Paul Industries delivers data center commissioning in North Carolina for cooling plants, liquid cooling loops and mechanical systems, flushing and pressure testing the piping, starting up chillers, pumps and dry coolers, running functional and integrated tests, and assembling the records that North Carolina inspectors, engineers and operators need at turnover. Paul Industries is an East Coast contractor headquartered in Kilmarnock, Virginia, and commissions data center work in every North Carolina region. New campus buildings, phased colocation halls and retrofits in operating rooms are all part of the scope.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Code in force 2018 NC State Building Code until the 2024 edition takes effect
Energy code form Appendix C1 Statement of System Commissioning, Parts 1 to 3
Pressure vessels No operation without an NC inspection certificate (G.S. 95-69.16)
Hot test window 214 hours a year at 90 F or above at Charlotte (2021 to 2024)
Reviewed November 2026

How data center commissioning in North Carolina ties to the permit

Data center commissioning in North Carolina ties to the permit through three documents: the mechanical permit and its inspections under the North Carolina State Building Code, the Statement of System Commissioning that the North Carolina Energy Conservation Code requires in Appendix C1, and, for any pressure vessel the Boiler and Pressure Vessel Act covers, the inspection certificate without which the vessel cannot operate. The owner’s commissioning program usually goes further than the code, through factory witness tests and integrated systems testing, but those three items are what the state and the county actually check.

Inspections are run by county and city code enforcement departments rather than by the state. In Mecklenburg County, the Land Use and Environmental Services Agency’s Code Enforcement division handles permitting, plan review and inspections throughout the county, and it lists an Appendix C1 mechanical form among its permit documents. Wake, Durham, Catawba and other counties, along with cities that run their own inspection departments, follow the same state code with their own scheduling and submittal practices. The commissioning schedule is built around that jurisdiction’s inspection sequence from the start.

The national treatment of commissioning levels, flushing practice and test scripts is on the data center commissioning page. This page covers what is particular to North Carolina.

Which North Carolina State Building Code edition applies to a data center today?

The 2018 North Carolina State Building Code, effective January 1, 2019 and based on the 2015 International codes, remains the code in force according to the Office of State Fire Marshal, while the 2024 edition waits for its effective date. The 2024 code was first set for January 1, 2025, then delayed to July 1, 2025 by Session Law 2024-57, and Session Law 2025-2 replaced that date with a trigger: the 2024 code takes effect 12 months after the State Fire Marshal certifies that its components have been published and distributed. The 2024 Energy Conservation Code, based on the 2021 International Energy Conservation Code, was finalized on March 24, 2025.

For a data center with a long build, the governing edition is set building by building through the permit process, so a campus whose first building was permitted under the 2018 code may see later buildings permitted under the 2024 code. Paul Industries confirms the edition on each building’s permit before writing pressure test procedures and commissioning forms, because test pressures, energy code requirements and form versions follow that edition. The North Carolina Building Code Council adopts the codes; the Office of State Fire Marshal within the Department of Insurance publishes them and issues interpretations.

Is commissioning required by code in North Carolina?

Commissioning is required by code in North Carolina for mechanical, service water heating and electrical systems in new commercial buildings through Section C408.1 of the North Carolina Energy Conservation Code, which calls for a Statement of System Commissioning in Appendix C1. Part 1 covers mechanical systems, Part 2 service water heating and Part 3 electrical system installation, and the completed statement becomes part of the permit record.

The Office of State Fire Marshal has published an interpretation that settles two common questions. The engineer of record may complete the Appendix C1 statement but is not required to; a second engineer may complete it, certifying only what that engineer can verify under responsible charge, as the North Carolina Board of Examiners for Engineers and Surveyors has explained. And the minimum code does not require an outside commissioning agent; an owner who wants one arranges it by contract with a commissioning agent. North Carolina owners of large data centers usually do, and the agent then writes the test scripts that the mechanical work is proved against. For alterations, the requirements of C408.1 apply to the systems in an altered space larger than 10,000 square feet and are not invoked by code for a smaller altered area.

That last point matters for data center retrofits. A liquid cooling fit-out in a 6,000 square foot hall inside a larger building does not trigger Appendix C1 by code, yet the owner still needs the same flushing, pressure testing, startup and functional testing to protect the IT equipment. Paul Industries runs those tests to the owner’s program whether or not the code asks for the statement, and supplies the test data the engineer needs where it does.

How to commission a data center on a North Carolina permit

How to commission a data center on a North Carolina permit comes down to matching each commissioning level to the inspection or document it supports, so that the owner’s five levels and the county’s inspection sequence move together. The table shows how the levels line up with North Carolina milestones on a typical cooling plant.

Commissioning levels and the North Carolina milestones they support
LevelMechanical activityNorth Carolina milestone it supports
L1 factory witnessChiller, CDU, pump skid and switchgear factory testsNameplate and data report review for any vessel the Boiler Act covers
L2 delivery and installationReceiving inspection, setting, piping, supports, pre-installation checksRough-in and above-ceiling mechanical inspections by the county or city
L3 startup and pre-functionalFlushing, hydrostatic tests, fill, rotation checks, manufacturer startupWitnessed pressure tests; Boiler Safety Bureau inspection of covered vessels before operation
L4 functional performanceSequence of operations, alarms, failover, capacity at available loadTest data for the Appendix C1 Part 1 mechanical statement
L5 integrated systems testUtility failure, generator transfer, cooling ride-through with full heat loadOwner acceptance, generator runs counted against the DEQ air permit, certificate of occupancy timing

The order is not fixed by any North Carolina rule, and on a phased campus the levels overlap: one building may be in integrated testing while the next is in rough-in. Paul Industries keeps a separate test record set for each building and each phase, so that one inspector’s sign-off and one Appendix C1 statement map to exactly the systems they cover.

Pressure vessels on the cooling plant and the North Carolina Boiler Act

Pressure vessels on a data center cooling plant fall under the North Carolina Uniform Boiler and Pressure Vessel Act unless the statute excludes them, and a covered vessel may not be operated without an inspection certificate under General Statute 95-69.16. The Act’s exclusions in 95-69.10 reach many chilled water components: vessels operating at 15 psig or less, small vessels within set volume and pressure limits, and vessels containing water at no more than 110 F with a maximum allowable working pressure of no more than 300 psig, an exclusion that does not extend to hydropneumatic tanks on potable water.

Common data center vessels and how the North Carolina Boiler Act treats them
VesselTypical serviceTreatment under G.S. 95-69.10Commissioning step
Chilled water expansion tankWater near 40 to 70 F, under 300 psigExcluded under (b)(14) while water stays at 110 F or belowPrecharge check, relief valve setting, fill pressure record
Air and dirt separator on chilled or condenser waterWater under 110 F, moderate pressureExcluded under (b)(14) within the same limitsBlowdown, vent function, strainer inspection after flushing
Heat recovery or heating hot water tankWater above 110 F for reuse or reheatCovered unless another exclusion appliesBoiler Safety Bureau inspection and certificate before operation
Compressed air receiver for controls or generator startingAir, often above 100 psigCovered unless within the small-vessel limits of (b)(8)Certificate check, relief valve test, drain function
Domestic water hydropneumatic tankPotable water serviceCovered; the (b)(14) exclusion does not applyCertificate before operation, relief and precharge records
Thermal storage tank at atmospheric pressureChilled water buffer, ventedExcluded under (b)(9) at 15 psig or lessLevel controls, overflow, temperature stratification check

Heat reuse projects are where data center owners most often meet the Act. A liquid cooling loop that sends water above 110 F to a campus heating system can bring tanks and heat exchangers into coverage that a plain chilled water plant never had. Paul Industries identifies covered vessels during submittal review, confirms the vessel’s ASME nameplate and manufacturer’s data report, and schedules the Boiler Safety Bureau inspection ahead of startup so the vessel has its certificate before it is put in service. Vessel fabrication for these plants is covered on pressure vessel fabrication in North Carolina.

Pressure testing and flushing on North Carolina data center jobs

Pressure testing and flushing on North Carolina data center jobs follow the mechanical code for hydronic piping, the ASME piping code named in the project specification, and the manufacturer’s requirements for chillers, CDUs and cold plates. The model mechanical code on which North Carolina’s is based calls for hydronic piping to be tested hydrostatically at one and a half times the maximum system design pressure, with a floor of 100 psi, held for at least 15 minutes. Project specifications for data center loops commonly ask for longer holds, and ASME B31.9 or B31.3 governs where the piping falls under those codes.

Flushing comes before anything sensitive is connected. Mains are flushed at velocities that move construction debris, with chillers, CDUs and plate heat exchangers bypassed through temporary jumpers, then filled with treated water or glycol and sampled until the water meets the cleanliness and chemistry limits in the specification. Liquid cooling loops get a finer standard, with filtration at the rating the cold plate manufacturer sets, before any server is connected. Paul Industries supplies temporary pumps, strainers and bypasses, records each test and flush on a form the inspector and owner can sign, and keeps the readings with the turnover package. The national page on hydrostatic testing covers test methods in more depth.

North Carolina winters shape when tests can run outdoors. Over 2021 to 2024, Raleigh averaged about 306 hours a year at or below freezing and Hickory about 367, so a water-filled test on rooftop or yard piping in an unheated building has to be drained before nightfall, heated or run with glycol. Paul Industries plans test windows around the forecast and keeps heaters and drain points ready on winter jobs.

Generators, DEQ air permits and integrated testing

Generators, DEQ air permits and integrated testing are linked in North Carolina because every hour a diesel generator runs during commissioning counts toward the operating limits in the site’s air permit from the Department of Environmental Quality’s Division of Air Quality. Under 15A NCAC 02Q .0807, a facility whose only permit-triggering sources are emergency generators may be excluded from Title V permitting by using its actual emissions, but that exclusion does not remove the state construction and operation permit, and large campuses carry permits written around their generator fleets. A September 2026 petition challenging the permit for Amazon’s Hamlet data center says that permit authorizes 592 diesel emergency generators.

For the cooling contractor, the permit sets the budget of generator hours available for load bank tests, transfer tests and integrated systems testing. Paul Industries plans the mechanical side of integrated testing so that each generator run proves as much as possible: chillers restarting in sequence, pumps returning on their programmed delays, CDUs holding rack supply temperature through the transfer, and thermal storage carrying the gap. Trend data from those runs goes straight into the test record, so a run does not have to be repeated for missing data.

During each integrated run the mechanical team watches a short list of numbers that decide whether the design worked: chilled water or facility water supply temperature at the hall, rack inlet air temperature at the worst-placed racks, the time each chiller takes to return to full capacity, the level in any thermal storage tank, and CDU flow and supply temperature at the rack loops. Those readings are compared against the owner’s acceptance limits on the spot. A sequence that misses a limit is corrected, retested on load banks without the generators where possible, and then proved once more in the next scheduled transfer, which keeps generator hours within the permit while the record closes cleanly.

Testing cooling plants against North Carolina weather

Testing cooling plants against North Carolina weather means deciding which tests need summer conditions and which can be proved with load banks in any season. Charlotte saw about 214 hours a year at 90 F or above over 2021 to 2024 and Raleigh about 276, mostly in July and August, so a heat rejection capacity test at design conditions has a short natural window. Many owners prove chiller and pump capacity with load banks at turnover and defer the full tower or dry cooler capacity test to the first summer, with the deferred test written into the commissioning plan.

Economizer changeover is the opposite case: free cooling sequences are best tested in spring or autumn, when the outdoor conditions cross the changeover points every day. Paul Industries schedules seasonal tests in the commissioning plan from the start, so the owner knows which records will be complete at turnover and which arrive with the first season of operation.

Data center construction in North Carolina and where commissioning fits

Data center construction in North Carolina has shifted toward multi-building campuses, which turns commissioning from a single event into a repeating program. Amazon’s Richmond County campus was announced in June 2025 with up to 20 buildings, and Microsoft’s Catawba County program began site setup and earthwork at its Hickory site in May 2026. On campuses like these, the first building’s commissioning writes the test scripts, forms and sequences that every following building reuses, so problems found in building one are fixed in the standard before building two.

Commissioning also follows the utility. The date Duke Energy energizes a building’s permanent service sets when integrated testing on permanent power can begin, and on a phased campus the mechanical team often runs startup on temporary power and repeats key tests once permanent service is live. Paul Industries plans flushing, startup and functional testing to finish ahead of energization so that integrated testing starts on time. Cooling plant design and installation for these campuses is covered on data center cooling in North Carolina, and rack-level loops on data center liquid cooling in North Carolina.

Turnover records for a North Carolina data center

Turnover records for a North Carolina data center serve three readers: the code official who closes the permit, the engineer who signs the Appendix C1 statement, and the operator who will run the plant for decades. Each needs a different subset, and preparing them as separate packages saves time at the end of the job.

Turnover records by recipient, a data center commissioning checklist for North Carolina work
RecipientRecordsWhy they need them
County or city code enforcementPressure test reports, inspection sign-offs, Appendix C1 statementFinal mechanical inspection and certificate of occupancy
NC Department of Labor Boiler Safety BureauVessel nameplate data, data reports, installation details for covered vesselsInspection certificate before operation
Engineer signing Appendix C1Functional test results, balancing reports, control sequence verificationBasis for the Part 1 mechanical statement
Owner’s environmental staffGenerator run log during testing, fuel delivered and usedAir permit recordkeeping with DEQ
Operations teamFlushing and water chemistry records, coolant data, startup reports, as-built drawings, trend baselinesWarranty, maintenance planning and future troubleshooting

What does data center commissioning cost in North Carolina?

Data center commissioning cost in North Carolina depends on the number of systems and levels in scope, the size of the plant, how many phases repeat the tests, the load bank capacity and run time needed, and whether the work includes retrofits in an operating room, where every test is staged around live equipment. Load bank energy itself is a modest line: a 10 MW heat load test run for 24 hours on utility power uses 240,000 kilowatt-hours, about $18,700 at North Carolina’s 2025 average industrial price of 7.79 cents (EIA), while the same test on generators costs fuel and permit hours instead.

Paul Industries prices the mechanical commissioning scope with the installation, as a separate flushing, testing and startup package for owners whose installation is already contracted, or as recommissioning for an existing hall after a liquid cooling addition. A budget figure from comparable plants comes first, followed by a firm price once systems, phases and test durations are listed.

Who performs data center commissioning in North Carolina?

Paul Industries performs data center commissioning in North Carolina for the mechanical and cooling systems: flushing, hydrostatic testing, fill and water treatment, equipment startup, functional performance testing, integrated systems testing support and the records for inspectors, engineers and operators. The work covers Charlotte, Raleigh, Durham, RTP, Greensboro, Winston-Salem, Hickory, Lenoir, Rockingham, Sanford, Fayetteville and Wilmington.

Headquartered at 256 Shore Drive in Kilmarnock, Virginia, and formerly based in northern New Jersey and then Pennsylvania, Paul Industries commissions data center systems across North Carolina, in all 50 states and at sites outside the United States through its international work. State comparisons are on the data center commissioning page for Virginia, the headquarters state, and commissioning for Maryland data halls. Pharmaceutical commissioning and qualification in the state is on validation and commissioning in North Carolina, the full mechanical scope on data center mechanical contractors in North Carolina, and Paul’s broader work in the state on the North Carolina page.

Commissioning from Paul Industries for North Carolina data halls

Paul Industries provides data center commissioning services across North Carolina, from the first flush to the last integrated test: test procedures matched to the permit’s code edition, Boiler Act vessel checks, Appendix C1 test data, generator-aware integrated testing and turnover packages for each reader. Send the drawings, equipment list, phase plan and target dates, and request a quote for the commissioning scope.

Standards referenced: North Carolina State Building Code (2018 edition in force; 2024 edition pending) · North Carolina Energy Conservation Code, Section C408 and Appendix C1 · North Carolina State Building Code: Mechanical Code · North Carolina Uniform Boiler and Pressure Vessel Act (G.S. 95-69.8 et seq.) · 15A NCAC 02Q (air quality permits) · ASHRAE Guideline 0 · ASHRAE 202 · ASME B31.9 · ASME B31.3 · NFPA 110

Frequently asked questions

Who commissions data center cooling systems in Charlotte and Mecklenburg County?

Paul Industries commissions data center cooling systems in Charlotte and across Mecklenburg County, where the county’s Code Enforcement division handles permits, plan review and inspections. Flushing, pressure tests and startup are scheduled around the county’s inspection sequence, and the Appendix C1 mechanical form is supported with functional test data so the permit can close on time.

Does Paul Industries commission data centers in Raleigh, Durham and Research Triangle Park?

Yes. Paul Industries commissions data center cooling and liquid cooling systems in Raleigh, Durham, Cary, Morrisville and Research Triangle Park, for colocation buildings, enterprise rooms and university computing. Each county or city inspection department sets its own scheduling, so the commissioning plan is matched to the jurisdiction that issued the permit.

Who handles commissioning on Catawba Valley data center campuses?

Paul Industries handles mechanical commissioning on data center campuses in Hickory, Conover, Maiden and Lenoir, where buildings repeat across phases. The first building’s flushing procedures, test scripts and forms become the standard for later buildings, and records are kept per building so each permit and each Appendix C1 statement maps to exactly the systems it covers.

Does Paul Industries commission data center buildings in Richmond County and Lee County?

Paul Industries commissions data center buildings in Richmond County around Rockingham and Hamlet, and in Lee County around Sanford. Campuses there are planned in many repeated buildings, so the commissioning program is written once, tested on the first building and repeated, with generator hours for integrated testing budgeted against each site’s DEQ air permit.

Does Paul Industries test retained chillers and tanks in Triad industrial conversions?

Yes. Paul Industries commissions data center cooling in Greensboro, Winston-Salem, High Point and converted industrial buildings across the Triad. Conversions often retain existing chillers, pumps or tanks, so commissioning includes condition checks and testing of retained equipment, and Boiler Act status is confirmed for any retained vessel before it returns to service.

Does the North Carolina energy code require an outside commissioning agent?

The minimum code leaves that to the owner. The Office of State Fire Marshal’s interpretation of Section C408.1 says the code does not require the work to be performed by an outside commissioning agent; an owner who wants one arranges it by contract. The Appendix C1 statement itself is completed by the engineer of record or a second engineer under responsible charge.

Who signs the Appendix C1 Statement of System Commissioning in North Carolina?

The engineer of record may complete it but is not required to; a second engineer may complete it instead, certifying only items verified under that engineer’s responsible charge, according to the North Carolina engineering board’s response published by the Office of State Fire Marshal. Paul Industries supplies the functional test data, balancing results and sequence checks the signing engineer relies on.

Does a liquid cooling retrofit in an existing North Carolina hall need Appendix C1?

Under the Office of State Fire Marshal’s interpretation, C408.1 commissioning applies to systems in an altered space larger than 10,000 square feet and is not invoked by code for a smaller altered area. Many hall retrofits fall under that size, but the owner still needs flushing, pressure testing and functional testing to protect the servers, and Paul Industries runs them to the owner’s program.

Does a chilled water expansion tank need a North Carolina boiler inspection certificate?

A chilled water expansion tank holding water at 110 F or less, with a maximum allowable working pressure of 300 psig or less, is excluded from the Boiler and Pressure Vessel Act under G.S. 95-69.10(b)(14). Tanks on heat recovery or heating loops above 110 F, compressed air receivers above the small-vessel limits and potable water hydropneumatic tanks are covered and need a certificate before operation.

Which North Carolina building code edition will a data center permitted in 2027 use?

That depends on whether the 2024 North Carolina State Building Code has taken effect by the permit date. Under Session Law 2025-2 it takes effect 12 months after the State Fire Marshal certifies its publication, and until then the 2018 code applies. Paul Industries checks the edition on each building’s permit before writing test procedures and forms.

Do generator runs during commissioning count against a North Carolina air permit?

Yes. Generator hours during load bank tests, transfer tests and integrated testing count toward the operating limits and recordkeeping in the site’s DEQ air permit. The commissioning plan budgets those hours, combines tests where possible so each run proves several sequences, and logs run time and fuel for the owner’s environmental records.

What is the difference between testing and commissioning on a North Carolina data center job?

Testing proves a single item, such as a pipe holding pressure or a pump making its rated flow. Commissioning proves that the systems work together as designed, through the full sequence of startup, functional tests and integrated failure tests, and documents it for the inspector, the Appendix C1 engineer and the operator. Both are part of the Paul Industries scope.

When should cooling tower and dry cooler capacity tests run in North Carolina?

A full heat rejection capacity test at design conditions needs summer weather; Charlotte averaged about 214 hours a year at 90 F or above over 2021 to 2024, mostly in July and August. When turnover falls outside that window, chiller and pump capacity are proved with load banks, and the heat rejection test is scheduled as a deferred seasonal test in the commissioning plan.

Can an operating North Carolina data center be recommissioned after adding liquid cooling?

Yes. Recommissioning covers the new loops and the existing systems they affect: the chilled water plant’s new loads, control sequences changed for warmer water, CDU failover, and the response of the whole plant to a utility outage. Paul Industries stages each test around live equipment under a written method of procedure.

How much does data center commissioning cost in North Carolina?

Cost follows the number of systems and levels in scope, the number of repeated phases, load bank capacity and hours, and whether testing happens in an operating room. Load bank energy is a small part: a 10 MW, 24 hour test on utility power uses about $18,700 of electricity at the 2025 state industrial average. Send the scope for a budget figure and a firm price.

What records should a North Carolina data center owner keep after commissioning?

Keep the pressure test and flushing reports, water and coolant chemistry records, startup reports, functional and integrated test results, the Appendix C1 statement, Boiler Safety Bureau certificates for covered vessels, generator run logs from testing and trend baselines. Those records support warranty claims, future inspections and troubleshooting long after the commissioning team leaves.

Can Paul Industries flush and test an installation that another contract built?

Yes. Paul Industries takes on flushing, pressure testing, startup and functional testing as a separate package on North Carolina projects where the installation is already under contract, and commissions existing systems whose records are incomplete, retesting where needed so the owner ends up with a full record set.

What should a North Carolina owner send to scope commissioning work?

Send the mechanical drawings and specifications, the equipment list with any pressure vessels, the commissioning plan or owner’s requirements, the phase and energization schedule, the permit jurisdiction and target dates. Paul Industries returns the test sequence, the records each phase will produce and a budget figure.

Commissioning a data center cooling plant in North Carolina?

Send the drawings, equipment list, phase plan, permit jurisdiction and target dates. Call 201-450-8280 or request a quote.