Paul Industries designs, fabricates and installs process piping in Georgia for battery and solar plants, kaolin and chemical producers, paper mills, food processors and biologics campuses, from metro Atlanta and the Highway 316 corridor to Savannah, Augusta, Macon and Dalton. The state’s new manufacturing, from cell plants in Bryan and Jackson counties to solar cell lines in Bartow County, sits beside older mineral, paper and chemical operations, and each brings its own fluids, codes and permits. Paul Industries supplies fabricated spools, builds complete systems design-build, and installs, tests and turns over the lines at operating plants.
Request a quote or call 201-450-8280
What does process piping in Georgia carry today?
Process piping in Georgia carries solvents and coolants in battery cell plants, etching chemistry and deionized water in solar cell lines, mineral slurries in the kaolin belt, pulping liquors and steam in paper mills, brines and ammonia in food plants, and purified water and clean utilities on biologics campuses. Few states mix that range inside a few hours of highway, and the mix decides what a piping job needs: the material, the code the line is built to, the agency that reviews it and the kind of shutdown the plant can give.
The national approach to code selection, materials and spool fabrication is laid out on the process piping service page, and the Georgia market as a whole on the Georgia page. This page goes plant type by plant type through what is particular to Georgia piping work in 2026: the new cell and solar plants, the fall line mineral belt, the coast, and the code and permit path that applies when a line is added or changed.
For a plant engineer asking what is industrial process piping, as against building services, the short answer is that it moves the material the plant makes or the utilities that make it possible, at the pressures, temperatures and chemistries the process sets, and it is designed and tested to ASME B31.3 or, for steam and boiler service, ASME B31.1.
Battery and solar plants: the newest Georgia piping work
Georgia’s battery and solar plants are the newest large source of process piping work in the state, with Hyundai Motor Group Metaplant America and its HL-GA battery joint venture with LG Energy Solution at Ellabell in Bryan County, SK Battery America’s two plants in Commerce in Jackson County, and Qcells module production in Dalton with ingot, wafer and cell production in Cartersville that began in June 2026. These are market facts about where the work is, and the piping needs of a cell plant follow from its process rather than from any one owner.
Cell plant utilities and solvent lines
A lithium-ion cell plant coats electrodes from a slurry, and in the wet route the cathode slurry uses N-methyl-2-pyrrolidone (NMP) as its solvent. NMP leaves the coating ovens as vapor and is recovered by condensing it out of the exhaust, so the plant carries solvent supply lines, recovered-solvent return lines, condensate and cooling water to the recovery units, and the vent and drain piping around them. Those lines are B31.3 fluid service with a combustible organic liquid, and they are routed, supported and tested accordingly, with stainless steel the usual material because solvent purity drives cell quality.
Cell assembly happens in dry rooms, and a dry room specification commonly calls for a dew point around minus 40 degrees Celsius. Desiccant dehumidifiers serving those rooms need chilled water, hot water or steam for regeneration, and compressed air and nitrogen at very low moisture levels. Every joint on a dry-air or nitrogen header is a leak path for moisture, so orbital welded tube, helium leak testing where the owner specifies it, and dew point checks at the point of use are part of commissioning the piping, not an afterthought.
Solar cell lines in Bartow and Whitfield counties
Solar cell manufacturing uses wet chemical benches for texturing and cleaning, deionized water, process exhaust and scrubbed wastewater, and module assembly uses compressed air, vacuum and cooling water. Acid and caustic distribution in those plants is frequently thermoplastic or lined pipe, often double contained under walkways and where it crosses over equipment, and the drain and waste lines are segregated by chemistry so incompatible streams never meet in a sump. Paul Industries designs that segregation into the routing, fabricates the stainless and the thermoplastic spools off site, and installs them around running lines.
| Plant type and area | Typical process lines | Common materials | What shapes the job |
|---|---|---|---|
| Battery cell plants, Bryan and Jackson counties | NMP supply and recovery, chilled and process cooling water, dry compressed air, nitrogen | 304L and 316L stainless, orbital welded tube for dry gases | Solvent fluid service, moisture-tight joints, EPD air permit conditions on recovery |
| Solar cell and module plants, Dalton and Cartersville | Acids, caustic, deionized water, process exhaust, segregated wastewater | PVDF, polypropylene, lined steel, stainless for water | Chemical compatibility, double containment, drain segregation |
| Kaolin plants, Augusta to Macon and Columbus | Clay slurry, dispersant and bleach chemicals, process water, steam to dryers | Carbon steel with wear allowance, rubber-lined steel, HDPE | Abrasion at bends, settling velocity, flushing |
| Pulp and paper mills, coast and interior | Pulping and bleaching liquors, stock, steam and condensate, chemical feed | Duplex and austenitic stainless, carbon steel, FRP | Corrosive liquors, outage-timed tie-ins, B31.1 at the boilers |
| Food and poultry plants, Gainesville and statewide | Ammonia, brine, glycol, chilled water, hot water, CIP supply and return | Carbon steel for ammonia, 304 and 316 stainless | PSM for ammonia, washdown, sanitation windows |
| Biologics campuses, Highway 316 corridor | Purified water, WFI, clean steam, process gases, utility headers | 316L stainless to ASME BPE, orbital welds | Weld documentation, passivation, qualification |
Process piping, Savannah, Brunswick and the coastal plants
Process piping in Savannah and along the Georgia coast serves chemical plants, food and ingredient processors, distribution and packaging operations tied to the Port of Savannah, and the remaining paper and pulp operations of the coastal plain. The Georgia Ports Authority describes its Garden City Terminal as the largest single-terminal container facility of its kind in North America, and that traffic has pulled manufacturing and value-added processing into Chatham, Effingham and Bryan counties, including the Metaplant at Ellabell.
Coastal plants share three piping concerns. Salt air attacks carbon steel pipe and bolting outdoors, so pipe racks near the water get coating systems chosen for marine exposure, stainless or coated fasteners and careful detailing where insulation jacketing can trap water against the pipe. Hurricane season, from June through November, shapes when outdoor tie-ins are scheduled and how temporary supports and open spools are secured. And low, wet ground means buried lines and their cathodic protection need more attention than on the Piedmont.
The coast also changed in 2025, when International Paper closed its Savannah and Riceboro mills at the end of September. Paper and pulp remain a large part of Georgia’s forest-products output, and mills that keep running are investing in reliability of their liquor, stock and steam systems, which is where carefully timed replacement piping and outage tie-ins come in.
The fall line: kaolin slurry piping from Augusta to Macon and Columbus
Georgia’s kaolin deposits run in a band along the fall line from Augusta through Macon to Columbus, and the state mined 93 percent of US kaolin tonnage in 2012, according to the US Geological Survey. Sandersville, in Washington County, calls itself the kaolin capital of the world. Paper coating is the most common use of the clay, followed by fillers for plastics, rubber and paint, ceramics and pharmaceutical ingredients.
Wet-processed kaolin moves through a plant as a water slurry, and slurry piping fails in a different way from clean-service pipe. The two limits are settling and wear: run the slurry too slowly and solids drop out and plug the line, run it too fast and the bends and reducers erode through. A slurry line is therefore sized for a velocity window, laid out with long-radius bends, wear-back or replaceable elbows at changes of direction, and flushing connections so a line can be cleared after a trip rather than set up solid. Rubber-lined steel and HDPE are common in abrasive service, with carbon steel given a wear allowance where pressure or temperature rule out plastics.
Dryers and calciners at kaolin plants need steam, condensate return and gas piping, and the chemical additions in processing, such as dispersants and bleaching agents, need their own feed systems. Paul Industries builds slurry lines, steam and condensate systems and chemical feed piping as one scope, so the line that carries clay and the utilities that support it share one set of drawings, one test plan and one turnover package.
| Design choice | Option | Where it fits | What to watch |
|---|---|---|---|
| Pipe material | Rubber-lined carbon steel | Abrasive slurries at moderate temperature | Lining temperature limit, flange face protection |
| Pipe material | HDPE | Low-pressure slurry transfer and process water | Thermal expansion, support spacing, fusion procedure records |
| Pipe material | Carbon steel with wear allowance | Higher pressure or temperature lines | Thickness surveys at bends, planned replacement intervals |
| Bends | Long-radius or wear-back elbows | Every change of direction in slurry service | Access for change-out without cutting straight runs |
| Velocity | Sized inside a settling and wear window | All slurry lines | Pump turndown at low production rates |
| Flushing | Water flush and drain points | Lines that stop with solids inside | Flush water source, interlocks on shutdown |
Process piping: Atlanta, Gainesville and the Highway 316 corridor
Metro Atlanta and the corridors running out of it, Highway 316 toward Athens and Interstate 985 toward Gainesville, hold Georgia’s food and beverage plants, ingredient and packaging producers, and its growing life sciences base, including the $2 billion UCB biologics plant announced in March 2026 for the Rowen district in Gwinnett County. Piping on those sites ranges from carbon steel utility headers to ASME BPE stainless product lines.
In Gainesville and Hall County, and across the state’s poultry plants, refrigeration and sanitation piping lead the work; the hygienic layout of overhead lines in those plants is covered on the sanitary process piping in Georgia page. On biologics and pharmaceutical sites, piping is one part of a documented system that later has to be qualified, so weld logs, material certificates and passivation records are planned from the start and handed to the validation and commissioning in Georgia program as engineering turnover.
Buyers looking for industrial piping contractors Atlanta plants can rely on for both ends of that range want the same things: drawings that agree with what is installed, welds traceable to the welder and the procedure, test records that match the line list, and tie-ins that happen inside the window the plant gave. Those are the things Paul Industries plans around.
Which Georgia codes apply to process piping inside a plant?
Process piping inside a Georgia plant is designed and built to ASME B31.3 as the owner’s specification, while the state’s adopted codes, the Georgia State Minimum Standard Codes maintained by the Department of Community Affairs, govern plumbing, mechanical and fuel gas systems in the building. Since January 1, 2026, those codes are the 2024 International Building, Plumbing, Mechanical and Fuel Gas Codes with 2026 Georgia amendments, and a city or county that enforces codes has to enforce the current editions with the state amendments. Process piping requirements beyond those codes come from the owner’s piping specification, the fluid service category under B31.3 and any state rule that reaches the specific line.
Other state rules reach specific kinds of piping. Boiler external piping falls under Georgia’s Boiler and Pressure Vessel Safety Act, now O.C.G.A. Title 25, Chapter 15; the state fire commissioner’s Safety Engineering staff enforce it, and their Rule 120-3-26 adopts the ASME Boiler and Pressure Vessel Code, the National Board Inspection Code and ASME B31.1 for that piping. Flammable and combustible liquid piping meets the International Fire Code as modified by the Safety Fire Commissioner in Rule 120-3-3. Underground piping connected to regulated underground storage tanks falls under the Georgia EPD rules in Chapter 391-3-15, which since the 2017 amendments call for secondary containment and interstitial monitoring on new and replaced tanks and piping.
Georgia has no OSHA state plan, so federal OSHA covers private plants directly, and 29 CFR 1910.119 applies to any line in a covered process, such as an ammonia system above 10,000 pounds or a chemical process above its threshold quantity. In a PSM-covered process, a new line or a changed one goes through management of change and a pre-startup safety review before it carries product.
| Rule or agency | What it covers | When it matters on a piping job |
|---|---|---|
| Georgia State Minimum Standard Codes (DCA) | 2024 IPC, IMC and IFGC with 2026 Georgia amendments | Plumbing, fuel gas and mechanical work in the building, permits and inspections by the city or county |
| O.C.G.A. Title 25, Chapter 15 and Rule 120-3-26 | Boilers, pressure vessels, B31.1 boiler external piping | Steam headers at the boiler, repairs to vessels, new boiler and vessel installations |
| Rule 120-3-3 (Safety Fire Commissioner) | International Fire Code with Georgia modifications | Flammable and combustible liquid piping, solvent rooms, hot work |
| Georgia EPD Rule 391-3-1-.03 | Air construction and operating permits | New or modified emission units and the piping that feeds them |
| Georgia EPD Chapter 391-3-15 | Underground storage tanks and their piping | Buried fuel and chemical lines connected to regulated tanks |
| O.C.G.A. Title 25, Chapter 9 (Georgia 811) | Locating buried utilities before excavation | Trenching for buried process lines, pipe rack foundations |
| Federal OSHA 29 CFR 1910.119 | Process safety management | Lines in covered ammonia and chemical processes, management of change |
Process piping vs plumbing in a Georgia plant
Process piping vs plumbing in a Georgia plant comes down to what the pipe serves: domestic water, sanitary drainage, fixtures and their vents are plumbing under the Georgia-amended International Plumbing Code, while lines that carry product, chemicals or plant utilities to equipment are process piping built to B31.3 or B31.1. The boundary matters because it decides which drawings go to the building department, who inspects what, and where a backflow preventer has to sit.
The connection points are where most questions arise. A process water system fed from the city supply needs a backflow assembly at the point of separation; a floor drain receiving process waste may need neutralization or segregation before it joins sanitary drainage; and fuel gas to a process burner is governed by the fuel gas code up to the equipment. Georgia licenses the plumbing, conditioned air, electrical, low-voltage and utility trades through the Construction Industry Licensing Board under O.C.G.A. Title 43, Chapter 14, and general contracting through a separate board under Chapter 41, so the permit path for the building-code side of a project is set before work starts. Paul Industries draws that boundary on the piping drawings at design, so the permit set and the process scope agree.
Georgia EPD air permits and the piping that feeds an emission unit
Georgia EPD Rule 391-3-1-.03 requires any person to obtain a permit from the EPD Director before beginning construction or modification of a facility that may result in air pollution, and the piping that feeds a new or modified emission unit is part of that change. A new solvent line to a coating oven, added fuel piping to a dryer, a bigger feed to a reactor or a new tank vent header can each be the physical change that triggers permit review.
Small changes can sometimes be deferred under the rule’s provisions for modifications with low cumulative emission increases, and EPD keeps a list of exemptions, but the call is the plant’s environmental staff to make with EPD, and the piping scope has to wait for it where a permit is needed. Paul Industries prepares what the permit writer needs from the piping side: line lists, design flows and pressures, vent and relief routing, and the equipment the lines connect to. Building the line before the permit is issued risks a violation, so the construction schedule is built around the permit date.
Solvent recovery in cell plants, scrubbers on solar cell lines and dryers in kaolin plants are typical Georgia examples where piping and air permits meet. The permit often sets operating limits, such as recovery efficiency or scrubber flow, that depend on the piping and instruments working as designed, so commissioning the piping and proving the permitted performance belong in the same plan.
Pipe fabrication: Georgia spools built off site
Pipe fabrication for Georgia plants moves most welding off site, where spools are cut, fitted, welded, examined and pressure tested before they reach the plant. Off-site fabrication cuts the amount of hot work inside a running building, improves weld quality because welders work in controlled conditions, and shortens the tie-in window because spools arrive ready to bolt or weld in at a few field joints.
A Georgia spool package is built from isometric drawings with field-fit allowances at tie-in points, heat numbers traced to mill certificates, welds logged to the welder and the qualified procedure under ASME Section IX, and examination to the extent the fluid service and the owner’s specification call for. Stainless spools are bagged or capped to keep them clean on the way to the plant and while they wait for installation. For heavy wall or alloy lines, preheat and postweld heat treatment are done before shipping wherever the design allows. The industrial welding services in Georgia page goes into qualification and examination on field welds.
Summer heat and humidity in Georgia affect field work more than fabrication: field welds on stainless get shielding protected from drafts, carbon steel gets preheat where moisture could condense on the joint, and coatings are applied inside their dew point limits. Off-site fabrication keeps most of that work out of the weather.
Shutdown windows and pressure testing in a running Georgia plant
Shutdown windows in a running Georgia plant are short and fixed, whether it is a poultry plant’s sanitation shift, a paper mill’s annual outage or a cell plant’s planned stop, so the tie-in plan is written before fabrication begins. The plan lists each tie-in, the isolation and draining needed, the work that can be done before the stop, the work that has to happen inside it, and the test that proves each joint before the line returns to service.
| Step | What happens | Record produced |
|---|---|---|
| 1. Walkdown and line list | Verify existing lines, sizes, materials and valve positions against drawings | Marked-up drawings, tie-in list |
| 2. Pre-outage work | Install new supports and runs up to isolation valves while the plant runs | Installation checklist |
| 3. Isolation and lockout | Isolate, drain, purge or clean the existing line under the plant’s energy control program | Isolation permit and lockout list |
| 4. Tie-in | Cut in, weld or bolt the new spool, examine the welds | Weld map, examination reports |
| 5. Pressure test | Hydrostatic or pneumatic test to B31.3, or an alternative the code permits for closure welds | Signed test record |
| 6. Return to service | Reinstate the line, check for leaks under operating conditions, complete the PSSR where PSM applies | Turnover package and as-built drawings |
Hydrostatic testing to B31.3 is the default, at 1.5 times design pressure with temperature correction; pneumatic testing is used where water cannot be tolerated, such as dry-air and nitrogen headers in cell plants, with the safety distances and stepped pressurization the code requires. Closure welds that cannot be pressure tested get the code’s alternative examination. The hydrostatic testing page describes the test methods and records.
What drives the cost of process piping in Georgia?
The cost of process piping in Georgia is driven by material, joint count, examination and access more than by the length of pipe, and the same footage can vary several times in price between a carbon steel utility run and an orbital welded stainless line in a dry room. Stainless and alloy material prices move with nickel and molybdenum markets, so quotes are valid for a stated period.
Other drivers are the work that has to happen inside a shutdown, the examination percentage the fluid service calls for, the height and congestion of the rack, coating and insulation, and documentation, which on a biologics site can be a large share of the effort. Georgia’s lack of a state prevailing wage law for private work keeps labor rates on private plant projects at market rates; projects with federal funding are a different case under the federal Davis-Bacon Act.
Paul Industries gives a budget range from comparable scope as soon as the line list and drawings are known, then a firm price once the design, materials and outage plan are fixed. To price process piping in Georgia, send the P&IDs or a line list, materials and pressure classes, the outage windows, and photos of the tie-in points.
Who installs process piping in Georgia?
Paul Industries installs process piping in Georgia, from design and spool fabrication through installation, testing and turnover, for battery, solar, mineral, paper, chemical, food and life sciences plants statewide. Its headquarters sit at 256 Shore Drive, Kilmarnock, Virginia; the company was formerly based in northern New Jersey and later Pennsylvania, and as an East Coast contractor it takes plant work across Georgia and in all 50 states.
An industrial piping contractor at a Georgia plant is judged on accountability for the line from drawing to signed test record. Paul Industries takes that whole scope under one contract: engineering, material supply, spool fabrication, installation, testing, documentation and start-up. The Virginia program is on the process piping in Virginia page for the headquarters state, and the neighboring Carolina work is on the process piping in North Carolina page.
Most Georgia piping jobs connect to other plant systems Paul Industries builds there, including pressure vessel fabrication in Georgia, tank fabrication in Georgia and boiler repair in Georgia. Work across the region is summarized on the Southeast page.
Paul Industries and Georgia plant piping
Paul Industries is an industrial process piping company that designs, fabricates, supplies, installs, tests, starts up and maintains plant piping for Georgia manufacturers, as supply-only spools, as design-build packages or as complete installations at the plant. The scope covers solvent and chemical lines, slurry systems, steam and condensate, compressed air and gases, refrigeration and sanitary process lines, and the documentation each needs. Plants in metro Atlanta, Savannah, Augusta, Macon, Columbus, Dalton, Rome, Athens and Gainesville can start with a line list or a drawing. Call 201-450-8280 or request a quote.
Standards referenced: ASME B31.3 Process Piping · ASME B31.1 Power Piping · ASME Section IX · ASME Boiler and Pressure Vessel Code · National Board Inspection Code · 2024 International Plumbing Code with 2026 Georgia amendments · 2024 International Mechanical Code with 2026 Georgia amendments · 2024 International Fuel Gas Code with 2026 Georgia amendments · International Fire Code with Georgia modifications (Rule 120-3-3) · Georgia Boiler and Pressure Vessel Safety Act (O.C.G.A. Title 25, Chapter 15) · Georgia Rules for Boilers and Pressure Vessels (Rule 120-3-26) · Georgia Rules for Air Quality Control (Rule 391-3-1-.03) · Georgia Underground Storage Tank Management Rules (391-3-15) · Georgia Utility Facility Protection Act (O.C.G.A. Title 25, Chapter 9) · OSHA 29 CFR 1910.119
Frequently asked questions
Who installs process piping for battery plants in Bryan County and Commerce, Georgia?
Paul Industries installs process piping for battery plants in Bryan County, around Ellabell and Savannah, and in Commerce and Jackson County. The work covers NMP solvent supply and recovery lines, chilled and process cooling water, dry compressed air and nitrogen headers with moisture-tight joints, and the drains and vents around recovery units. Send the line list, the dry room dew point specification and the outage plan for a scope and price.
Does Paul Industries take process piping work in Augusta, Macon and the kaolin belt?
Paul Industries takes process piping work in Augusta, Macon, Sandersville, Columbus and the rest of the fall line kaolin belt. Typical jobs are slurry lines with wear-back elbows and flushing points, steam and condensate to dryers and calciners, process water, and chemical feed systems for dispersants and bleaching agents. Paul Industries plans replacement of worn bends and spools around the plant’s production schedule.
Who builds process piping for plants around the Port of Savannah and Brunswick?
Paul Industries builds process piping for plants around the Port of Savannah, Brunswick and the Georgia coast, including chemical, food, ingredient and packaging operations in Chatham, Effingham, Bryan and Glynn counties. Coastal jobs get coating systems for salt air, stainless or coated bolting, careful insulation jacket detailing and outdoor work scheduled with hurricane season in mind.
Can Paul Industries pipe solar cell and module plants in Dalton and Cartersville?
Paul Industries pipes solar cell and module plants in Dalton, Cartersville and northwest Georgia, including Rome and Calhoun. The scope includes acid and caustic distribution in thermoplastic or lined pipe, double containment where lines cross walkways or equipment, deionized water loops, process exhaust and segregated wastewater lines. Drain segregation is designed so incompatible chemistries never meet in a sump.
Does process piping inside a Georgia plant need a building permit?
Process piping built to ASME B31.3 inside a Georgia plant is set by the owner’s specification, while plumbing, mechanical and fuel gas work in the building falls under the Georgia State Minimum Standard Codes and the city or county permit process. Projects often include both, so Paul Industries marks the boundary on the drawings and prepares the permit set for the building-code side early in design.
Which edition of the plumbing and mechanical codes applies in Georgia in 2026?
Since January 1, 2026, Georgia’s state minimum codes are the 2024 International Plumbing Code, 2024 International Mechanical Code and 2024 International Fuel Gas Code, each with 2026 Georgia amendments from the Department of Community Affairs. A city or county that enforces codes has to use those editions and amendments, and can add its own amendments on top.
Which code governs steam piping at a boiler in Georgia?
Boiler external piping in Georgia is built to ASME B31.1 as adopted by ASME Section I, under Rule 120-3-26 of the Safety Fire Commissioner, which administers the Boiler and Pressure Vessel Safety Act in O.C.G.A. Title 25, Chapter 15. Beyond the boiler external piping boundary, plant steam distribution is commonly built to B31.1 or B31.3 according to the owner’s specification.
Does adding a solvent line to a coating oven need a Georgia EPD permit?
Adding a solvent line to a coating oven can be part of a modification that needs a Georgia EPD air permit under Rule 391-3-1-.03, because the rule requires a permit before construction or modification of a facility that may result in air pollution. The plant’s environmental staff makes that determination with EPD, and Paul Industries supplies line lists, flows and vent routing for the application and schedules the work around the permit.
How is buried process piping located and protected in Georgia?
Buried process piping in Georgia starts with a Georgia 811 locate request under the Utility Facility Protection Act in O.C.G.A. Title 25, Chapter 9, before any excavation. New buried lines get coating, cathodic protection where the soil and material call for it, tracer wire or marking tape for future locates, and as-built locations tied to plant coordinates in the turnover drawings.
What do Georgia rules require for piping connected to an underground storage tank?
Georgia EPD rules in Chapter 391-3-15 adopt the federal underground storage tank requirements largely by reference, and since the 2017 amendments new and replaced tanks and piping need secondary containment with interstitial monitoring, along with periodic testing of spill equipment and containment sumps. Paul Industries installs the double-wall piping, sumps and monitoring points and hands over the test records.
Does a piping change on a Georgia ammonia system need management of change?
A piping change on a Georgia ammonia system holding more than 10,000 pounds falls under federal OSHA process safety management, because Georgia has no state OSHA plan. Management of change applies before the work, process safety information such as drawings and relief design is updated, and a pre-startup safety review is completed before the modified system returns to service. Paul Industries builds that paperwork into the piping scope.
Which materials suit NMP and other solvent lines in a battery plant?
NMP and similar solvent lines in battery plants are usually 304L or 316L stainless, because solvent purity affects cell quality and stainless resists the solvent without leaching. Gaskets and valve seats are chosen for compatibility with the solvent, the lines are treated as combustible liquid service under B31.3 and the fire code, and joints are welded wherever possible to reduce leak points.
Is HDPE a good choice for kaolin slurry lines?
HDPE is a good choice for many low-pressure kaolin slurry and process water lines because it resists abrasion and does not corrode, but it needs support spacing and expansion allowance for Georgia summer temperatures, and fusion joints made to a qualified procedure with records. Higher pressures or temperatures usually call for rubber-lined or wear-allowance steel instead, and Paul Industries selects the material line by line.
Is there prevailing wage on a private plant piping project in Georgia?
Georgia has no state prevailing wage law, so private plant piping projects are priced at market labor rates. Projects funded or assisted by the federal government are a different case, because the federal Davis-Bacon Act sets wage rates on covered work. Paul Industries prices each project on the basis that applies to it and states that basis in the proposal.
How much does process piping cost at a Georgia plant?
Process piping at a Georgia plant costs according to material, joint count, examination, access, outage work and documentation rather than length alone, so a carbon steel utility run and an orbital welded stainless dry-air line can differ several times per foot. Paul Industries provides a budget range from comparable scope once the line list is known and a firm price after the design and outage plan are fixed.
Can Paul Industries supply fabricated spools to a Georgia plant as a supply-only order?
Paul Industries supplies fabricated spools to Georgia plants as supply-only orders, built from the plant’s isometrics or from drawings Paul Industries prepares. Each spool ships with heat numbers traced to mill certificates, a weld map tied to welder and procedure, examination and pressure test records, and clean, capped ends. Paul Industries also installs them when the plant wants one contract from fabrication to start-up.
What records does a Georgia plant receive when a piping job is finished?
A finished Georgia piping job comes with as-built drawings and isometrics, the line list, material certificates, weld maps with welder and procedure records, examination reports, signed pressure test records, cleaning and passivation records where they apply, and the PSSR documentation for PSM-covered lines. On biologics sites the package is arranged so the validation team can use it directly as engineering turnover.
What should a Georgia plant send to get process piping quoted?
To get process piping quoted, a Georgia plant should send P&IDs or a line list with fluids, pressures and temperatures, the material and piping class specification, any existing isometrics or photos of the routing and tie-in points, the outage windows available, and the plant’s documentation requirements. Paul Industries returns a budget range first and a firm price once the scope is defined.
Adding or replacing process lines at a Georgia plant?
Send the line list or P&IDs, materials, pressure classes, outage windows and photos of the tie-in points. Call 201-450-8280 or request a quote.