.

Which data center construction companies in Georgia handle the mechanical yard and the data hall together?

Paul Industries is among the data center construction companies in Georgia that handle the mechanical yard and the data hall together, from chillers, dry coolers and buried mains to hall distribution, CDU loops and fuel systems. Holding both under one contract keeps the interface between yard and hall, where flushing, testing and cleanliness are most often lost, inside one schedule and one set of records.

Does Paul Industries offer design-build mechanical packages for Georgia data halls?

Paul Industries offers design-build mechanical packages for Georgia data halls, from heat rejection selection through CDU loops, as well as supply-only prefabricated racks, skids and spools and complete installation of an engineer’s design. Design-build suits owners who want the cooling concept matched to Georgia water and power limits early; complete installation suits owners whose design team has already fixed the systems.

How should a coastal Georgia data center protect yard equipment from salt air?

A coastal Georgia data center protects yard equipment from salt air with coil coatings rated for marine exposure, stainless or coated fasteners and supports, sealed electrical enclosures, and a maintenance plan that includes regular coil washing. Equipment selection matters most: coil and fin construction chosen for the coast lasts far longer than standard inland construction near Savannah and the Port.

Which drawings and schedules help Paul Industries price a Georgia data center mechanical package?

Paul Industries prices a Georgia data center mechanical package fastest from the cooling concept, block sizes and redundancy level, mechanical plans and P&IDs, the equipment schedule with owner-furnished items marked, the water source and any utility limits, the power delivery dates by block, and the site plan with yard routing. With those, a budget range comes first and a firm price follows once phasing is fixed.

Planning a data center campus or hall in Georgia?

Tell us the cooling concept, the size of each power block, where the water comes from and when power arrives, and attach the drawings. Call 201-450-8280 or request a quote.