Paul Industries is a US process equipment contractor for the United Kingdom, designing and fabricating process skids, pressure vessels, purified water and WFI systems, CIP units and hygienic piping in the United States for pharmaceutical, vaccine, food and chemical plants in England, Scotland, Wales and Northern Ireland. Every system is built to the Pressure Equipment (Safety) Regulations 2016 with UKCA or CE marking, documented so the plant meets its duties under the Pressure Systems Safety Regulations 2000, and engineered for the British 50 Hz supply. After a factory acceptance test and shipment to Felixstowe, Southampton or Liverpool, Paul installs and commissions the system or supervises its installation, and hands over the full qualification file.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
GB pressure equipment law Pressure Equipment (Safety) Regulations 2016, UKCA or CE
In-service duty PSSR 2000 written scheme of examination before first use
Supply 230 V phase to neutral, 400 V three phase, 50 Hz
Medicines regulator MHRA, standalone UK regulator since 1 January 2021
Reviewed November 2026

What a US process equipment contractor for the United Kingdom supplies

A US process equipment contractor for the United Kingdom supplies equipment that a British plant can lawfully put into service and then operate under its own statutory duties: a design and conformity file under UK product law, fabrication with full traceability, a witnessed factory test, export packing, and installation, start-up and qualification at the site. Paul Industries, whose headquarters are at 256 Shore Drive in Kilmarnock, Virginia, delivers the whole chain under one contract and one schedule.

British plants order the same families of equipment from Paul as American ones: pump and dosing skids, fabricated pressure vessels, purified water and WFI systems, CIP and SIP systems, process tanks, and the process piping that links them. For a new building or a line extension, Paul combines them into a turnkey process system. Plants choose between supply with installation supervision, design-build with layout and utility design, and complete installation through qualification.

Plants that shortlist pressure vessel manufacturers UK-wide often find that domestic shops are booked through the same capital programmes they are trying to deliver. Paul gives the project a transatlantic supply line, with shop capacity in the United States and documentation written for British law from the first page.

Which UK regulations apply to pressure equipment after Brexit?

Pressure equipment placed on the market in Great Britain is governed by the Pressure Equipment (Safety) Regulations 2016, SI 2016/1105, which took over the role the EU directive played before Brexit and keep its structure of hazard categories, conformity assessment modules and essential safety requirements. Once the equipment is installed, the plant’s duties come from the Pressure Systems Safety Regulations 2000. The two sets of UK pressure vessel regulations sit at opposite ends of the equipment’s life: one governs how it is made and marked, the other how it is examined and operated.

UKCA or CE: marking pressure equipment for Great Britain and Northern Ireland

The Pressure Equipment Safety Regulations require a conformity mark on equipment above the sound engineering practice threshold, and Great Britain now accepts either the UKCA mark or the CE mark. The UK government announced in August 2023 and January 2024 that recognition of CE marking would continue indefinitely for the regulations owned by the Department for Business and Trade, and the Pressure Equipment Safety Regulations 2016 are among them. On CE marking, UK law since October 2024 confirms that a vessel conforming to the EU directive can be placed on the British market without a second assessment.

Northern Ireland follows different rules. Under the Windsor Framework it applies EU product law for goods, so pressure equipment for a plant in Belfast or County Antrim carries the CE mark, or the CE mark with the UKNI mark where a UK body carried out the assessment. Paul confirms the marking route for each destination during the code review, so a company with plants in both Northern Ireland and Great Britain receives equipment documented for each.

What the Pressure Equipment (Safety) Regulations 2016 require of a US-built vessel

The Pressure Equipment (Safety) Regulations 2016 require a US-built vessel to be classified, assessed and documented exactly as a British-built one would be. The manufacturer classifies each vessel and piping run by fluid group, maximum allowable pressure and volume or nominal size, which places it in one of four hazard categories or below them under sound engineering practice. The category fixes the conformity assessment module, and from Category II upward the module brings an assessment body into design review, production quality or final inspection. For the UKCA route that body is a UK approved body; for the CE route it is an EU notified body, and the CE route lets one assessment serve plants in Britain and in the EU alike.

The regulations also set essential safety requirements for design, materials, welding, non-destructive testing, the final pressure test and the instructions. An ASME Section VIII design reaches Britain by meeting those requirements through the chosen module: weld procedures and welders qualified for the route, materials supported by the right certificates, and a final assessment that includes the hydrostatic test. Paul Industries plans all of this before material is ordered, so the conformity file grows with the vessel instead of being reconstructed after it is finished.

Pressure Systems Safety Regulations 2000 summary for equipment buyers

The Pressure Systems Safety Regulations 2000 (PSSR), SI 2000/128, apply to a pressure system, meaning one or more rigid pressure vessels with their pipework and protective devices, that contains or is liable to contain a relevant fluid. A relevant fluid is steam, or a gas, or a liquid whose vapour pressure exceeds 0.5 bar above atmospheric pressure. That definition captures almost every clean steam generator, autoclave, compressed air receiver, nitrogen buffer vessel and jacketed reactor a pharmaceutical or chemical plant runs.

The central duty is the written scheme of examination required by regulation 8. The scheme must be in place, and the first examination carried out, before the system is used, and it is drawn up or approved as suitable by a competent person. The user also has to establish safe operating limits for the system. The written scheme of examination for pressure vessels lists the parts to be examined, the nature of each examination and its interval, which depend on the equipment and its duty.

Paul Industries delivers everything the plant needs to meet those duties on day one: design pressures and temperatures, safe operating limits, relief device sizing and set points, material certificates, weld and NDT records, and the hydrostatic test certificate for every vessel. The equipment arrives ready for its first examination, with access openings, inspection nozzles and nameplate data arranged so the examination proceeds without dismantling more than the scheme requires.

UK law that applies to US-built process equipment
RequirementInstrumentWhat it asks of the equipment and its filePaul Industries’ delivery
Placing pressure equipment on the GB marketPressure Equipment (Safety) Regulations 2016Category, conformity module, UKCA or CE mark, declaration of conformity, English instructionsCategory schedule for every vessel and line, design dossier, marking and declaration documents
Operating a pressure systemPressure Systems Safety Regulations 2000Safe operating limits, protective devices, written scheme of examination before first useSafe operating limits schedule, relief calculations, inspection access, test records
MachinerySupply of Machinery (Safety) Regulations 2008Risk assessment, essential health and safety requirements, UKCA or CE markingRisk assessment, guarding and interlocks, technical file for the skid as a whole
Fixed electrical installationBS 7671:2018+A3:2024Protective devices, earthing and cable selection to the IET Wiring RegulationsPanels and field wiring designed to connect into a BS 7671 installation
Medicines manufactureHuman Medicines Regulations 2012, UK GMP, MHRA inspectionEquipment fit for the plant’s qualification and contamination control approachURS-based design, ASME BPE fabrication, IQ and OQ protocols, turnover package

Where are the pharmaceutical companies in the UK that buy process equipment?

The pharmaceutical companies in the UK that buy large process systems concentrate in a few regions: the North West around Macclesfield and Liverpool, the North East around County Durham, and Hertfordshire north of London. These sites are named here as market facts about the British industry, to show where process demand sits.

In Cheshire, AstraZeneca runs its Macclesfield manufacturing campus and has announced new production capacity there for a cancer medicine. In Speke, Liverpool, AstraZeneca’s plant continues to produce its nasal flu vaccine, and next to it stands the CSL Seqirus vaccine factory, described as the UK’s largest. In County Durham, GSK’s Barnard Castle site added an aseptic sterile facility of about 90 million pounds, and in Hertfordshire GSK’s Ware site makes respiratory inhalers. Each of these industries depends on purified water, clean steam, CIP and sterile utilities of the kind Paul builds.

UK process regions and the systems their plants run
RegionPlants named as market factsProcess focusEquipment Paul Industries supplies
Cheshire and MerseysideAstraZeneca Macclesfield; AstraZeneca and CSL Seqirus at SpekeOral and injectable medicines, influenza vaccinesWFI and clean steam, CIP and SIP, formulation and buffer vessels
North East EnglandGSK Barnard Castle aseptic facilitySterile manufacturingSanitary process piping, hold vessels, sterile utility skids
HertfordshireGSK WareRespiratory inhalersPurified water, process cooling, compressed air and nitrogen systems
Scotland and WalesDistilling, food and chemical plantsFermentation, distillation, food processingProcess tanks, CIP, glycol and chilled water, stainless piping
Northern IrelandPharmaceutical, dairy and food plants under EU product rulesDairy processing, generics, foodCE-marked skids and vessels, CIP, hygienic piping

Clean utilities for UK GMP: water, steam and CIP

Clean utilities are where UK GMP and UK pressure law meet most directly, because a clean steam generator or a hot WFI storage vessel is both a GMP-critical system and a pressure system under the PSSR. Paul Industries designs these utilities as single packages: a WFI or purified water generation skid, a jacketed storage vessel with its vent filter and spray ball, a distribution loop with sanitary heat exchangers and zero-dead-leg valves, and clean steam generation with sampling points for condensate testing. The product-contact surfaces are fabricated from ASME BPE components with orbital welds, borescope records and surface roughness readings, and the pressure-bearing parts carry the documents the plant’s written scheme and first examination will rely on. Clean steam systems and CIP return lines are sloped and drained to the standards an MHRA inspector checks during a walk-down.

Electrical supply, units and documents for British sites

British sites take a 50 Hz supply declared at 230 volts between phase and neutral under the Electricity Safety, Quality and Continuity Regulations 2002, with 400 volts between phases on three-phase systems. The declared tolerance band runs from 10 percent above to 6 percent below the nominal voltage, a legacy of the move from 240 volts to the harmonised 230 volt figure, so Paul Industries rates motors, heaters and control transformers for the whole band rather than the nominal value alone.

The fixed installation a skid plugs into follows BS 7671, the IET Wiring Regulations, currently BS 7671:2018 with Amendment 3 published in July 2024, and machine panels follow BS EN 60204-1. Drawings are metric with DN sizes and pressures in bar, although many British pharmaceutical sites already standardise on ASME BPE tube sizes, which Paul matches. Documents are in English throughout, including the declaration of conformity and the operating instructions.

What does shipping to the UK from the USA involve?

For a process skid, shipping to UK from USA ports means an ocean crossing from an East Coast port to Felixstowe, Southampton or Liverpool, followed by customs clearance and road haulage to the site. Published schedules put New York to Felixstowe at roughly 11 to 16 days port to port on direct services, with Southampton in the same range, and inland legs and clearance on top. Liverpool on the west coast shortens the road leg to plants in Cheshire, Merseyside and the North West.

Felixstowe suits standard boxes bound for the South East and the Midlands. Flat rack and out-of-gauge loads need a sailing whose carrier handles that equipment at the chosen port, which is why Paul fixes skid dimensions early and books the crossing to match.

Customs and VAT on equipment entering Great Britain

Since the United Kingdom left the EU customs union, goods from the United States are cleared on the Customs Declaration Service, and the importer needs a GB EORI number, since an EU-issued EORI is no substitute. Duty depends on the commodity code under the UK Global Tariff, and import VAT is charged at the standard 20 percent rate on the value of the goods plus shipping and duty. VAT-registered businesses use postponed VAT accounting to declare it on their VAT return instead of paying at the port.

Incoterms 2020 set where Paul’s delivery ends. British buyers commonly choose FCA at the US port with their own forwarder, DAP to the site in Macclesfield, Teesside or Hertfordshire with Paul carrying freight and risk, or DDP when they want customs entry and duty inside Paul’s price.

How does a UK project run with Paul Industries?

A UK project with Paul Industries runs in eight stages, and the regulatory decisions for Great Britain or Northern Ireland are taken in the first stage so that fabrication, testing and paperwork follow one plan. The table lists each stage, what is particular to a British destination, and what the plant receives.

A UK project with Paul Industries, stage by stage
StageWhat is particular to a UK plantDeliverables
1. Code and marking reviewPE(S)R 2016 categories, UKCA or CE route, Northern Ireland marking where relevant, PSSR data the plant will needRegulatory basis document and equipment category list
2. Design50 Hz equipment selection rated for the 230 V tolerance band, BS 7671 interfaces, metric drawingsP&IDs, layouts, calculations, electrical drawings for approval
3. FabricationWeld procedures and materials matched to the conformity route, traceable from mill to nameplateMaterial certificates, weld and NDT records, finish readings
4. Factory acceptance testFunction and pressure tests to the agreed protocol, witnessed by the plant in person or by video linkSigned FAT record and punch list close-out
5. Packing and transportISPM 15 crating, preservation, booking to Felixstowe, Southampton or LiverpoolShipping documents for the Customs Declaration Service
6. InstallationWork under the site’s permit system and the plant’s construction safety arrangements, by Paul or under Paul’s supervisionInstallation and tie-in records
7. CommissioningFlushing, start-up, site acceptance test, data handed over for the PSSR first examinationExecuted SAT, safe operating limits, test certificates
8. Qualification and handoverIQ and OQ to the site’s procedures under UK GMP, operator trainingExecuted protocols, as-builts, manuals, spares list

Installation of fixed process equipment and its services at a British plant is normally treated as construction work under the Construction (Design and Management) Regulations 2015, so Paul Industries prepares method statements, risk assessments and lifting plans for the plant’s construction phase plan before the first crate arrives, and works within the principal contractor arrangements the site has set. Lifts into existing buildings, crane access and the route from the delivery bay to the process room are surveyed during design, which is also when the skid’s split points are fixed if the equipment has to pass through a standard door.

The commissioning and qualification stage closes the project, and its protocols are drafted alongside the FAT protocol so nothing proven in the shop has to be proven twice.

Who builds process systems for plants in the United Kingdom?

Paul Industries builds process systems for plants in the United Kingdom, from a single dosing skid to complete water, CIP and process trains, and carries them through design, US fabrication, factory testing, shipment, installation and qualification at the British site. Among skid manufacturers UK buyers compare, Paul offers one contract for the equipment and the field work, so the company that designed and tested the system is the one that commissions it.

The difference for a British plant shows most at handover. A UK quality unit expects the conformity file, the PSSR data and the GMP qualification record to agree with each other, item by item, and Paul compiles all three from one master equipment list, so a vessel’s tag number, design pressure and material grade read the same in the declaration of conformity, the safe operating limits schedule and the IQ protocol. That consistency is what lets a plant move from mechanical completion to qualified operation without a documentation gap.

Most British enquiries come from pharmaceutical plants and vaccine and biotech sites, followed by distilling and brewing and food producers that need hygienic tanks, CIP and glycol cooling.

What drives the cost of a process equipment project in the UK?

The cost of a process equipment project in the UK is set by the equipment and by the delivery factors around it: conformity assessment and marking, freight and port, crating, duty and import VAT under the chosen Incoterm, and the installation route. Paul Industries prices each factor as a separate line so the plant’s commercial team can compare the offer with a domestic tender.

  • Conformity and marking. Higher categories under the Pressure Equipment Safety Regulations bring an approved or notified body into design and final assessment, and the marking route for Great Britain or Northern Ireland shapes that work.
  • Freight. Container-sized skids cost less to ship than flat rack loads, and the choice between Felixstowe, Southampton and Liverpool changes the road haul at the British end.
  • Crating and preservation. Heat-treated crates, desiccant, end caps and nitrogen blankets for sanitary systems scale with the equipment.
  • Duty and VAT. Under FCA or DAP the British importer pays duty and 20 percent import VAT; under DDP Paul includes them.
  • Installation route. Supervision uses fewer Paul field days; complete installation places start-up responsibility with the builder of the equipment.

Two British specifics also feature in the estimate: the extra marking work when the same equipment design is going to plants in both Great Britain and Northern Ireland, and the scheduling of site work around the plant’s shutdown calendar, which for many pharmaceutical sites falls in a short summer or year-end window.

A budget range follows a scope description, and a firm price follows drawings, the site location and the agreed Incoterm.

Paul Industries for UK process plants

Paul Industries takes process equipment projects across England, Scotland, Wales and Northern Ireland as part of its work for plants outside the United States, all run from its headquarters at 256 Shore Drive, Kilmarnock, Virginia. For a British plant Paul engineers the system, builds the skids, vessels, tanks and pipe spools in its US shop, tests them before they leave, ships them to the port that suits the site, and then installs and commissions them, start-up included, or supervises the installation. Each system is built and documented to UK law and the plant’s GMP standards. Companies with sites on both sides of the Irish Sea will find EU rules for the Republic on the Ireland page. Send the scope, the site location and your preferred Incoterm to request a quote.

Standards referenced: Pressure Equipment (Safety) Regulations 2016 (SI 2016/1105) · Pressure Systems Safety Regulations 2000 (SI 2000/128) · Supply of Machinery (Safety) Regulations 2008 · Construction (Design and Management) Regulations 2015 · Pressure Equipment Directive 2014/68/EU (Northern Ireland) · BS EN 13445 · ASME Boiler and Pressure Vessel Code Section VIII · ASME BPE · BS 7671:2018+A3:2024 (IET Wiring Regulations) · BS EN 60204-1 · Electricity Safety, Quality and Continuity Regulations 2002 · Human Medicines Regulations 2012 · EU GMP Annex 1 (as applied in UK GMP) · Incoterms 2020 · ISPM 15

Frequently asked questions

Is UKCA marking compulsory on a US-built pressure vessel for England?

UKCA marking is one of two accepted routes for a pressure vessel going to England, Scotland or Wales. The UK government has extended recognition of CE marking indefinitely for the Pressure Equipment Safety Regulations, so a vessel that meets the EU directive and carries the CE mark is also accepted. Paul Industries agrees the marking route with the plant at the code review and documents the vessel to match.

When is a written scheme of examination required?

A written scheme of examination is required under regulation 8 of the Pressure Systems Safety Regulations 2000 before a pressure system containing a relevant fluid is first used, and the first examination is carried out before use as well. Only very small systems fall outside that duty. Paul Industries delivers the design data, safe operating limits, relief settings and test records the scheme is built on, so the plant has it in place before start-up.

What is a written scheme of examination?

A written scheme of examination is the document the Pressure Systems Safety Regulations 2000 require for each pressure system, listing the parts to be examined, the kind of examination for each and the interval between examinations, and it is drawn up or approved as suitable by a competent person. For equipment from Paul Industries, the vessel drawings, material records, relief device data and hydrostatic test certificate give the scheme its technical basis.

How often should pressure systems be inspected in the UK?

The interval for examining a pressure system in the UK is the one set in its written scheme of examination, which reflects the equipment, its materials, its fluid and the way it is operated, rather than a single fixed period for every system. Paul Industries designs vessels for practical examination, with access openings and inspection points placed so the plant’s examinations proceed quickly and with minimal dismantling.

Does Paul Industries build equipment for vaccine plants in Liverpool?

Paul Industries builds WFI and clean steam systems, CIP and SIP units, buffer and formulation vessels and sanitary piping for vaccine and biologics plants in the Liverpool City Region, including the Speke cluster. Each system is designed for the plant’s contamination control approach under UK GMP, built to the Pressure Equipment Safety Regulations, and installed and qualified at the site or installed under Paul’s supervision.

Can a vessel for a plant in Northern Ireland carry the UKCA mark?

Pressure equipment for a plant in Northern Ireland follows EU product rules under the Windsor Framework, so it carries the CE mark, or CE together with UKNI where a UK body performed the conformity assessment. Paul Industries documents equipment for Belfast, Antrim or Craigavon sites on that basis, and documents equipment for the same company’s plants in Great Britain separately where the routes differ.

What are the UK pressure equipment rules for a skid with several vessels?

Each pressure vessel and piping run on a skid is categorised under the Pressure Equipment (Safety) Regulations 2016, and the skid as a whole is assessed as an assembly where the regulations require it. The machinery rules also apply when the skid has pumps, drives or automatic valves. Paul Industries prepares a category schedule for every component, a conformity file for the assembly and the machinery technical file together.

Which ports serve plants in Cheshire and the North West?

Plants in Cheshire, Merseyside and the wider North West are served well by the Port of Liverpool, which shortens the road haul compared with an east coast arrival. Felixstowe and Southampton remain options when sailing frequency or flat rack availability matters more. Paul Industries chooses the routing with the plant’s logistics team and books it under the agreed Incoterm.

How do Teesside chemical plants use US-built process equipment?

Chemical plants on Teesside and in the North East buy pressure vessels, reactors, process tanks, solvent and utility piping and dosing skids that must meet the Pressure Equipment Safety Regulations and, once installed, the plant’s PSSR duties. Paul Industries designs that equipment with the corrosion allowances, materials and relief arrangements the process needs, and delivers the data the plant’s examinations depend on.

What import charges apply when a British plant buys American-built equipment?

A UK plant importing equipment from the United States pays whatever duty the UK Global Tariff sets for the equipment’s commodity code, plus import VAT at 20 percent, unless the order is placed on DDP terms, in which case Paul Industries carries duty and clearance. VAT-registered importers use postponed VAT accounting through the Customs Declaration Service, which moves the VAT to their return.

What does BS 7671 mean for a skid control panel?

BS 7671, the IET Wiring Regulations, governs the fixed installation the skid connects to, so the panel’s incoming supply, protective devices, earthing and cable sizes have to suit a BS 7671 design. The panel itself follows BS EN 60204-1. Paul Industries designs British panels for 230/400 V, 50 Hz supply, with IEC wiring colours and metric conductor sizes, and tests them before shipment.

Can Paul Industries supply distilleries in Scotland?

Paul Industries supplies Scottish distilleries with stainless process tanks, CIP systems, process and utility piping, glycol and chilled water systems and pump skids, built to UK pressure and machinery law and to hygienic practice. Equipment for Speyside, Islay or the Central Belt ships through a British port of the plant’s choosing, and Paul installs and commissions it on site or supervises the installation.

How does the MHRA view equipment built outside the UK?

The MHRA inspects the manufacturing site against UK GMP rather than the origin of each piece of equipment, so what matters is that the equipment is designed, built, qualified and documented to support the plant’s GMP system. Paul Industries supplies the URS traceability, material and weld records, surface finish data and executed IQ and OQ that an MHRA inspection of the plant draws on.

What does a sterile manufacturing site in County Durham need from a skid supplier?

A sterile manufacturing site in County Durham needs skids and utilities that fit an aseptic contamination control strategy: drainable, cleanable and sterilisable product-contact parts, closed transfers, and complete documentation for qualification. Paul Industries fabricates those systems to ASME BPE practice, builds them to UK pressure and machinery law, and executes IQ and OQ at the plant.

How long is the sea leg from the US East Coast to Felixstowe?

The sea leg from the US East Coast to Felixstowe is roughly 11 to 16 days port to port on direct services, with customs clearance and haulage to the site added on arrival. Flat rack bookings and transshipment routings take longer. Paul Industries plans the FAT date, crating and sailing together so the equipment reaches the British site in line with the installation schedule.

What does the Pressure Systems Safety Regulations 2000 (PSSR) mean for a new skid?

The Pressure Systems Safety Regulations 2000 (PSSR) mean that a new skid containing steam, compressed gas or another relevant fluid needs safe operating limits, suitable protective devices and a written scheme of examination before it is first used. Paul Industries designs the skid with those duties in mind, labels relief devices and set pressures clearly, and delivers the data the plant needs to put the scheme in place before start-up.

Does Paul Industries hand over the data a PSSR competent person asks for?

Paul Industries hands over every item a PSSR examination draws on: design codes and pressures, safe operating limits, relief valve sizing and set pressures, material certificates, weld maps and NDT reports, hydrostatic test certificates and nameplate details. The data arrives in one indexed turnover package, so the plant’s scheme of examination and first examination proceed on schedule.

What should a UK plant send for a quote?

A UK plant receives the most precise quote by sending its URS or a scope note, P&IDs where available, the site town and nearest port, utility data such as steam pressure and supply voltage, the preferred Incoterm and the installation route it wants. Paul Industries responds with a budget range and then a firm price that shows conformity work, freight, crating and installation as separate lines.

Planning process equipment for a UK plant?

Send your scope, the site location in England, Scotland, Wales or Northern Ireland, and your preferred Incoterm, and Paul Industries will return the marking route, delivery plan and price. Call 201-450-8280 or request a quote.