Paul Industries is a US process equipment contractor for Taiwan that designs, fabricates and commissions ultrapure water skids, chemical and slurry distribution modules, process cooling and chilled water systems, purified water and WFI systems, pressure vessels and high-purity piping for semiconductor fabs, pharmaceutical and biotech plants, and petrochemical and chemical sites, built for Taiwan’s 60 Hz supply and its pressure equipment inspection rules. Every system leaves the US fabrication floor after a witnessed factory acceptance test, sails to the port of Kaohsiung, Taichung or Keelung, and Paul installs, starts up and commissions it on site or supervises its installation. Paul Industries has its headquarters at 256 Shore Drive in Kilmarnock, Virginia, after earlier bases in northern New Jersey and later Pennsylvania.
Request a quote or call 201-450-8280
The scope a US process equipment contractor for Taiwan delivers
A US process equipment contractor for Taiwan carries a utility or process system from user requirements through design, US fabrication, factory acceptance testing, export, the Pacific voyage and on-site commissioning, and hands the plant one record set that serves the Ministry of Labor inspection, the plant’s quality system and its maintenance team. Paul Industries builds ultrapure water systems, process cooling systems, pressure vessels, purified water and WFI systems, prefabricated pipe spools and complete skids with their controls.
Plants in Taiwan choose between three delivery routes. Supply with installation supervision fits a fab or plant running a large construction program, with Paul directing setting, hook-up and testing of each module. Design-build adds the utility room layout, distribution and controls. Turnkey delivery puts the whole system, from the user requirement specification to executed commissioning and qualification records, under one Paul contract. The international projects page places Taiwan among Paul’s Asia Pacific destinations, alongside Japan, South Korea and Singapore.
Semiconductor companies in Taiwan and the utilities their fabs run on
Semiconductor companies in Taiwan operate fabs and packaging plants in three science park clusters: Hsinchu in the north, the Central Taiwan Science Park in Taichung, and the Southern Taiwan Science Park in Tainan and Kaohsiung. TSMC began 2-nanometer volume production at its Fab 20 in Hsinchu’s Baoshan district in late 2025 and at Fab 22 in Kaohsiung, and is developing Fab 25 in Taichung for 1.4-nanometer technology, with advanced packaging plants in Chiayi and Taichung. These names are market facts that show what fabs in Taiwan build; they describe no Paul project.
Chip manufacturing in Taiwan depends on utilities that run every hour of the year: ultrapure water at resistivity near 18.2 megohm-centimeters with total organic carbon in the low parts per billion, process cooling water held to tight temperature bands for tools, chilled water for cleanroom air handling, bulk and specialty chemical distribution, slurry distribution for chemical mechanical planarization, and wastewater treatment for fluoride, ammonia and copper streams. Semiconductor manufacturing in Taiwan also leans on reclaim: fabs recover rinse water and return it to the ultrapure water train, which adds reverse osmosis, ion exchange and polishing capacity.
Ultrapure water and chemical distribution for Taiwan semiconductor fabs
Taiwan semiconductor fabs buy ultrapure water trains with multimedia and ultrafiltration pretreatment, double-pass reverse osmosis, electrodeionization, vacuum degasifiers, ultraviolet TOC destruction, mixed-bed polishers and final ultrafilters, distributed in PVDF loops with continuous recirculation. Paul Industries builds those trains as tested skids, welds high-purity PVDF and stainless piping in controlled conditions, and documents particle, resistivity and TOC results at factory test. Chemical and slurry modules follow SEMI F57 for high-purity polymer components and SEMI F63 for ultrapure water quality as the fab’s specification calls for them. The semiconductor industry page explains how those utilities connect to tool hook-up.
Electronics manufacturing in Taiwan beyond the wafer fab
Electronics manufacturing in Taiwan extends past wafer fabrication into packaging and test, displays, printed circuit boards, passive components and server assembly, and those plants buy deionized water systems, process cooling, compressed dry air, exhaust scrubbing support and wastewater pretreatment. Paul builds DI water skids, closed loop cooling, glycol systems and pump skids for that work, sized for 220/380 V at 60 Hz and documented for the plant’s preventive maintenance system.
Wastewater and water reuse at fabs and packaging plants
Wastewater systems at fabs and packaging plants in Taiwan separate their streams before treatment: fluoride from etch and clean steps, ammonia and copper from planarization and plating, acid and alkali rinses, and organic solvents. Each stream needs its own reactor, dosing and solids handling, and the cleaner rinse streams are polished and returned to the ultrapure water train or used as cooling tower makeup. Paul builds neutralization, fluoride precipitation and copper removal skids, chemical dosing packages and reuse trains as tested modules, with instruments and controls wired for the plant’s distributed control system, as described on the process wastewater page.
| Cluster | Plants (market facts) | Usual receiving port | Systems Paul Industries supplies |
|---|---|---|---|
| Hsinchu and northern Taiwan | Advanced-node wafer fabs, biomedical park, electronics plants | Keelung or Taipei | Ultrapure water skids, process cooling, chemical distribution |
| Taichung and central Taiwan | Fab 25 site, advanced packaging, machinery and food plants | Taichung | Cooling water, DI water, pump skids, pipe spools |
| Yunlin (Mailiao) | Refinery and naphtha cracker complex | Taichung | Pressure vessels, heat exchanger bundles, alloy piping |
| Tainan, Kaohsiung and Chiayi | Southern science park fabs, packaging, petrochemical and steel plants | Kaohsiung | Ultrapure water reclaim, wastewater skids, vessels, exchangers |
Pharmaceutical companies in Taiwan and Taiwan GMP regulations
Pharmaceutical companies in Taiwan manufacture under Taiwan GMP regulations that follow the PIC/S Guide to Good Manufacturing Practice: the Taiwan Food and Drug Administration became a PIC/S participating authority on 1 January 2013, and the Pharmaceutical Affairs Act requires every pharmaceutical manufacturer in Taiwan to comply with PIC/S GMP. TFDA reported in 2025 that 144 pharmaceutical manufacturers and 28 active ingredient manufacturers in Taiwan held PIC/S GMP compliance, and it runs routine inspections every two to four years.
Taiwan FDA GMP inspections judge water, steam and process equipment by the same PIC/S annexes on sterile manufacture and on qualification and validation that apply across the scheme. For a plant seeking Taiwan GMP certification of a new line, Paul Industries supplies purified water and WFI systems, clean steam, formulation and buffer vessels, CIP and SIP skids and sanitary piping built to ASME BPE, with orbital weld logs, borescope records, passivation records and installation and operational qualification protocols in the plant’s format, executed under the validation and commissioning service. The pharmaceutical industry page lists the utilities a sterile or oral solids plant needs.
Biologics, vaccines and contract manufacturing utilities
Biologics, vaccine and contract manufacturing plants in Taiwan add equipment that small-molecule plants rarely need: media and buffer preparation vessels with tight temperature control, single-use and stainless bioreactor support utilities, clean-in-place for harvest and purification skids, and kill systems or inactivation tanks for biological waste. Hot WFI loops held above 65 degrees Celsius, or ozonated cold loops, supply formulation and cleaning, and clean steam serves SIP of vessels and transfer lines. Paul designs buffer and media hold vessels, CIP and SIP skids and biowaste inactivation systems with drainable layouts, sanitary instruments and sterile boundaries that are clearly defined in the drawings, so validation runs follow the same boundaries the operators work within.
Manufacturing in Taiwan: petrochemical, chemical and food plants
Manufacturing in Taiwan beyond electronics and medicines includes a large petrochemical base, with the Formosa Plastics Group’s Sixth Naphtha Cracker complex at Mailiao in Yunlin County, petrochemical plants in the Kaohsiung area, and specialty chemical producers that supply the fabs with solvents, acids and gases. Those sites buy pressure vessels, heat exchanger bundles, reactors and receivers, pump skids and alloy piping for turnarounds and debottlenecking, and Paul builds them to ASME Section VIII and ASME B31.3 for inspection under Taiwan’s rules, as covered on its chemical manufacturing page. Food and beverage plants across the west coast buy tanks, CIP and cooling from Paul on the same terms.
How do Taiwan pressure vessel regulations apply to an imported vessel?
Taiwan pressure vessel regulations sit in the Ministry of Labor’s Regulations for Safety Inspection of Hazardous Machines and Equipment, which treat boilers, Category A pressure vessels, high-pressure gas specific equipment and high-pressure gas containers as hazardous equipment subject to a chain of inspections. Category A covers vessels above the pressure and volume thresholds the regulations define, and a vessel made in Taiwan passes type, sealing and structure inspections during manufacture.
A Category A pressure vessel imported into Taiwan goes through re-inspection on the employer’s application before its completion inspection, and the application carries the vessel specification, the structure drawing and calculation sheet, and the inspection certificates from manufacture. The inspecting organization may exempt an imported vessel from all or part of that re-inspection where it is documented by proper corresponding inspection certificates. After installation the completion inspection clears the vessel for use, with a certificate valid for up to one year, and periodic inspection follows yearly, or every two years for vessels on continuous-production lines. Paul Industries delivers each vessel with the manufacturer’s data report, material certificates, weld maps, examination records and hydrostatic test report organized for that re-inspection file.
Taiwan pressure vessel code choice and seismic restraint
The Taiwan pressure vessel code a project uses is named in the purchase order and accepted through the inspection steps, and Paul designs to ASME Section VIII Division 1 or the code the owner specifies, with the calculation sheet and structure drawing prepared in the form the re-inspection application uses. Taiwan sits in an active seismic zone and is exposed to typhoons, so vessel supports, skid frames, rooftop cooling equipment and pipe racks need anchorage designed for the seismic and wind actions in the owner’s structural design basis. Paul supplies anchor loads with the first submittal and designs seismic bracing with the equipment.
| Requirement | Rule | What Paul Industries delivers |
|---|---|---|
| Imported Category A pressure vessel | Re-inspection on the employer’s application, then completion inspection | Specification, structure drawing, calculation sheet, data report, inspection certificates |
| Periodic inspection | Yearly, or every two years on continuous-production lines | Inspection access, relief valve data, maintenance plan |
| GMP equipment | PIC/S GMP under the Pharmaceutical Affairs Act, TFDA inspection | Design, installation and operational qualification protocols and reports |
| Fab utilities | Owner specification, SEMI F57 and F63 where called for | Factory water quality data, cleanliness and pressure test records |
| Electrical equipment | Taipower connection review, 60 Hz supply, CNS standards | Panel drawings, single-line diagrams, test records in Traditional Chinese and English |
Taiwan voltage and frequency for plant equipment
Taiwan voltage and frequency for plant equipment follow the Taiwan Power Company supply: 60 Hz, with low voltage service at 110 V and 220 V single phase and 220/380 V three-phase, distribution at 11.4 and 22.8 kV, and transmission at 69, 161 and 345 kV. For anyone asking what voltage does Taiwan use, or whether Taiwan voltage 110 or 220 is correct, the answer is both: 110 V serves lighting and outlets, 220 V serves larger single-phase loads, and plants run motors and process equipment on the 380 V three-phase supply or on Taiwan high voltage service with their own substations.
Taiwan electricity frequency matches the US 60 Hz grid, so pumps, fans and compressors keep their US speeds and curves. Asked whether Taiwan voltage is the same as US supply, engineers get a split answer: 110 V outlets sit close to US 120 V, but Taiwan three phase voltage at 380 V differs from the US 480 V and 208 V systems. Taiwan voltage vs US designs therefore changes motor windings, drive ratings, heater elements and transformer taps rather than speeds, and Paul specifies 380 V, 60 Hz motors and drives from the start.
Taiwan industrial voltage, panels and documentation
Taiwan industrial voltage at a fab or chemical plant is usually stepped down from 22.8 or 11.4 kV, or from higher transmission levels at large sites, to the 380 V buses that feed process equipment, so a Taiwan 3 phase power supply at the skid needs panels rated for the fault levels of those buses. Taiwan power supply voltage tolerances and the plant’s ride-through rules for voltage dips shape drive and UPS selection on critical utilities such as ultrapure water and process cooling. Paul builds panels to the plant’s electrical specification with CNS-aligned components where the specification calls for them, labels in Traditional Chinese and English, and a Taiwan voltage 3 phase single-line diagram, cable schedule and test record set for the site connection review.
Shipping to Taiwan from USA ports: the port of Kaohsiung, Taichung and Keelung
Shipping to Taiwan from USA East Coast ports takes about 30 to 42 days from Savannah to the port of Kaohsiung, Taiwan, on direct and single-transshipment services, and around 50 days from New York on the quickest listed routing, based on forwarder transit data. The port of Kaohsiung serves the southern science park, petrochemical and steel plants, Taichung serves central Taiwan and the Mailiao area, and Keelung and Taipei serve the north, including Hsinchu.
Kaohsiung port handles containers and flat racks for oversize skids and vessels, and the road leg to the plant decides module size. Paul lays out skids to fit 40-foot high cube containers where the process allows, ships tanks and frames on flat racks, marks centers of gravity and lifting points, and sends rigging drawings ahead so cranes and transport permits are arranged before arrival. Between Kaohsiung port and Keelung port, the choice follows the plant location and the sailing that lands the equipment soonest ahead of the installation window. Crates use ISPM 15 heat-treated wood, high-purity modules ship nitrogen-purged and double-bagged, and contracts use Incoterms 2020, most often FCA at the US loading port, CIF Kaohsiung or DAP at the plant gate.
Keeping high-purity modules clean on the voyage
High-purity modules for Taiwan fabs and pharmaceutical plants spend weeks at sea in warm, humid air, so cleanliness is protected at the factory rather than restored on arrival. Paul dries every circuit after hydrostatic testing, fills stainless and PVDF piping with dry nitrogen at slight positive pressure, caps every connection, double-bags critical assemblies and adds desiccant and humidity indicators to each crate. Receiving checks at the plant confirm that purge pressure held, indicators stayed dry and bags arrived intact before any module enters a cleanroom support area.
Taiwan import duty, the Taiwan VAT rate and clearance
Taiwan import duty is charged on the customs value by tariff heading, so the pumps, vessels and panels shipped together on one order can fall under different headings, and Taiwan import duty rates generally range from zero to 30 percent depending on the goods. The Taiwan VAT rate, called business tax, is 5 percent and is charged on the customs value plus duty, and a trade promotion service fee of 0.04 percent of the customs value is added at entry. VAT-registered plants generally recover the business tax as input tax. Paul lists each item by heading, weight, value and origin on the commercial invoice and packing list, so the importer’s customs agent clears the shipment cleanly.
Project stages from requirements to handover in Taiwan
Paul Industries runs a Taiwan project in nine stages, and the first two lock the code basis, the 380 V, 60 Hz equipment selection, the inspection route for any pressure vessel and the qualification or water quality acceptance criteria. The table lists each stage and its output.
| Stage | Activity | Output for the Taiwan plant |
|---|---|---|
| 1. Requirements | Water quality or GMP targets, 220/380 V, 60 Hz supply, site constraints | Signed requirement specification |
| 2. Design | ASME VIII, ASME B31.3 and ASME BPE design with seismic supports and 380 V electrics | Drawings, calculation sheets, design review minutes |
| 3. Fabrication | Orbital and PVDF welding, NDE, passivation and US panel assembly | Mill certificates, weld logs, examination and borescope files |
| 4. Factory test | Pressure, function and water quality runs with the plant’s engineers present or on video | FAT report with punch list |
| 5. Export | Purging, bagging, ISPM 15 crating, sailing to Kaohsiung, Taichung or Keelung | Invoice, packing list, bill of lading |
| 6. Entry and inspection file | Customs clearance, duty and business tax, vessel re-inspection application documents | Cleared equipment and inspection document set |
| 7. Installation | Paul sets, connects and wires the modules, or supervises that work | Field records and marked-up drawings |
| 8. Commissioning | Water quality ramp-up, IQ and OQ, completion inspection support | Executed protocols and acceptance data |
| 9. Handover | Training, spares, periodic inspection and maintenance plan | Manuals and as-built package in English and Traditional Chinese |
After handover Paul services the systems it supplied with planned maintenance, membrane and resin change-outs, requalification, spare parts and repairs, and keeps vessel records ready for each periodic inspection.
Who builds process systems for plants in Taiwan?
Paul Industries builds process systems for plants in Taiwan: ultrapure water trains, reclaim skids, process cooling and chemical distribution modules for fabs in Hsinchu, Taichung, Tainan and Kaohsiung; purified water, WFI, clean steam, vessels and CIP for pharmaceutical and biotech plants under PIC/S GMP; and pressure vessels, exchangers and alloy piping for petrochemical and chemical sites at Mailiao and Kaohsiung. Paul engineers each system for 380 V at 60 Hz, documents its pressure equipment for re-inspection and completion inspection, then installs and commissions it, or supervises its installation, with a single contract and record set. The Japan page covers another Asian market whose fabs and pharmaceutical plants buy from Paul on the same model.
What drives the delivered cost of a system for a plant in Taiwan?
The delivered cost of a system for a plant in Taiwan depends on six items beyond the equipment, and Paul’s proposal prices each of them separately in US dollars.
- Voltage engineering. 380 V motors, drives, heaters and panels, with Traditional Chinese labels, change component selection on a US design.
- Purity scope. PVDF and electropolished stainless, cleanroom assembly and water quality testing for fab utilities set much of the fabrication figure.
- Inspection documents. Calculation sheets, structure drawings and certificates for vessel re-inspection, and qualification protocols for GMP equipment.
- Freight. A Pacific voyage of four to seven weeks, flat racks for oversize items and the road leg from Kaohsiung, Taichung or Keelung.
- Border costs. Duty by heading, business tax at 5 percent and the trade promotion fee, under the Incoterm the plant chooses.
- Site route. Full installation inside an operating fab, with gowning and tool-down windows, costs more than supervision; Paul prices both.
Paul Industries for Taiwan fabs, pharmaceutical and chemical plants
Paul Industries designs, fabricates and tests ultrapure water, cooling and chemical systems, pressure vessels, water and steam systems, skids and piping for plants across Taiwan, ships them to Kaohsiung, Taichung or Keelung, and installs and commissions them or supervises installation, with inspection, electrical and qualification records in English and Traditional Chinese. With the user requirements, site supply details, code basis and target start-up in hand, Paul prepares a US dollar proposal covering fabrication, sailing, site work and commissioning dates. Ask for a quote for a plant in Taiwan.
Standards referenced: Regulations for Safety Inspection of Hazardous Machines and Equipment (Ministry of Labor) · Occupational Safety and Health Act (Taiwan) · PIC/S GMP Guide (TFDA) · Pharmaceutical Affairs Act · ASME Boiler and Pressure Vessel Code Section VIII · ASME BPE · ASME B31.3 · SEMI F57 and SEMI F63 · CNS standards · Incoterms 2020 · ISPM 15
Frequently asked questions
Which three-phase supply do Taiwan plants run process motors on?
Taiwan Power Company supplies three-phase plant power at 220/380 V and 60 Hz, with 110 V and 220 V single phase for lighting and smaller loads, and larger plants take 11.4 kV, 22.8 kV or higher and step it down on site. Paul Industries builds skids for Taiwan with 380 V, 60 Hz motors and drives, and control circuits to the plant’s specification.
Is Taiwan electricity frequency the same as in the United States?
Taiwan runs at 60 Hz like the United States, so pumps, fans and compressors keep their US speeds and performance curves. The change is in voltage: 380 V three-phase in place of 480 V. Paul Industries selects 380 V motors, drives and heaters in the original design and tests them at factory acceptance.
Who builds ultrapure water systems for semiconductor fabs in Hsinchu and Tainan?
Paul Industries designs and fabricates ultrapure water trains, reclaim skids and polishing loops for semiconductor fabs in Hsinchu, Tainan and Kaohsiung, with reverse osmosis, electrodeionization, degasification, ultraviolet TOC reduction, mixed-bed polishing and ultrafiltration. Each skid is factory tested for resistivity, TOC and particles, shipped purged and bagged, and installed and commissioned by Paul or under Paul’s supervision.
How does an imported pressure vessel pass inspection in Taiwan?
An imported Category A pressure vessel in Taiwan goes through re-inspection on the employer’s application, with the vessel specification, structure drawing, calculation sheet and inspection certificates, and the inspecting organization may exempt all or part of it where proper corresponding certificates exist. Completion inspection follows installation. Paul Industries organizes the data report and records for that file.
How often are pressure vessels inspected in Taiwan once in service?
Category A pressure vessels in Taiwan carry a completion or periodic inspection certificate valid for up to one year, and periodic inspection runs yearly, or every two years for vessels connected to continuous-production lines or used for power generation. Paul Industries designs inspection openings and access into each vessel and supplies a maintenance plan matched to that cycle.
Which GMP standard applies to pharmaceutical plants in Taiwan?
Pharmaceutical plants in Taiwan follow PIC/S GMP, which the Pharmaceutical Affairs Act makes mandatory for every pharmaceutical manufacturer, and TFDA has been a PIC/S participating authority since January 2013. Paul Industries builds water, steam and process equipment for Taiwan plants to ASME BPE and the PIC/S annexes, with qualification protocols in the plant’s format.
Who supplies WFI and clean steam systems for biotech plants around Hsinchu and Taipei?
Paul Industries designs, fabricates and qualifies WFI generation and distribution, clean steam generators, formulation and buffer vessels and CIP and SIP skids for biotech and pharmaceutical plants around Hsinchu and Taipei. Each system ships with orbital weld records, passivation records and IQ and OQ protocols, and Paul installs and commissions it or supervises installation.
Which equipment do petrochemical plants at Mailiao and Kaohsiung order from US fabricators?
Petrochemical and refinery plants at Mailiao in Yunlin County and around Kaohsiung order pressure vessels, heat exchanger bundles, reactors and receivers, pump skids and alloy piping spools for turnarounds and upgrades. Paul Industries builds them to ASME Section VIII and ASME B31.3, documents them for Taiwan’s vessel inspections, and times delivery to the turnaround window.
How long does shipping a skid from the US East Coast to Kaohsiung take?
Forwarder transit data puts Savannah to Kaohsiung at about 30 to 42 days, and New York to Kaohsiung at around 50 days on the quickest listed routing, depending on carrier and transshipment. Customs clearance and the road leg are added. Paul Industries books the sailing that lands equipment ahead of the plant’s installation window.
What is the Taiwan VAT rate on imported process equipment?
Taiwan charges business tax, its form of VAT, at 5 percent on imported goods, calculated on the customs value plus import duty, and a trade promotion service fee of 0.04 percent of the customs value is added. Registered businesses generally recover the business tax as input tax. Paul Industries itemizes invoices so the importer’s customs agent calculates each charge accurately.
How are Taiwan import duty rates set for a skid?
Taiwan import duty rates depend on the tariff heading of each item and generally range from zero to 30 percent, so a skid is declared either as one machine or item by item. Paul Industries prepares the classification detail, values, weights and origin with the shipping documents and quotes delivered terms when a plant prefers a landed price.
Which port should equipment for a Taichung fab or factory use?
Equipment for fabs and factories in Taichung and central Taiwan usually lands at Taichung port, which keeps the road leg short, while Kaohsiung serves the south and Keelung or Taipei serve the north. Paul Industries checks the road route from the port to the site before sizing modules and marks lifting points on every module.
Are manuals and drawings for Taiwan plants written in Traditional Chinese?
Paul Industries supplies manuals, labels, panel drawings and inspection documents for Taiwan plants in Traditional Chinese and English, with metric units throughout. Qualification protocols and turnover files follow the plant’s document control format, and inspection documents are arranged in the order the re-inspection and completion inspection applications use.
How are skids and vessels anchored against earthquakes and typhoons in Taiwan?
Plants in Taiwan design equipment anchorage for the seismic and wind actions set in the owner’s structural design basis, since Taiwan sits in an active seismic zone with typhoon exposure. Paul Industries designs skid frames, vessel supports, rooftop cooling equipment and pipe supports to those actions, supplies anchor loads for foundations and records the calculations in the turnover file.
Can engineers from a Taiwan plant witness the factory acceptance test?
Plant engineers from Taiwan witness Paul Industries factory tests in person in the United States or follow them on a live video feed, watching pressure tests, water quality runs and interlock checks and reviewing the records. The signed FAT report and punch list are closed out before the crates are sealed.
What process cooling do fabs in Tainan and Kaohsiung need?
Fabs in Tainan and Kaohsiung run process cooling water loops held within tight temperature bands for tools, chilled water for cleanroom air handling, and heat recovery between them, all with redundant pumps and controls. Paul Industries builds process cooling skids, heat exchanger packages and chilled water modules for 380 V at 60 Hz, factory tested before shipment.
Which project details does Paul need to price a system for Taiwan?
Paul Industries prices a Taiwan system from the process description or user requirements, water quality or GMP targets, the site layout and electrical supply, the code basis, the start-up date and the Incoterm the plant prefers. The US dollar proposal splits equipment, engineering, freight, border charges and site work so each can be compared.
How is equipment maintained after commissioning in Taiwan?
Paul Industries services Taiwan installations with planned maintenance, membrane, resin and filter change-outs, requalification runs, spare parts, passivation of stainless systems and repairs. Maintenance plans follow each vessel’s periodic inspection cycle, and service reports are filed against the asset records from the original turnover package.
Planning process equipment for a plant in Taiwan?
Tell Paul Industries what the system must deliver, where it will stand and when it must run, and the reply gives a budget in US dollars with fabrication and sailing dates. Call 201-450-8280 or request a quote.
