Paul Industries provides data center commissioning in Georgia for cooling plants and liquid cooling loops, flushing and pressure testing pipe, starting chillers, pumps, towers and coolant distribution units, running functional performance tests and carrying the mechanical side of integrated systems tests for halls from metro Atlanta to Savannah. Georgia’s codes call the core of this work functional performance testing, send larger pressure vessels to the state’s boiler inspectors, and tie generator test runs to air permit conditions. Paul Industries plans each test around those Georgia rules and hands the owner the records that prove it.
Request a quote or call 201-450-8280
How does data center commissioning in Georgia fit the permit?
Data center commissioning in Georgia fits inside the Georgia State Minimum Standard Codes, a set of mandatory codes adopted by the Department of Community Affairs that apply statewide, with each county or city deciding whether to enforce them through its own inspectors. A county that enforces must use the latest editions and the Georgia amendments DCA has adopted, must write its own administrative procedures, and must send any amendment of its own to DCA for review. In practice, the inspections, test witnesses and paperwork a hall faces in Douglas County can differ from those in Fayette, Newton or Fulton County, even though the technical codes are the same.
That split shapes the commissioning plan. The general sequence of levels, test scripts and turnover is set out on the data center commissioning page. On a Georgia project, Paul Industries adds the county’s inspection steps, the state boiler inspector’s certificate visits, the energy code’s functional performance testing and the air permit’s generator conditions to that sequence, so no inspection waits on a test that has not run and no test runs before the permit that governs it.
| Code or rule | Edition or authority in force | What it asks of testing and start-up |
|---|---|---|
| Georgia State Minimum Standard Energy Code | 2015 IECC with Georgia Supplements and Amendments | Functional performance testing of mechanical systems, balancing and documentation under Section C408 |
| Mechanical code | 2024 IMC with Georgia Amendments, January 1, 2026 | Hydronic pressure test; tower listing and efficiency; pressure vessels referred to state law |
| Building code | 2024 IBC with Georgia Amendments | Permit, special inspections and certificate of occupancy steps set by the county |
| Fire code | 2024 IFC under the State Fire Marshal | Fuel storage, generator rooms and fire protection acceptance tests |
| Boilers and pressure vessels | O.C.G.A. Title 25, Chapter 15; Rules 120-3-26 | State inspection and certificate before vessels outside the exemptions operate |
| Air quality | Georgia EPD, Rule 391-3-1-.02(2)(mmm) and the facility permit | Generator run hours and conditions during load bank and integrated tests |
What energy code does Georgia use, and what does it say about commissioning?
The current Georgia energy code for commercial buildings is the 2015 International Energy Conservation Code with Georgia Supplements and Amendments, updated by amendment packets in 2020, 2022 and 2023, and its compliance software path lets a designer choose either the 2015 IECC or ASHRAE 90.1-2013. The commissioning section of that code, C408, applies to mechanical systems in any building with 480,000 Btu per hour or more of cooling or 600,000 Btu per hour of heating, which takes in every data hall of any size.
The Georgia energy code amendments make one change that every commissioning plan in the state should reflect: they strike the words commission and commissioning throughout C408 and replace them with functional performance testing. They also delete C408.2.4.1, the model code clause that holds final inspection until the code official has received the preliminary report. The Georgia commercial energy code still requires the plan, the balancing, the testing and the documentation; it simply names the activity by what it proves, so energy code commissioning requirements in Georgia read as functional performance testing requirements. Owners should expect permit reviewers and inspectors in Georgia to use that term, and the test reports Paul Industries delivers are titled to match it.
Georgia energy code requirements beyond C408
Two more requirements in the state energy code bear on a data hall. Georgia’s amendments exempt computer room applications from the economizer requirement, so the commissioning plan tests an economizer only when the owner chose to build one. And chilled water plants with more than one chiller must reduce flow automatically through the plant when a chiller shuts down, which becomes a functional test step: stage a chiller off and confirm flow drops without upsetting the loop. Georgia energy code compliance for the hall rests on those tests being run and recorded as well as designed.
Georgia building code 2026 adoption and the mechanical test
The Georgia building code 2026 adoption brought the 2024 International Mechanical Code, with Georgia Amendments, into force on January 1, 2026, alongside the 2024 building, plumbing and fuel gas codes and the 2023 National Electrical Code. Georgia deletes the IMC’s administrative Chapter 1 and leaves it as a guide, which is why test witnesses and inspection procedures come from each county’s own ordinance. The technical test for hydronic piping remains the model code test: a hydrostatic test at one and a half times the maximum system design pressure, but not less than 100 psi, held for at least 15 minutes.
Data center loops often carry their own stricter test from the engineer’s specification or the piping code it names, which on data center work is typically ASME B31.9, or ASME B31.3 when an owner applies process piping rules to its liquid cooling loops. Paul Industries runs the higher of the code test and the specification test, records pressure, duration and temperature for each section, and isolates any coolant distribution unit, cold plate manifold or instrument that is not rated for the test pressure. Failed sections are repaired, retested and logged before the county inspector is called, so the inspection is a witness of a passed test rather than a search for leaks. Hydrostatic test methods across the full range of systems are covered on the hydrostatic testing page.
Georgia boiler inspection requirements for vessels on a cooling plant
Georgia boiler inspection requirements reach a data center cooling plant through its pressure vessels: expansion tanks, buffer tanks, air and dirt separators, compressed air receivers and any boiler serving humidifiers or offices. The state’s law is O.C.G.A. Title 25, Chapter 15, with rules issued by the Office of Insurance and Safety Fire Commissioner and handled by the Safety Fire Division’s Safety Engineering Section. Those rules have statewide force without county adoption, and the 2026 Georgia mechanical amendments point to them for boilers and pressure vessels over 200,000 Btu per hour, 210 degrees Fahrenheit or 120 gallons.
The exemptions in O.C.G.A. 25-15-16 decide which vessels need a state of Georgia boiler inspection before they operate. Vessels that hold water under pressure are exempt up to a nominal 120 gallon capacity, including those with an air cushion, as are vessels working at 15 psig or less. A large campus plant often has expansion and buffer tanks well above 120 gallons, so those vessels need ASME construction, a data report and a state certificate inspection. Paul Industries collects the nameplate data and manufacturer’s data reports during Level 2 inspections, prepares each vessel for the certificate inspection, and schedules the inspector before the loop is filled for flushing.
| Vessel | Georgia status | Commissioning step |
|---|---|---|
| Expansion tank, 120 gallons or less, water with air cushion | Exempt under O.C.G.A. 25-15-16 | Verify precharge and nameplate; record in turnover |
| Expansion or buffer tank over 120 gallons | Subject to state inspection and certificate | Data report on file; certificate inspection before operation |
| Vessel working at 15 psig or less | Exempt | Confirm relief setting and design pressure |
| Compressed air receiver up to 16 cubic feet, under 250 psig | Exempt from the statute’s inspection provisions | Relief valve test and drain check |
| Boiler or water heater above 200,000 Btu per hour, 210 F or 120 gallons | Subject to state rules | Certificate inspection; controls and safety tests at start-up |
Construction and repair follow the codes the Georgia boiler and pressure vessel rules name. Vessels are built to the applicable sections of the ASME Boiler and Pressure Vessel Code, and repairs follow the National Board Inspection Code, Part 3, under the National Board’s R program with the inspector consulted before work starts. Vessel fabrication for Georgia plants is covered on the pressure vessel fabrication in Georgia page.
How commissioning levels line up with Georgia approvals
Commissioning levels line up with Georgia approvals in a way that lets each level close out one set of state or county requirements. The data center commissioning process runs from factory witness testing through integrated systems testing, and each step on a Georgia job has a matching record that an inspector, the boiler inspector, the air permit or the owner will ask for.
| Level | Work | Georgia record or approval it supports |
|---|---|---|
| Level 1, factory tests | Witness chiller, CDU and pump skid tests | ASME data reports for vessels; equipment efficiency for the energy code |
| Level 2, delivery and installation | Receiving inspection, installation checks | County rough-in inspections; vessel data collected for the state inspector |
| Level 3, start-up | Pressure tests, flushing, fill, equipment start-up | Hydronic test record under the IMC; certificate inspection of non-exempt vessels |
| Level 4, functional tests | Each system tested through its sequences and failure modes | Functional performance testing and balancing under Georgia’s C408 |
| Level 5, integrated tests | Utility failure, generator pickup, cooling ride-through | Generator runs inside the EPD permit conditions; owner acceptance |
Flushing and testing in Georgia heat, humidity and the occasional freeze
Flushing and testing in Georgia have to work around two seasons that each cause trouble. In summer, chilled water pipe tested and filled in a building without running air handlers sweats heavily in Atlanta air that sits at a 70 degree dew point for about 1,000 hours a year, so Paul Industries schedules insulation inspections after flushing and protects open electrical gear from drip during tests. In winter, a shell without heat can freeze a filled loop: Atlanta’s lowest hourly reading from 2021 through 2024 was 8 degrees Fahrenheit, so loops filled before the building is closed in get temporary heat, glycol or a drain-down plan.
Flushing volumes on a campus plant are large, so Paul Industries arranges a metered water connection with the water utility, a discharge route the sewer utility has approved, temporary pumps sized for flushing velocity, and strainers and bypasses around chillers, coolant distribution units and coils. Water quality is sampled at the end of flushing and again after the treatment chemistry is added, and the results go into the turnover record.
Generators, Georgia EPD air permits and integrated testing
Generators on a Georgia data center fall under the state’s air rules, chiefly Georgia Rule 391-3-1-.02(2)(mmm), which limits nitrogen oxide emissions from stationary engines between 100 kilowatts and 25 megawatts that generate electricity and exempts engines that meet its emergency standby criteria. Each facility permit then sets conditions for how and when those engines run. A Georgia Environmental Protection Division narrative for a proposed Fulton County data center on Selig Drive in Atlanta, issued in 2023, shows the pattern: the emergency generators are subject to Rule (mmm) and to the federal engine standards, and the permit lists the operating criteria.
That matters for commissioning because load bank runs and integrated tests are generator operation. In 2026 one Georgia developer installed 36 of its 37 backup generators before it held an air permit, drawing complaints and enforcement requests. Paul Industries builds the integrated test schedule around the permit: no engine runs under load before the permit allows it, run hours are logged against the permit’s limits, and the cooling plant’s ride-through, restart and generator pickup steps are written into the test script so each run proves as much as possible.
Commissioning liquid cooling loops in Georgia halls
Commissioning a liquid cooling loop in a Georgia hall adds steps that an air-cooled plant never needed, because cold plates have fine internal channels that a single weld bead, a fleck of pipe scale or a pocket of air can block. Paul Industries pressure tests each technology cooling loop section with its coolant distribution units and manifolds isolated, flushes with temporary pumps and bypass hoses until the particle count meets the cold plate maker’s limit, and only then fills the loop with the specified coolant through a filter cart. Air is purged at every high point, and the coolant is sampled for pH, conductivity, inhibitor level and bacteria before any server connects.
Functional tests then prove the loop as a system: pump changeover inside each coolant distribution unit, response to a lost facility water supply, leak detection alarms in each zone, and the control loop that holds supply temperature as rack heat steps up. Load banks shaped like servers, or the first servers themselves under the owner’s supervision, provide the heat. In a hall that mixes air and liquid cooling, Paul Industries also tests how the air handlers respond as heat moves from the air to the loop, so the room neither overcools nor drifts out of its humidity range.
Warranty records come out of the same work. Server and cold plate makers ask for evidence of cleanliness, coolant chemistry and pressure testing before they accept warranty claims, and Paul Industries delivers those records for each loop along with the valve, sensor and leak zone maps the operator uses afterward.
Data center commissioning in Atlanta at campus scale
Data center commissioning in Atlanta increasingly means commissioning the same building several times on one campus, because the metro’s large sites repeat a design across many halls. The first hall carries the most risk: sequences are tested for the first time, control programming is new, and every lesson must be carried into the next building. Paul Industries keeps a single issues log across the campus, updates the test scripts after each hall, and retests a changed sequence in every hall that runs it.
Campus schedules in Georgia also ride on outside dates. Contracts under the Public Service Commission’s 2025 large-load rule set when power is available, temporary county pauses on new projects in 2026 moved some start dates, and air permits govern generator testing. The Georgia data center regulation that most often moves a commissioning date is whichever of those three arrives last, so Paul Industries builds a schedule that can run cooling plant tests on temporary power or load banks when the permanent feed or the permit is late. The cooling plants being tested are described on the data center cooling in Georgia page, and the liquid loops on the data center liquid cooling in Georgia page.
Turnover records a Georgia owner should hold
Turnover records for a Georgia data hall should prove four things: that the pipe passed its pressure tests, that the vessels hold valid state certificates, that each system passed functional performance testing, and that the integrated test ran within the air permit. Because Georgia deleted the clause that ties final inspection to the code official receiving the preliminary report, owners should write delivery and review of that report into the contract instead, so it is read before occupancy.
Paul Industries delivers, for each system it commissions, the pressure test and flushing records, water quality results, vessel data reports and certificate dates, start-up reports, functional performance test scripts with results, the balancing report, the issues log with closures, equipment manuals and as-built drawings. Owners with process or qualification needs as well, such as biotech or pharmaceutical tenants, can extend the same records under the work described on the validation and commissioning in Georgia page.
What does data center commissioning in Georgia cost?
The cost of data center commissioning in Georgia depends on the number of systems tested, the commissioning levels the owner requires, the number of halls and how much testing repeats across them, the flushing scope, and how many integrated test runs the owner asks for. Paul Industries prices commissioning from the system list and test scripts rather than from a percentage of construction cost, and gives a budget from comparable scope before a firm price.
A few Georgia items move the number more than owners expect. Non-exempt pressure vessels add certificate inspections that have to be booked with the state, and a large campus plant may carry several. Flushing a long chilled water main needs temporary pumps, hoses and a metered water supply sized for flushing velocity, plus a discharge route for the water. Integrated tests that rely on generators must fit the hours the air permit allows, which can split one long test into several shorter runs. And campuses that repeat a design save money on every hall after the first, because test scripts, issues lists and lessons carry forward.
Energy for load bank testing is easy to estimate with verified Georgia prices. A 10 megawatt load bank run for 24 hours draws 240,000 kilowatt hours, about $27,700 at Georgia’s 2025 average commercial price of 11.53 cents per kilowatt hour or about $18,900 at the industrial average of 7.88 cents, before any demand charges under the site’s contract. Labor rates on private work are market rates, since Georgia has no state prevailing wage law; federal Davis-Bacon rates apply only where federal funding brings them.
Who performs data center commissioning in Georgia?
Paul Industries performs data center commissioning in Georgia for the mechanical systems of a hall: pressure testing, flushing, filling, start-up, functional performance testing and the cooling plant’s part of integrated tests, working under the owner’s commissioning authority and to the owner’s levels and scripts. Paul Industries has its headquarters at 256 Shore Drive, Kilmarnock, Virginia; formerly based in northern New Jersey and then Pennsylvania, it now works as an East Coast contractor throughout Georgia, in every one of the 50 states and at plants outside the country. Commissioning in its headquarters state is described on the data center commissioning in Virginia page, and Southeast work on the North Carolina data center commissioning page.
Paul Industries commissions the systems it builds and existing systems built under other contracts, and the same team handles the building’s full mechanical scope on the data center mechanical contractor in Georgia page. Supply of test equipment, temporary pumps and strainers, design-build of permanent flushing connections, and complete installation of the plant itself are all available under one contract.
Paul Industries commissioning for Georgia data halls
Paul Industries tests, starts and documents cooling plants and liquid loops for data halls in metro Atlanta, Augusta, Macon, Columbus, Athens and Savannah, with records written to Georgia’s codes, the state boiler rules and each site’s air permit. The wider range of Georgia work is on the Georgia page and the regional view on the Southeast page. Send the system list, levels and schedule, and request a quote for commissioning.
Standards referenced: Georgia State Minimum Standard Energy Code (2015 IECC with Georgia Supplements and Amendments), Section C408 · 2024 International Mechanical Code with Georgia Amendments · 2024 International Building Code with Georgia Amendments · O.C.G.A. Title 25, Chapter 15 (boilers and pressure vessels) and Rules 120-3-26 · Georgia Rule 391-3-1-.02(2)(mmm) · ASME B31.9 · ASME Boiler and Pressure Vessel Code Section VIII · National Board Inspection Code · ASHRAE Guideline 0
Frequently asked questions
Who commissions data center cooling plants in Atlanta and Fulton County?
Paul Industries commissions data center cooling plants in Atlanta and across Fulton County, from pressure tests and flushing through start-up, functional performance testing and the cooling side of integrated tests. In the city and inner suburbs much of this work happens in occupied buildings, so Paul Industries runs tests inside the operator’s change control windows and isolates live systems before any test pressure is applied.
Does Paul Industries commission data halls in Douglas, Fayette and Coweta counties?
Paul Industries commissions mechanical systems for data halls in Douglas, Fayette and Coweta counties and the rest of metro Atlanta. Each county enforces the state codes through its own inspection procedures, so Paul Industries confirms the county’s witness and paperwork steps at the start, schedules tests to meet them, and keeps the campus issues log current as each hall follows the first.
Can Paul Industries flush and test cooling loops for a data center in Augusta or Savannah?
Paul Industries flushes, pressure tests, fills and starts cooling loops for data centers in Augusta, Savannah and elsewhere in Georgia. In Savannah’s humid air, chilled water pipe sweats heavily during testing, so Paul Industries protects electrical gear from drip and checks insulation after flushing. The same records are delivered in every Georgia city: test logs, water quality results and functional performance test reports.
What is the current energy code for Georgia commercial buildings?
Georgia’s commercial energy code is the 2015 IECC with Georgia Supplements and Amendments, with amendment packets from 2020, 2022 and 2023, according to the Department of Community Affairs. Designers can show compliance through the 2015 IECC or ASHRAE 90.1-2013 in the compliance software. Other Georgia codes moved to 2024 editions on January 1, 2026, but the energy code did not change edition.
What does functional performance testing mean in the Georgia energy code?
Georgia’s amendments replace the words commission and commissioning in Section C408 with functional performance testing. The requirements behind the term remain: a plan, system balancing, tests of each system through its control sequences, a preliminary report and documentation to the owner. Paul Industries titles its Georgia test reports to match the code’s wording so reviewers and inspectors recognize them.
Does Georgia's energy code apply to computer rooms the same way it applies to offices?
Most mandatory requirements apply to both, including equipment efficiency, controls, pump flow reduction in multi-chiller plants and functional performance testing. Georgia adds an exception for computer room applications to the economizer requirement, so an economizer is tested only where the owner chose to build one. Paul Industries writes the test plan to the systems actually installed.
Does a chilled water expansion tank need a Georgia boiler inspection?
Expansion tanks holding water under pressure with a nominal capacity of 120 gallons or less, including those with an air cushion, are exempt under O.C.G.A. 25-15-16. Larger expansion and buffer tanks on campus plants fall under the state’s boiler and pressure vessel rules and need a certificate inspection. Paul Industries checks each vessel’s capacity and design data during installation and schedules the inspector when needed.
Who carries out the state of Georgia boiler inspection for data center vessels?
Boiler and pressure vessel inspections in Georgia fall under O.C.G.A. Title 25, Chapter 15, handled by the Safety Fire Division’s Safety Engineering Section within the Commissioner’s office. Paul Industries prepares vessels for the certificate inspection under the state rules, with data reports, nameplates and relief valves ready, so the visit closes without a return trip.
Can generator load tests run before a Georgia air permit is issued?
Generator operation during commissioning is engine operation under Georgia’s air rules, so it belongs inside the permit’s conditions. In 2026 a Georgia developer drew enforcement requests after installing generators before its permit was issued. Paul Industries schedules engine runs only once the permit allows them, logs hours against its limits, and runs cooling tests on temporary power or utility-fed load banks when the permit is late.
Do Georgia counties witness hydronic pressure tests?
Georgia deletes the mechanical code’s administrative chapter and leaves inspection procedures to each county or city that enforces the state codes, so witness practice varies. Paul Industries confirms the jurisdiction’s requirement at the start, runs and passes each test before calling for a witness, and records pressure, duration and temperature for every section either way.
How is a cooling plant proven at design load when commissioning ends in a Georgia winter?
A plant finished in winter cannot see a 94 degree, humid afternoon, so heat rejection capacity is tested with load banks at the conditions available and the results are corrected against the equipment ratings. A seasonal test is then scheduled for the first Georgia summer, when Atlanta typically logs about 160 hours above 90 degrees. Paul Industries writes the deferred test into the plan from the start.
Does Georgia's lack of a prevailing wage law affect commissioning prices?
Georgia has no state prevailing wage law, so labor on privately funded data center projects is priced at market rates. Federal Davis-Bacon rates apply only where federal money funds the work. Paul Industries prices commissioning from the system list, levels and test scripts, and states the labor basis in every proposal.
What testing does an Atlanta hall need after a liquid cooling loop is added?
A new liquid loop needs a pressure test, flushing to the cold plate maker’s cleanliness limits, filling and coolant analysis before any server connects, then functional tests of the coolant distribution units and an integrated test showing the loop rides through a utility failure. Paul Industries runs those tests in the operator’s change control windows and updates the hall’s records.
Which Georgia certificates and reports belong in the turnover binder?
The binder should hold pressure test and flushing records, water quality results, vessel data reports with state certificate dates, start-up reports, functional performance test results, the balancing report, the closed issues log, generator run logs against the air permit, manuals and as-built drawings. Paul Industries delivers each of these for the systems it commissions.
Which Georgia data center regulation moves commissioning dates most often?
Three dates usually decide it: when the utility contract delivers permanent power, when the air permit allows generator runs, and whether a county pause or zoning change delays the start. Paul Industries builds the schedule so cooling plant tests can run on temporary power or load banks when one of those dates slips, keeping the rest of the program moving.
Which commissioning tasks does Paul Industries carry on a Georgia data hall?
Paul Industries carries the mechanical tasks: pressure testing, flushing and filling, vessel preparation for state inspection, equipment start-up, functional performance testing of cooling systems, and the cooling side of integrated tests. It works to the owner’s commissioning authority, levels and scripts, and logs issues and closures in the project’s shared record.
Which documents start a commissioning scope for a Georgia hall?
Send the system list and drawings, the commissioning levels and scripts the owner requires, the number of halls and phases, the county where the site sits, the air permit status, and the schedule. From those, Paul Industries sets out a budget drawn from similar programs, then a firm price once the test plan is agreed. Call 201-450-8280 or request a quote.
Testing and starting a data hall in Georgia?
Send the system list, commissioning levels and schedule, and Paul Industries will plan the tests around Georgia’s codes and permits. Call 201-450-8280 or request a quote.