Paul Industries provides tank fabrication in New York, designing, building and installing petroleum, chemical, water and stainless process tanks for plants, hospitals, campuses and data centers, built to the NYSDEC bulk storage rules wherever they apply. New York regulates stored petroleum under 6 NYCRR Part 613 and listed hazardous substances under the Chemical Bulk Storage program, and in the five boroughs fuel oil tanks also answer to the city’s Mechanical Code and Fire Department. Paul Industries builds each one so its design standard, containment, gauging and records fit the program it falls under.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
PBS facility Over 1,100 gallons combined, or an underground tank over 110 gallons
Before installing Notify NYSDEC at least 30 days ahead (Part 613)
Containment Required on aboveground tanks of 10,000 gallons or more
Chemical tanks Registered from 185 gallons aboveground; renewed every two years
Reviewed November 2026

Tank fabrication in New York: which program covers your tank?

A tank in New York falls under one of three regulatory tracks, or none: Petroleum Bulk Storage for oil and fuel at qualifying facilities, Chemical Bulk Storage for substances on the state’s hazardous substance list, and, inside New York City, the fuel oil provisions of the city’s Mechanical Code and Fire Code. Water, food product and most process tanks sit outside the bulk storage programs and are built to the owner’s specification and the relevant industry standard instead. Deciding which track applies comes first, because it fixes the construction standard, the containment and the paperwork before a drawing is made.

Which New York program applies to a new tank
ProgramWhat it coversRegistrationMain tank requirements
Petroleum Bulk Storage (6 NYCRR Part 613)Facilities with more than 1,100 gallons of petroleum storage in total, or an underground tank over 110 gallonsNYSDEC or a delegated county; renewed every five yearsListed construction standard, coating, containment, gauging, 30-day inspections
Chemical Bulk Storage (6 NYCRR Parts 596-599)Tanks holding substances on the Part 597 list or mixtures containing themAll underground tanks and aboveground stationary tanks of 185 gallons or more; renewed every two yearsCompatible materials, containment and the handling and storage rules
NYC fuel oil rulesFuel oil storage and piping in the five boroughsFDNY permit for fuel oil storage; notice for new or modified tanksMechanical Code Chapter 13 construction, venting, piping and testing
Owner’s specificationWater, food product, process and pharmaceutical tanksNone under the bulk storage programsIndustry standards such as API 650, 3-A Sanitary Standards or ASME BPE

What is petroleum bulk storage under New York law?

Petroleum bulk storage in New York is the storage of petroleum at a facility whose tank systems hold more than 1,100 gallons combined, or that has an underground tank larger than 110 gallons, and it is governed by Environmental Conservation Law Article 17, Title 10 and the New York State petroleum bulk storage regulations in 6 NYCRR Part 613, in effect since October 11, 2015. The 6 NYCRR Part 613 petroleum bulk storage rules split tank systems into Subpart 2 underground tanks, Subpart 3 special-case underground tanks such as heating oil tanks for use on the premises, and Subpart 4 aboveground tanks, which may also fall under the federal spill prevention rule in 40 CFR 112.

New York petroleum bulk storage facilities register through the NYS DEC petroleum bulk storage program, or with Nassau, Suffolk, Westchester or Cortland County, which run delegated programs and may add stricter requirements. A NYS petroleum bulk storage registration expires every five years, the fee scales with total capacity from nothing at 1,100 gallons or less to $500 for 5,000 to under 400,000 gallons, and the current certificate is displayed at the facility. A facility’s registration record, tank by tank, appears in the NYSDEC petroleum bulk storage database, which is why the tank Paul Industries installs is labeled and documented to match the registration form exactly.

New York above ground storage tank regulations for a new tank

New York above ground storage tank regulations require every new petroleum tank of 60 gallons or more at a PBS facility to be built of steel to one of the listed standards: UL 142, UL 80, UL 2258, API Standard 620, API Standard 650 or ULC-S601. Tanks installed after October 11, 2015 are Category 3 tanks under Part 613, and they must also carry a corrosion-resistant surface coating, be protected from corrosion to API 651 where they touch the ground, and have a gauge that shows the liquid level, or a high-level alarm or pump cut-off in its place. The facility notifies NYSDEC at least 30 days before a tank is installed.

Storage tank containment requirements in the New York State above ground storage tank regulations depend on size and setting. Any aboveground tank of 10,000 gallons or more needs secondary containment able to hold a leak until it is found and removed. A smaller tank within 500 feet of a stream, well, principal aquifer, wetland, lake or storm drain needs either the same containment or a design that keeps a release from occurring, such as a double-walled tank. An impermeable barrier under a tank in contact with the ground must have a permeability of 1 x 10-6 cm per second or less and allow monitoring between the tank bottom and the barrier, and dikes are sized to NFPA 30.

Part 613 requirements for a new aboveground petroleum tank (Category 3)
RequirementWhat Part 613 asks forHow Paul Industries builds it
Construction standardSteel tank to UL 142, UL 80, UL 2258, API 620, API 650 or ULC-S601Standard chosen from capacity, shape and site: UL listed for shop tanks, API 650 for large field-built tanks
CoatingSurface coating that prevents corrosion and deteriorationCoating system matched to service and exposure, with inspection records
Ground contactCorrosion protection to API 651Cathodic protection designed with the foundation, or the tank raised off the ground
Secondary containmentRequired at 10,000 gallons or more, or near sensitive receptorsDouble-wall tank, concrete dike or lined containment sized to NFPA 30
Barrier and monitoringPermeability 1 x 10-6 cm/sec or less; monitorable between bottom and barrierLiner or double bottom with leak detection ports
Level gaugingAccessible level gauge, or high-level alarm or cut-offGauge and high-level alarm fitted and wired before fill
Advance noticeNYSDEC notified at least 30 days before installationTank data supplied for the owner’s notice and registration

Chemical bulk storage tanks and the NYS chemical bulk storage regulations

Chemical bulk storage tanks in New York are tanks that hold a substance on the state’s hazardous substance list in 6 NYCRR Part 597, or a mixture containing one, and they are regulated under the Chemical Bulk Storage program in 6 NYCRR Parts 596 to 599. Every underground tank of a listed substance and every aboveground stationary tank of 185 gallons or more is registered with NYSDEC, and the CBS registration is renewed every two years until the owner reports the facility closed. Acids, caustics, solvents and treatment chemicals at semiconductor, pharmaceutical, water treatment and manufacturing sites commonly fall here.

The NYS chemical bulk storage regulations set standards for new tank systems, handling and storage practices, inspections and release response, so a chemical tank is designed with its contents in mind from the first calculation: material and lining compatibility, venting and scrubbing, secondary containment sized for the tank, and transfer connections that limit spills. Paul Industries fabricates carbon steel, stainless steel and alloy chemical tanks to those chemical bulk storage tank regulations and supplies the data the owner needs for the NYSDEC chemical bulk storage registration. Growth in semiconductor manufacturing, with Micron breaking ground in Clay in January 2026, is adding chemical storage demand across Central New York.

New York underground storage tank regulations and the move aboveground

New York underground storage tank regulations cover any facility with an underground petroleum tank larger than 110 gallons, and most underground tanks fall under both Part 613 Subpart 2 and the federal underground tank rules in 40 CFR 280. Heating oil tanks used on the premises and field-constructed underground tanks are handled under Subpart 3. Many owners replacing an aging buried tank choose an aboveground tank instead, because it can be inspected from the outside, its containment is visible, and a tank in a vault or basement that is accessible for visual inspection is treated as an aboveground tank.

Paul Industries removes the old system as part of the replacement where the owner asks, and builds the new aboveground tank, containment and piping to the Part 613 standards so the closure and the new registration are filed together.

How often should storage tanks be inspected in New York?

Storage tanks at New York PBS facilities get a documented walkthrough inspection every 30 days, covering the tank, accessible piping, leak detection, secondary containment, cathodic protection and overfill equipment, with records kept for three years. Older Category 1 aboveground tanks of 5,000 gallons or more, or with a manway, also get an internal inspection every ten years, to API Standard 653 for field-constructed tanks or STI SP001 for shop-fabricated tanks. After a tank repair, a tightness test is performed within 30 days unless the tank has been internally inspected to one of those standards, and a copy of the result goes to NYSDEC within 30 days of the test.

Recurring inspections and records for New York aboveground petroleum tanks
ActivityFrequency or triggerRecord kept
Walkthrough inspectionEvery 30 daysChecklist kept 3 years
Internal inspection (older tanks of 5,000 gallons or more, or with a manway)Every 10 years to API 653 or STI SP001Report kept 20 years or until the next inspection, whichever is later
Tightness test after a tank repairWithin 30 days of the repair, unless internally inspectedResults kept, and a copy sent to NYSDEC within 30 days
Cathodic protection test after repairWithin 6 monthsTest record kept until the system is closed
Permanent closureNYSDEC notified at least 30 days beforeClosure report within 30 days after closure

Fuel oil and generator tanks in New York City buildings

Fuel oil tanks in New York City buildings are designed, installed and repaired under Chapter 13 of the city’s Mechanical Code, stored under an FDNY permit, and, where the building’s tanks total more than 1,100 gallons, registered under Part 613 as well. A single heating oil tank under 1,100 gallons used on the premises and not connected to other tanks is excluded from the PBS facility definition, unless the property already has other tanks that qualify. Hospitals, data centers and towers with emergency generators usually exceed that threshold once the main storage tank and day tanks are counted together.

Bulk fuel storage regulations in the city also interact with the boiler fuel rules: the city’s LL32 of 2023 bars boilers from burning No. 4 oil from July 1, 2027, so buildings converting to No. 2 oil or gas often reuse, reline or retire tanks at the same time. Paul Industries fabricates and installs fuel oil storage and day tanks, sets them in basements, vaults and on roofs, and connects them to the generator and boiler fuel systems, coordinating with data center mechanical contracting in New York where the tanks feed critical power. Tank fabrication in NYC rarely has room to spare, so tanks are often built in sections that fit the building’s access route.

Stainless dairy and process tanks for Upstate plants

Stainless dairy and process tanks make up much of New York’s non-regulated tank work, because the state is a major milk producer, with 642,000 milking cows and more than 16.5 billion pounds of milk in 2025. Chobani broke ground in Rome in April 2025 on a $1.2 billion plant designed to process about 12 million pounds of milk a day, and processors in the Finger Lakes, Central New York and Western New York run silos, raw milk receivers, cultured product tanks and CIP tanks every day. Dairy tank fabrication follows the 3-A Sanitary Standards and the processor’s own specification for finish, drainability and cleaning coverage.

A stainless steel tank New York food and pharmaceutical plants specify typically calls for 304 or 316L stainless, polished product-contact surfaces, sloped bottoms, sanitary nozzles, spray devices and, for cultured and cooked products, jackets for heating or cooling. Paul Industries fabricates and installs those tanks, passivates them through passivation services in New York, and ties them into the plant’s cleaning circuits through CIP and SIP systems in New York. Tanks that hold pressure as well as product are built as code vessels under pressure vessel fabrication in New York.

Choosing material and lining by what the tank holds

Material and lining for a New York tank are chosen from the contents, their temperature and concentration, and the cleanliness the product needs, and the choice also has to satisfy the construction standard the regulatory track requires. Steel is mandatory for regulated petroleum storage of 60 gallons or more, while chemical and process service opens the choice to stainless grades, linings and alloys. Paul Industries confirms compatibility with the owner’s process data before ordering plate, and records the material certificates in the turnover file so the next inspector can see what the shell is made of.

Common material choices for New York tank service
ContentsCommon constructionPoints to settle in design
Diesel, No. 2 oil and generator fuelCarbon steel, single or double wall, to UL 142, UL 2258 or API 650Containment, overfill alarm, interstitial monitoring, venting
Concentrated sulfuric acidCarbon steel with a corrosion allowanceMoisture control at the vent, inlet velocity, inspection of the vapor space
Sodium hydroxide (caustic)Carbon steel or stainless, depending on temperature and purityHeat tracing against freezing, stress corrosion limits at high temperature
Hydrochloric acid and hypochloriteRubber-lined or other lined carbon steelLining inspection access, fume scrubbing
Milk, juice and cultured product304 or 316L stainless to 3-A Sanitary StandardsFinish, drainability, spray coverage, jacket design
Purified water and ultrapure water316L stainless, polished or electropolishedSanitary vent filter, spray device, passivation records

Snow, wind and foundations for New York tanks

Snow, wind and foundation loads set much of a New York tank’s structure, because a roof that carries the Tug Hill or Buffalo snowpack and a tall shell exposed to coastal wind on Long Island are designed for very different forces. API 650 and the building codes require the roof, shell stiffening and anchorage to resist the site’s design loads, and an empty tank is the critical case for wind uplift and overturning. Paul Industries designs the anchorage and foundation with the tank, specifies the ring wall or slab, and plans the bottom so the leak monitoring that Part 613 requires can be read between the floor and the barrier.

Frost depth matters for every outdoor foundation in Upstate New York, and soft ground along the Hudson, the Erie Canal corridor and coastal Long Island often calls for a soil investigation before the foundation is fixed. Paul Industries sizes the foundation from that data and sets the tank so settlement stays inside the tolerances of the tank standard.

Delivered whole or built in place: choosing for a New York site

A New York tank is delivered whole when its diameter and length fit the road and the site, and built in place when they do not. Shop-built tanks to UL 142 or UL 2258 arrive listed and tested, which shortens installation and simplifies the Part 613 paperwork. Large API 650 storage tanks for terminals, utilities and plants are erected on a prepared foundation, with the shell, roof and bottom welded and examined on site and the tank hydrostatically tested before it is put into service. Winter erection Upstate adds weather protection and preheat planning for the welding, and urban sites add crane and street-closure planning. Paul Industries performs both routes and pairs field erection with industrial welding in New York and process piping in New York for the connections.

Repairs, closures and replacements of regulated New York tanks

Repairs to a regulated New York petroleum tank are documented when made, followed by a tightness test within 30 days unless the tank has been internally inspected, and the test result is copied to NYSDEC. A NYSDEC tank closure begins with notice to the Department at least 30 days before the tank is permanently closed and ends with a closure report within 30 days afterward, kept for at least three years. Paul Industries repairs shells, bottoms, nozzles and roofs, replaces tanks that are past economical repair, and performs closures and removals so the owner’s registration stays accurate.

Planning matters as much as the welding. A plant with one fuel or chemical supply arranges temporary storage before its only vessel is emptied, cleaned and opened, and a terminal schedules bottom work for the season when throughput allows a unit to stand idle. Paul Industries sets out the sequence before work starts: draining and cleaning, gas-freeing and entry, inspection, repair, testing, coating and return to service, with each step recorded so the result matches what the owner reports to NYSDEC or the delegated county. Where an inspection shows widespread thinning, the comparison between a new floor and a complete replacement is made with real thickness data rather than an estimate.

What drives the cost of tank fabrication in New York?

The cost of tank fabrication in New York is driven by capacity, material, the design standard, whether the tank is built in the shop or in the field, the containment and monitoring Part 613 or the CBS program requires, internal finish for food or pharmaceutical service, and the access at the site. A double-walled UL 2258 generator tank, a 316L jacketed cultured product tank and a field-erected API 650 storage tank are priced on entirely different bases. Paul Industries prepares a budget range from capacity, contents, location and access, then a firm price once the drawings and containment are agreed.

Who fabricates tanks in New York, from Long Island to Buffalo?

Paul Industries fabricates tanks in New York and installs them, building petroleum, chemical, water, dairy and process tanks for owners from Montauk to Niagara Falls: the five boroughs and Long Island, Westchester and the Hudson Valley, Albany and the Capital Region, Utica and Rome, Syracuse, Rochester and the Finger Lakes, Buffalo, Binghamton and the Southern Tier, and the North Country. Its headquarters sit at 256 Shore Drive, Kilmarnock, Virginia. The company was formerly based in northern New Jersey and then Pennsylvania, and today it takes tank work throughout New York, across all 50 states and at international plants. Paul Industries offers supply-only, design-build and complete installation routes, and the New York page lists everything else it delivers in the state.

The same tank work runs in the headquarters state through tank fabrication in Virginia, and in neighboring states through tank fabrication in New Jersey and tank fabrication in Pennsylvania. The national guide to tank types, materials and standards is on the tank fabrication service page. Among tank manufacturers New York owners compare, Paul Industries carries each tank from design to a registration-ready installation under one contract.

Tank work from Paul Industries across New York

For tank fabrication, New York owners can rely on Paul Industries to design, fabricate, coat, line, deliver, erect, set, pipe, test and document storage and process tanks, and to repair, close and replace tanks already in service. Send the capacity, contents, location and any containment or registration details, and request a quote.

Standards referenced: 6 NYCRR Part 613 (Petroleum Bulk Storage) · 6 NYCRR Parts 596-599 (Chemical Bulk Storage) · API Standard 650 · API Standard 620 · API Standard 651 · API Standard 653 · STI SP001 · UL 142 · UL 2258 · NFPA 30 · 40 CFR 112 (SPCC) · New York City Mechanical Code Chapter 13 · 3-A Sanitary Standards

Frequently asked questions

Who handles tank fabrication for plants in Buffalo and Rochester?

Paul Industries provides tank fabrication Buffalo, NY food, chemical and materials plants schedule, and tank fabrication Rochester, NY manufacturers and campuses need. Western New York tanks are designed for heavy snow and wind loads and cold-weather service, with heat tracing and insulation where the contents can freeze. Each regulated tank is built and documented for its NYSDEC registration.

Who builds fuel and process tanks for New York City and Long Island sites?

Paul Industries handles tank fabrication NYC hospitals, data centers and towers need for fuel oil and generator storage, and tank fabrication Long Island plants and campuses schedule. Long Island sites in Nassau and Suffolk register petroleum tanks with their county’s delegated program, so Paul Industries prepares the tank data in the form the county asks for.

Who builds dairy and food tanks in the Mohawk Valley and Central New York?

Paul Industries builds silos, raw milk receivers, cultured product tanks, blending tanks and CIP tanks for dairy and food plants across the Mohawk Valley, Central New York and the Finger Lakes. Dairy tank fabrication follows the 3-A Sanitary Standards and the processor’s finish, drainability and cleaning coverage specification, with passivation before the tank enters service.

Who supplies process and storage tanks in Albany and the Capital Region?

Paul Industries handles tank fabrication Albany, NY plants, campuses and utilities need, along with work in Rensselaer, Schenectady, Saratoga County and the rest of the Capital Region. Biologics, semiconductor and water treatment sites there use stainless process tanks and chemical storage tanks, which Paul Industries builds to the owner’s specification and the Chemical Bulk Storage rules.

Is there a NYSDEC tank registration for a single new aboveground tank?

A NYSDEC tank registration is required when a single aboveground petroleum tank, or the site’s tanks together, hold more than 1,100 gallons, and for chemical tanks from 185 gallons. The facility notifies NYSDEC at least 30 days before installing a petroleum tank. Paul Industries supplies the tank data, standard and capacity for the owner’s filing.

What does the NYSDEC petroleum bulk storage database show?

The NYSDEC petroleum bulk storage database shows each registered facility, its registration status and the tanks on file, including capacity, product and installation details. Buyers, lenders and inspectors use it to check that a site’s tanks match its registration. Paul Industries labels and documents new tanks so the registration can be updated accurately.

What are the storage tank containment requirements for a tank under 10,000 gallons in New York?

A petroleum tank under 10,000 gallons needs secondary containment, or a design that keeps a release from occurring, when it sits within 500 feet of a stream, well, principal aquifer, wetland, lake or pond, or storm drain. Double-walled tanks meet the design option in many settings. Paul Industries checks the site against those receptors before choosing the tank type.

Do Nassau, Suffolk and Westchester counties run their own tank programs?

Nassau, Suffolk, Westchester and Cortland counties administer delegated Petroleum Bulk Storage programs on behalf of NYSDEC, and they may set requirements stricter than the state’s. Owners in those counties register and report through the county. Paul Industries designs tanks for Long Island and Westchester sites to the county’s rules as well as Part 613.

What must happen before a regulated tank is permanently closed in New York?

Before a regulated petroleum tank is permanently closed, the facility notifies NYSDEC at least 30 days in advance, then empties, cleans and closes or removes the tank, and files a closure report within 30 days afterward. The report is kept for at least three years. Paul Industries performs the cleaning, removal and replacement in one sequence.

How do bulk fuel storage regulations treat emergency generator tanks at New York hospitals and data centers?

Generator fuel tanks count toward a site’s petroleum capacity, so a main tank and its day tanks together usually exceed 1,100 gallons and bring the site under Part 613 registration. In New York City, the tanks also follow Mechanical Code Chapter 13 and FDNY permit rules. Paul Industries builds and installs the tanks, containment, gauging and fuel piping as one system.

Does a heating oil tank in a New York City building fall under Part 613?

A single heating oil tank under 1,100 gallons used on the premises and not connected to other tanks is excluded from the PBS facility definition, unless the property has other tanks that qualify. Larger or interconnected systems are registered. Either way, the tank in New York City follows the city’s Mechanical Code and FDNY rules for fuel oil storage.

How long does a NYSDEC chemical bulk storage registration last?

A NYSDEC chemical bulk storage registration is renewed every two years until the owner notifies the Department in writing that the facility has closed. It covers every underground tank of a listed substance and every aboveground stationary tank of 185 gallons or more. Paul Industries provides the tank details the renewal and any new registration require.

Which standards can a new petroleum bulk storage tank be built to?

A new petroleum bulk storage tank of 60 gallons or more installed in New York since October 11, 2015 is built of steel to UL 142, UL 80, UL 2258, API Standard 620, API Standard 650 or ULC-S601. Paul Industries chooses among them by capacity, shape and site, using UL listed tanks for shop-built units and API 650 for large field-erected tanks.

What happens after a repair on a regulated New York tank?

After a repair on a regulated New York petroleum tank, the repair is documented and the tank is tightness tested within 30 days, unless it has been internally inspected to API 653 or STI SP001; a copy of the test goes to NYSDEC within 30 days. Cathodically protected tanks are retested within six months. Paul Industries performs the repair and arranges the follow-up tests and records.

When does a stainless process tank become a regulated chemical tank in New York?

A stainless process tank becomes a regulated chemical tank when it stores a substance on the Part 597 hazardous substance list, or a mixture containing one, and it is aboveground and stationary with a capacity of 185 gallons or more, or underground. Product and water tanks stay outside the program. Paul Industries confirms the contents and registration status during design.

What must New York petroleum bulk storage facilities keep on display?

Petroleum bulk storage facilities in New York display their current registration certificate in a conspicuous place at the facility at all times. They also keep 30-day walkthrough inspection records, tank and piping repair records, and test results available for NYSDEC inspectors. Paul Industries hands over tank documentation organized for that file.

Which storage tank requirements shape an installation inside a New York building?

The storage tank requirements that shape an indoor installation are access for delivery, floor loading, venting to the outdoors, fill and overfill protection, containment, and, in New York City, the Mechanical Code Chapter 13 rules for tanks above the lowest floor. Paul Industries plans the tank around the building, often building it in sections that pass through existing openings.

What should a New York tank inquiry include?

A New York tank inquiry should include capacity, contents and temperature, the site and county, indoor or outdoor setting, any existing tank being replaced, containment and registration status, and the finish needed for food or pharmaceutical service. Paul Industries uses those details to prepare a budget range, then a firm price once drawings are agreed.

Replacing or adding a tank at a New York site?

Send the capacity, contents, county, indoor or outdoor setting and any current registration details. Call 201-450-8280 or request a quote.