A sanitary piping turnover package should let someone start from any single weld on a drawing and reach the welder, the procedure, the date, the examination result and the material heat – and start from a material heat and find every weld it appears in. Paul Industries delivers that documentation as standard on cGMP process piping installations nationwide.

Most packages are compliant. Fewer are usable. The difference only becomes visible during an investigation, which is the worst moment to discover it.

What the package has to contain

Document Source of the requirement What it lets you do later
Welding procedure specification and its procedure qualification record ASME Section IX Show the procedure was qualified for the material and thickness actually used
Welder performance qualification, current at the date of the weld ASME Section IX Show the individual was qualified when they made that weld, not merely at some point
Weld map and weld log, every weld identified ASME BPE Trace a suspect weld to a welder, a procedure, a date and an examination result
Examination records to the fluid service category ASME B31.3 Show the right proportion was examined for the service – Normal and Category M differ
Borescope records for internal weld examination ASME BPE Evidence internal weld quality, which cannot be judged from outside
Material test reports traceable to heat number ASTM A270, ASME BPE Tie installed material to its certification – what 21 CFR 211.184 relies on
Passivation record with acceptance test result ASTM A967 / A380 Evidence the 211.65(a) obligation that surfaces are not reactive or additive
Slope and drainability verification ASME BPE, project spec Show the system drains, which cleaning and sterilization depend on
Pressure test and cleanliness records ASME B31.3, project spec Close out mechanical integrity and handover condition
Instrument index with calibration certificates 21 CFR 211.68(a) Hand the calibration program to maintenance rather than leaving it to be invented

Get a single-source quote

Service needed *

The two questions that separate real packages from paperwork

What percentage of weld identities were borescoped, and who witnessed it? A package can be complete and still rest on a small unwitnessed sample. Ask before award, not at handover.

Can you trace in both directions? Weld to material is the easy direction and most packages manage it. Material heat back to every weld it appears in is the direction that matters when a heat is questioned, and it is the one most often missing.

More on how this maps to the regulation on our quality and documentation page.

Related questions

What is a turnover package?

The complete documentation set handed over at the end of a piping installation – weld records, material certifications, examination results, passivation records, pressure tests and calibration certificates. It is the evidence base for obligations the owner carries for the life of the system, not merely a contractual deliverable.

What weld documentation is required for ASME BPE piping?

A qualified welding procedure specification with its procedure qualification record, current welder performance qualifications, a weld map and weld log identifying every weld, examination records appropriate to the fluid service category under ASME B31.3, and borescope records for internal examination of hygienic welds.

Why do material test reports need heat numbers?

Because traceability to heat number is what ties the installed material to its certification. If a heat is later questioned, the heat number is the only way to find every weld and every component it appears in. 21 CFR 211.184 relies on records identifying the materials used, and a certificate without traceability does not provide that.

What should I ask a contractor before award?

What percentage of weld identities will be borescoped and who witnesses it; whether traceability runs in both directions from weld to material and from material heat back to welds; which codes they work to by number rather than by name; and whether they self-perform or broker the work.