Paul Industries provides validation and commissioning in Georgia for plasma fractionation, vaccine, biologics, pharmaceutical and medical device plants, writing and executing commissioning plans and IQ, OQ and PQ protocols for process systems, utilities and equipment from Covington and Newton County to Athens, Gwinnett County and metro Atlanta. Georgia’s life sciences manufacturing answers to three different federal rulebooks, FDA for human drugs and biologics, USDA for veterinary vaccines and FDA’s device regulation for medical device plants, and a qualification program has to match the one that applies. Paul Industries builds, commissions and qualifies the systems and hands over the documented evidence each regulator expects.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Largest biotech site Takeda plasma campus near Covington, over 1.1 million sq ft (Takeda)
Animal vaccines Boehringer Ingelheim, Athens: vaccines for pets, poultry and wildlife
New biologics plant UCB, $2 billion, Gwinnett County, announced March 2026
Plasma storage Not warmer than minus 20 C for injectable products (21 CFR 640.69)
Reviewed November 2026

What does validation and commissioning in Georgia cover, plant by plant?

Validation and commissioning in Georgia covers the engineering checks that prove a system was built and works as designed, and the documented qualification that proves it is fit for regulated manufacturing, at a set of plants unlike any other state’s mix. Georgia has a plasma fractionation campus that its owner counts among the biggest in the world, a large animal vaccine operation in Athens, a $2 billion human biologics plant in design for Gwinnett County, a growing bioprocess supply base around Athens, and medical device and pharmaceutical plants across metro Atlanta.

For each of those, commissioning confirms installation, function and performance against engineering requirements, and qualification, IQ, OQ and PQ, confirms the systems that touch product quality meet predetermined acceptance criteria under the applicable regulation. The national approach, including the difference between commissioning and qualification and how protocols are written, is on the validation and commissioning service page. This page covers how that work runs at Georgia plants and under the rules they answer to.

Pharmaceutical companies in Georgia and the plants behind them

Pharmaceutical companies in Georgia that make product inside the state are concentrated in three places: the Stanton Springs business park near Covington and Social Circle east of Atlanta, Athens-Clarke County, and Gwinnett County along the Highway 316 corridor. Lists of pharmaceutical companies in Georgia, USA, mix headquarters, sales offices and distribution centers with plants; the sites that matter for qualification work are the ones that make, fill or test product. The pharmaceutical industry in Georgia is built around a small number of large, specialized campuses, so a handful of sites carry much of the state’s qualification work.

Pharmaceutical companies in Atlanta, Georgia and the eastern metro

Takeda’s plasma-derived therapies campus near Covington began as a Baxter project, with construction starting in August 2012, and received FDA approval to manufacture GAMMAGARD LIQUID in June 2018 and FLEXBUMIN in March 2019. Takeda describes it as the largest biotech manufacturing facility in Georgia, at more than 1.1 million square feet, with fractionation, purification, fill-finish and testing on one site. In March 2026, UCB announced a $2 billion investment in its first US biologics manufacturing plant in the Rowen district of Gwinnett County, with design and construction expected to take six to seven years. These are market facts about where qualification work sits; the systems behind them, from water and clean steam to cold rooms and fill lines, are what a CQV program has to prove.

Biotech companies in Georgia: Athens and the Highway 316 corridor

Athens holds Boehringer Ingelheim’s animal health vaccine operation, which grew from Merial’s presence in the city since 1989 and makes vaccines for pets, poultry and wildlife; a $76 million expansion completed in 2019 doubled its capacity. Meissner, which makes filtration and single-use bioprocess products, announced a $250 million Athens-Clarke County campus in 2023, opened an X-ray irradiation facility there and broke ground on its second phase in October 2026. Biotech companies in Atlanta and along the corridor between the two cities add research, clinical and specialty manufacturing sites, and the pharmaceutical manufacturing companies in Georgia that supply them, from bioprocess consumables to packaging, run cleanrooms and equipment that need qualifying in their own right.

Georgia life sciences manufacturing and what qualification focuses on
Plant type and areaRegulatorSystems qualification centers onTypical evidence
Plasma fractionation, Newton CountyFDA (biologics, 21 CFR 600-680 and 211)Plasma freezers and thaw, cold processing, purification, WFI, clean steam, fill-finishTemperature mapping, cleaning and sterilization cycles, water PQ
Animal vaccines, AthensUSDA APHIS Center for Veterinary Biologics (9 CFR)Culture and inactivation systems, containment, biowaste kill systems, autoclavesSterilization and inactivation cycle data, containment tests
Human biologics, Gwinnett CountyFDA (biologics and 21 CFR 211)Bioreactors, purification, WFI, clean steam, cleanrooms, automationCommissioning records leveraged into IQ and OQ, PQ on utilities
Bioprocess supply, AthensCustomer quality agreements, ISO 13485 where devices applyCleanrooms, molding and assembly equipment, irradiation and packagingEquipment IQ and OQ, environmental monitoring qualification
Pharmaceutical and device plants, metro AtlantaFDA (21 CFR 211 or 21 CFR 820 QMSR)Process equipment, purified water, HVAC, computerized systemsProtocols, traceability matrix, data integrity tests

Three rulebooks: FDA, USDA and the device regulation in Georgia plants

Georgia plants answer to three different federal rulebooks for qualification, and the first decision on any CQV program is which one governs. Human drugs and biologics, including the plasma products made near Covington and the biologics planned for Gwinnett County, are regulated by FDA under the current good manufacturing practice rules in 21 CFR 211 and the biologics rules in 21 CFR 600 through 680. Veterinary vaccines, such as those made in Athens, are veterinary biologics regulated by the USDA APHIS Center for Veterinary Biologics under the Virus-Serum-Toxin Act, and an establishment needs a US Veterinary Biologics Establishment License and product licenses under 9 CFR 102.

Medical device plants follow FDA’s Quality Management System Regulation, the amended 21 CFR 820 that took effect on February 2, 2026 and incorporates ISO 13485:2016 by reference. Under it, process validation, equipment qualification and software validation are framed in ISO 13485 terms, and a device plant’s qualification records are organized to show that alignment.

The engineering method, risk-based commissioning and qualification under ASTM E2500 and the ISPE Baseline Guide on commissioning and qualification, works under all three. What changes is the vocabulary of the protocols, the approval chain inside the owner’s quality unit, and the records a regulator will ask for. Paul Industries writes protocols in the language of the governing regulation, so an inspector reads evidence in familiar terms.

How are plasma fractionation systems qualified in Newton County?

Plasma fractionation qualification starts with temperature, because plasma intended for injectable products has to be stored at minus 20 degrees Celsius or colder immediately after filling under 21 CFR 640.69, and every step from frozen storage through thawing and pooling has to be shown to hold its limits. Freezers and cold rooms are mapped empty and loaded, alarms and backup systems are challenged, and recovery after a door opening or a power interruption is measured and recorded.

Downstream, fractionation and purification run at controlled low temperatures with ethanol and other process chemicals, so chilled glycol and brine systems, jacketed vessels and the areas classified for flammable vapors are qualified together with the process equipment. Purification skids, ultrafiltration and chromatography systems, WFI and clean steam distribution, CIP and SIP circuits and the fill-finish line each carry their own IQ, OQ and PQ. Paul Industries qualifies these systems with protocols that tie each test to a user requirement and a risk assessment, which keeps the test count proportionate to the risk.

Fill-finish lines for plasma products are qualified in two layers. The equipment, from vial washers and depyrogenation tunnels to fillers, stoppering and capping, goes through IQ and OQ, and sterilization of components and product paths is proven with heat penetration and biological indicator studies. The aseptic process itself is then proven by process simulation, the media fill, which under FDA’s aseptic processing guidance means three consecutive successful runs for initial qualification and repeat runs twice a year on each line after that. Paul Industries plans the equipment qualification so the media fill program starts on schedule.

A plasma campus also runs constant change: new freezers, added purification capacity and replaced utilities. Each change goes through the site’s change control, and the requalification needed is set by impact assessment, so a like-for-like replacement can be closed with targeted testing rather than a full repeat of the original qualification.

Animal vaccine plants in Athens: inactivation, containment and kill systems

Animal vaccine plants in Athens qualify a set of systems that human pharmaceutical plants seldom need at the same scale: culture systems for growing the organisms, inactivation steps that render them non-infectious, containment for live agents, and biowaste systems that decontaminate liquid effluent and solid waste before it leaves the building. Each of those is a process where a failure has consequences beyond product quality, so qualification evidence is held to a high standard.

Autoclaves and liquid effluent decontamination systems are qualified with heat distribution and heat penetration studies and biological indicators placed at the worst-case locations. Containment areas are qualified for pressure cascades, airflow direction and filter integrity. Inactivation is proven as a process step with time, temperature and mixing data. Paul Industries builds and qualifies these systems with protocols written for the USDA licensing record, and the pressure vessel fabrication in Georgia page covers the vessels at the center of many of them.

Commissioning qualification and validation on a Georgia greenfield site

Commissioning qualification and validation on a Georgia greenfield site, such as a biologics plant planned over six or seven years of design and construction, is most efficient when it is planned from basic design, because the documents created during construction are the ones qualification relies on. A C&Q plan written early sets which systems are direct impact, which tests commissioning will run and how those results will be used in qualification, and what the turnover packages must contain.

CQV phases on a Georgia life sciences project
PhaseMain activitiesKey deliverablesApproved by
PlanningUser requirements, system boundaries, impact and risk assessmentC&Q plan, system list, requirements traceability matrixOwner engineering and quality unit
Design reviewCheck design against requirements and critical aspectsDesign review records, design qualification where usedOwner quality unit
Construction and turnoverInspection, testing, flushing, pressure tests, weld documentationEngineering turnover packagesEngineering, reviewed by quality
CommissioningFactory and site acceptance tests, start-up, functional testsCommissioning test records, punch list closureEngineering
QualificationIQ and OQ on direct impact systems, using commissioning results where justifiedExecuted protocols and summary reportsOwner quality unit
Performance and processPQ of utilities and equipment, then process validation runsPQ reports, release for manufacturingOwner quality unit

Construction quality feeds this directly. Weld logs, material certificates, passivation and pressure test records from the process piping in Georgia and industrial welding services in Georgia work become the evidence an IQ verifies, and gaps there turn into deviations later. Paul Industries builds and documents the systems and then qualifies them, so the records are created with qualification in mind.

Why do Georgia operating certificates for autoclaves and vessels belong in an IQ?

Georgia operating certificates for autoclaves, sterilizers, jacketed vessels and steam generators matter in an IQ because the Boiler and Pressure Vessel Safety Act, O.C.G.A. Title 25, Chapter 15, makes it unlawful to operate a boiler or pressure vessel without a valid inspection certificate. The state rules, Chapter 120-3-26, require ASME Code construction, shop inspection by a National Board commissioned inspector and National Board registration for regulated vessels.

An IQ for pressure equipment in a Georgia plant therefore verifies the ASME nameplate, the manufacturer’s data report, the National Board registration and the state inspection certificate alongside the usual drawings, materials and calibrations. Arranging the state installation inspection early keeps it from holding up OQ. The equipment side of this is covered on the boiler repair in Georgia page for steam generators and boilers serving clean utilities.

Which cleanroom and HVAC tests apply to Georgia fill and finish suites?

Cleanroom and HVAC qualification for Georgia fill and finish suites, purification areas and device cleanrooms follows ISO 14644 for classification and testing, and FDA’s aseptic processing guidance for sterile products, with EU GMP Annex 1 added wherever product is exported to Europe. The HVAC system is commissioned first, balancing airflow and proving controls, and the rooms are then qualified at rest and in operation.

Cleanroom and HVAC qualification tests and what they prove
TestReferenceWhat it provesWhen it is run
Airflow volume and velocityISO 14644-3Supply air delivers the design air change rate or unidirectional velocityOQ, then at requalification
HEPA filter installed leak testISO 14644-3Filters and their seals are free of leaksOQ and after any filter change
Room pressure differentialsOwner design basis, FDA aseptic guidanceAir moves from cleaner to less clean areas, including containment cascadesOQ with door-open and recovery checks
Airborne particle classificationISO 14644-1The room meets its ISO class at rest and in operationOQ at rest, PQ in operation
Recovery testISO 14644-3The room returns to its class within the set time after a challengeOQ
Airflow visualizationFDA aseptic guidance, EU GMP Annex 1Unidirectional flow sweeps critical zones without turbulenceOQ and after changes to equipment layout
Temperature, humidity and environmental monitoringOwner requirementsConditions and microbial levels hold through seasons and operationsPQ and ongoing monitoring

Georgia’s long, humid summers put the dehumidification side of HVAC under its heaviest load, so a PQ that spans a summer gives better evidence of humidity control than one completed in winter. Paul Industries plans HVAC PQ timing with that in mind and links the room data to the environmental monitoring program the plant runs afterward.

How are computerized systems and data integrity proven at Georgia plants?

Computerized systems at Georgia plants, from building management and environmental monitoring systems to batch control, chromatography skids and data historians, are proven fit for use through computer system validation scaled to their risk under GAMP 5. Where records and signatures are kept electronically for FDA-regulated product, 21 CFR Part 11 sets the controls for audit trails, access, electronic signatures and record retention.

In OQ, data integrity is tested rather than assumed: user roles are challenged so that operators cannot change setpoints or delete data beyond their permissions, audit trails are checked to capture who changed what and when, alarms and time synchronization are verified, and backup and restore are demonstrated. For veterinary biologics plants the same discipline applies under the owner’s quality system and USDA expectations, even where Part 11 itself is not the governing rule. Paul Industries writes and executes these tests with the automation on the systems it builds and on systems supplied by equipment vendors.

Water, clean steam and utilities on Georgia campuses

Water, clean steam and process gas utilities on Georgia campuses are qualified in phases, with water systems following the familiar pattern of intensive sampling during an initial phase, extended sampling while the system enters routine use, and a long-term phase covering a full year of seasonal variation. Feed water to metro Atlanta and Athens plants comes from surface water supplies, so pretreatment performance through seasonal changes in temperature and organic load is part of what the first year of data shows.

Clean steam is qualified for condensate quality and, for sterilization service, for non-condensable gases, superheat and dryness. Compressed air and nitrogen in contact with product are tested for particulates, moisture, oil and microbial content at points of use. The ultrapure water systems in Georgia page covers water treatment design, and the failed water system validation page covers what happens when results drift.

Change control and requalification at Georgia plants in production

Change control at Georgia plants in production decides how much requalification each modification needs, using an impact assessment that asks whether the change affects a critical aspect of a qualified system. Replacing a pump with an identical model may need only documentation and a functional check; changing a control sequence, a material of construction or a sterilization cycle needs targeted OQ or PQ testing and sometimes process revalidation.

Periodic review keeps qualified systems in their validated state between changes: trend data from water systems, environmental monitoring, calibration history and deviation records are reviewed on a schedule, and a decision is recorded on whether requalification is needed. Paul Industries carries out the engineering change, updates the drawings and records, and executes the requalification protocols, so the change and its evidence close together.

Cost drivers for a Georgia qualification program

The cost of a Georgia qualification program is driven by the number of direct impact systems, the regulator and owner procedures that govern the protocols, how much commissioning evidence can be used in place of repeated tests, and the length of PQ, especially for water systems that run through a year of monitoring. A single autoclave or skid qualification and a site-wide program for a new biologics plant differ by orders of magnitude in effort.

Other drivers are protocol review cycles in the owner’s quality unit, the state of existing documentation on legacy systems, computerized system validation and data integrity testing, and the access and production windows available. Paul Industries gives a budget range from comparable systems once the system list and requirements are known, and a firm price after the C&Q plan is agreed.

Who provides validation and commissioning in Georgia?

Paul Industries provides validation and commissioning in Georgia, building, commissioning and qualifying process systems, utilities and equipment for plasma, vaccine, biologics, pharmaceutical and device plants in Covington, Social Circle, Athens, Gwinnett County, metro Atlanta, Augusta and Savannah. Paul Industries is headquartered at 256 Shore Drive, Kilmarnock, Virginia; it was formerly based in northern New Jersey and then Pennsylvania, and as an East Coast contractor it takes qualification work in every part of Georgia, throughout the 50 states and at international plants.

The same company that builds a system can write and execute its qualification, which shortens the path between construction records and executed protocols and keeps one party accountable for both. Paul Industries also qualifies packaged equipment and systems supplied by equipment vendors, reviewing their documentation against the owner’s requirements and filling gaps with field testing. For operating Georgia plants, that includes single systems added between campaigns, legacy systems whose original records need rebuilding before a regulatory inspection, and periodic requalification of autoclaves, cold rooms and water systems on the plant’s calendar. The Virginia program is on the validation and commissioning in Virginia page for the headquarters state, and work for the Triangle biologics plants on the validation and commissioning in North Carolina page. The Georgia page summarizes all Georgia work.

Commissioning and qualification from Paul Industries across Georgia

Paul Industries designs, builds, commissions and qualifies process systems and utilities for Georgia life sciences plants, as qualification-only scopes on existing or vendor-built systems, as design-build packages with CQV included, or as complete installations through PQ. Deliverables include C&Q plans, risk assessments, traceability matrices, IQ, OQ and PQ protocols and reports, and turnover packages written for the regulator that governs the site. Call 201-450-8280 or request a quote.

Standards referenced: 21 CFR 211 · 21 CFR 600-680 · 21 CFR 640.69 · 21 CFR Part 11 · 21 CFR 820 (QMSR) and ISO 13485:2016 · 9 CFR 101-117 (Virus-Serum-Toxin Act regulations) · ASTM E2500 · ISPE Baseline Guide Volume 5: Commissioning and Qualification · GAMP 5 · ASME BPE · ISO 14644-1 and ISO 14644-3 · FDA Guidance: Sterile Drug Products Produced by Aseptic Processing · EU GMP Annex 1 · ASME Boiler and Pressure Vessel Code · Georgia Boiler and Pressure Vessel Safety Act (O.C.G.A. Title 25, Chapter 15) · Georgia Rules for Boilers and Pressure Vessels (Rule 120-3-26)

Frequently asked questions

Who provides commissioning and qualification for plasma plants in Covington and Newton County?

Paul Industries provides commissioning and qualification for plasma fractionation and biologics systems in Covington, Social Circle, Stanton Springs and the rest of Newton and Walton counties. The work covers freezer and cold room mapping, purification and fill-finish equipment, WFI and clean steam, and CIP and SIP circuits, with protocols written to FDA biologics and 21 CFR 211 expectations.

Does Paul Industries qualify vaccine and bioprocess systems in Athens?

Paul Industries qualifies vaccine, biologics and bioprocess manufacturing systems in Athens and Athens-Clarke County, including autoclaves, liquid effluent decontamination, containment areas, process vessels and cleanroom utilities. For veterinary vaccine plants, protocols and reports are organized for the USDA Center for Veterinary Biologics licensing record rather than FDA filings.

Who handles CQV in Gwinnett County and along the Highway 316 corridor?

Paul Industries handles commissioning, qualification and validation in Gwinnett County, Lawrenceville, Buford and along the Highway 316 corridor toward Athens, from early C&Q planning on greenfield biologics projects to qualification of new and modified systems at operating plants. Early involvement lets construction records be built to serve the IQ directly.

Which are the top pharmaceutical companies in Georgia by manufacturing footprint?

The top pharmaceutical companies in Georgia by manufacturing footprint include Takeda, whose plasma campus near Covington it describes as the largest biotech manufacturing facility in the state; Boehringer Ingelheim Animal Health, with its vaccine operation in Athens and more than 1,200 Georgia employees; and UCB, which announced a $2 billion biologics plant in Gwinnett County in 2026. Paul Industries qualifies systems for plants of that kind.

Do the top pharmaceutical companies in Atlanta manufacture in the metro area?

Many of the top pharmaceutical companies in Atlanta run headquarters, commercial and distribution operations in the city itself, while most large manufacturing sits on the metro edge and beyond: Newton County to the east, Gwinnett County to the northeast and Athens-Clarke County further along Highway 316. Qualification work follows the plants, and Paul Industries takes it at each of those locations.

Is Atlanta a biotech hub for manufacturing as well as research?

Atlanta is a biotech hub for research through its universities and public health institutions, and its manufacturing base has grown on the metro edge: plasma products near Covington, vaccines and bioprocess supply in Athens, and a $2 billion biologics plant planned in Gwinnett County. Each manufacturing site needs commissioning and qualification, which Paul Industries provides.

Which agency regulates an animal vaccine plant in Georgia?

An animal vaccine plant in Georgia is regulated by the USDA APHIS Center for Veterinary Biologics under the Virus-Serum-Toxin Act, and it needs a US Veterinary Biologics Establishment License and product licenses under 9 CFR 102. Animal drugs that are not biologics fall under FDA’s Center for Veterinary Medicine. Qualification records are organized for whichever agency governs the product.

How is a plasma freezer or cold room qualified for storage at minus 20 C?

A plasma freezer or cold room is qualified with an IQ of the unit, controls and alarms, then temperature mapping empty and fully loaded to find the warmest locations, door-opening and power-failure recovery tests, and alarm challenges. Results must show storage not warmer than minus 20 degrees Celsius under 21 CFR 640.69, with monitoring probes placed at the mapped worst cases.

What does FDA's QMSR change for device plants qualifying equipment in 2026?

FDA’s Quality Management System Regulation, which took effect February 2, 2026, amended 21 CFR 820 to incorporate ISO 13485:2016 by reference. Device plants in Georgia now frame process validation, equipment qualification and software validation in ISO 13485 terms, so qualification records are organized to show that alignment. Paul Industries writes device-plant protocols in that structure.

Does an autoclave in Georgia need a state certificate before it is qualified?

An autoclave or other pressure vessel in Georgia needs a valid state inspection certificate to operate under O.C.G.A. Title 25, Chapter 15, so the certificate, ASME nameplate, data report and National Board registration are verified during IQ. Arranging the state inspection early keeps OQ heat distribution and penetration studies on schedule. Paul Industries plans both steps together.

How many years should a Georgia greenfield biologics project allow for CQV?

A Georgia greenfield biologics project runs CQV across its whole schedule rather than at the end: planning starts in basic design, commissioning follows mechanical completion system by system, and qualification and utility PQ overlap the last year or more of construction. UCB has said its Gwinnett County plant will take six to seven years of design and construction, which is typical for that scale.

How are vendor skids brought into a Georgia site's qualification program?

Vendor skids are brought into a Georgia site’s qualification program by reviewing the vendor’s design, materials, factory acceptance test and documentation against the owner’s requirements, deciding which factory tests can be used in place of site testing, and filling gaps with site acceptance testing and IQ and OQ. Paul Industries carries out that review and the field testing.

How is a liquid effluent decontamination system qualified at a vaccine plant?

A liquid effluent decontamination system at a vaccine plant is qualified with an IQ of tanks, heating, controls and instruments, an OQ of the heating and hold sequence and alarms, and a PQ that proves the kill cycle with temperature data and biological indicators at worst-case locations under the expected load. Paul Industries builds and qualifies these systems.

What construction records does an IQ at a Georgia plant rely on?

An IQ at a Georgia plant relies on as-built drawings and P&IDs, material certificates, weld logs and weld maps, borescope records, passivation and cleaning records, pressure test records, instrument calibration certificates, vendor manuals and the commissioning test results. Paul Industries assembles those records during construction so the IQ verifies them rather than recreating them.

What triggers requalification after a change at an operating Georgia plant?

Requalification after a change at an operating Georgia plant is triggered when the impact assessment finds the change affects a critical aspect of a qualified system, such as a material of construction, a control sequence, a sterilization cycle or a capacity limit. Like-for-like replacements often need only documentation and functional checks. Paul Industries executes the change and the testing it calls for.

How much does validation and commissioning cost for a Georgia plant system?

Validation and commissioning for a Georgia plant system costs according to the system’s complexity and impact, the protocols the owner’s quality procedures require, how much commissioning evidence can be used in qualification, and the length of PQ. Paul Industries gives a budget range from comparable systems once the system list is known and a firm price after the C&Q plan is agreed.

What does Paul Industries need to quote qualification work in Georgia?

To quote qualification work in Georgia, Paul Industries needs the system list with P&IDs or descriptions, the user requirements or design basis, the regulator and owner procedures that govern protocols, the state of existing documentation, and the target dates. A budget range comes first, followed by a firm price once the C&Q plan is set.

Qualifying new or changed systems at a Georgia plant?

Send the system list, P&IDs or requirements, the governing regulator and your target dates. Call 201-450-8280 or request a quote.