Paul Industries designs, prefabricates, installs, flushes and fills data center liquid cooling in South Carolina: facility water loops, coolant distribution units, row manifolds and the dry cooler or chiller plant that rejects the heat, for halls from Berkeley County to the Upstate. South Carolina weather favors warm-water liquid cooling more than its humid summers suggest, because a facility loop held near 90 F runs on dry coolers alone for most of the year even in Charleston. Paul Industries, headquartered at 256 Shore Drive, Kilmarnock, Virginia, takes this work across the state as supply-only, design-build or complete installation.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
W32 dry cooler trim About 754 hours a year at Greenville-Spartanburg, 1,069 at Charleston (NWS hourly data 2021 to 2024, 7 F approach)
Freeze exposure 314 hours a year at or below 32 F at Greenville-Spartanburg; 7 F low in the record
Hydronic test 1.5 times design pressure, at least 100 psi, 15 minutes (2021 SC Mechanical Code 1208.1)
Industrial power 6.84 cents/kWh (EIA, 2024)
Reviewed November 2026

What is involved in data center liquid cooling in South Carolina?

A project for data center liquid cooling in South Carolina involves three connected loops: the heat rejection loop outdoors, the facility water loop that runs from the plant to the hall, and the technology cooling loop that a coolant distribution unit pumps through cold plates, rear doors or immersion tanks. Each loop has its own pressure rating, fluid, filtration and cleanliness standard, and each meets the next at a heat exchanger. Paul Industries builds all three, and on most South Carolina jobs the outdoor loop deserves the closest look at site weather, because that is where the coast and the Upstate differ.

For liquid cooling, South Carolina’s coast and Upstate call for different heat rejection, but the decision that shapes everything else is the facility water temperature. ASHRAE’s liquid cooling classes, W17 through W45 and W+, are named for the upper facility water supply limit in degrees Celsius, so a W32 loop accepts supply water up to about 89.6 F. The warmer the class the IT equipment accepts, the more hours a dry cooler can carry the load without a chiller. South Carolina owners who pick the class with the outdoor data in hand save chiller capacity, energy and water at the same time.

Which South Carolina rooms are moving to liquid cooling?

Liquid cooling in South Carolina is arriving first in hyperscale halls, university research computing and enterprise rooms adding dense GPU servers, and each of those settings asks something different of the mechanical work. Google’s October 2025 announcement of $9 billion for its Berkeley County campus and two new Dorchester County campuses framed the spending around cloud and artificial intelligence capacity, which in current hardware generations increasingly means direct to chip cooling. Smaller rooms at hospitals, insurers, manufacturers and colocation providers in Columbia and the Upstate often begin with a handful of liquid-cooled racks inside an air-cooled hall.

South Carolina rooms taking liquid-cooled racks and what each asks of the piping
Room typeWhere in South CarolinaTypical liquid cooling startMechanical work that decides the schedule
Hyperscale campus hallsBerkeley and Dorchester countiesDirect to chip on facility CDUs, designed in from the startLarge facility water headers, dry cooler or hybrid yards, phased CDU galleries
University research computingClemson, Columbia and Charleston campusesTertiary loop off a campus chilled water plantMixing valve control, chilled water capacity, outage windows around semesters
Enterprise rooms with new GPU serversGreenville, Spartanburg, Columbia, Rock HillRear doors or in-row CDUs on a few racksBranch off existing chilled water, condensation control, raised floor capacity
Colocation hallsMidlands and the I-85 corridorLiquid-ready rows offered to tenantsValved tap points for future tenants, metering per customer
Hospital and health system roomsCharleston, Columbia, Greenville, FlorenceImaging and analytics servers on rear doorsWork inside infection control and life safety rules, redundant pumping

The Clemson tertiary loop: liquid cooling in a South Carolina research data center

Clemson University’s Information Technology Center shows how a South Carolina research room adds liquid cooling to an existing chilled water plant: according to the university, about 275 tons of liquid cooling capacity reaches its Research Computing and Data Infrastructure space through a tertiary loop, with the temperature held by building automation and three-way mixing valves. The same description lists three 250-ton chillers, two of them active for 500 tons of capacity, two 2.5 MW transformers and roughly 10,000 square feet of the center’s 20,000 square feet of raised floor allocated to research computing. The Clemson Palmetto cluster, whose second iteration went live on May 13, 2024, includes nodes with H100 and H200 GPUs.

These are market facts, and the design pattern behind them is common to many campuses. A tertiary loop takes chilled water from the campus plant, blends it with warmer return water through a mixing valve, and delivers water at a temperature suited to the IT equipment rather than to air handlers. That lets an existing plant serve liquid-cooled racks without lowering its own setpoints or exposing cold plates to water below the room dew point. Paul Industries designs and installs tertiary loops, mixing stations, pumps and controls of this kind for universities, hospitals and enterprise rooms across South Carolina.

Dry cooler trim hours at Charleston, Columbia and Greenville-Spartanburg

Dry cooler trim hours are the hours each year when outdoor air is too warm for a dry cooler to deliver the facility water temperature on its own, so a chiller or an adiabatic stage must help. Paul Industries counted them for each ASHRAE class from National Weather Service hourly observations at the three main South Carolina airports for 2021 through 2024, assuming a 7 F approach between outdoor air and leaving fluid for dry coolers, and the same approach to wet bulb for adiabatic coolers in wet mode.

Hours per year a South Carolina liquid loop needs help beyond a dry cooler, by ASHRAE facility water class (NWS hourly data 2021 to 2024, Paul Industries calculation)
Facility water class and supply limitCharleston: dry / adiabaticColumbia: dry / adiabaticGreenville-Spartanburg: dry / adiabatic
W17, 62.6 F6,857 / 5,9196,296 / 5,3155,662 / 4,446
W27, 80.6 F3,352 / 1,6012,991 / 1,1562,129 / 328
W32, 89.6 F1,069 / 11,082 / 0754 / 0
W40, 104 F0 / 016 / 01 / 0

The table carries the main design lesson for the state. A W17 loop, sized like traditional chilled water, needs mechanical cooling for most of the year everywhere in South Carolina. Moving to W32 cuts Charleston’s dry cooler trim to about 1,069 hours, and with an adiabatic stage the chiller is almost never needed even on the coast. In the Upstate, a W27 loop on hybrid coolers needs help for only about 328 hours a year. A data center liquid cooling Greenville SC owners plan around W32 equipment can treat the chiller as a backup rather than a primary machine.

The hours matter for money as well as for equipment. For a 5 MW liquid-cooled load in Charleston, a chiller drawing 0.6 kW per ton would run about 5,788 fewer hours a year at W32 than at W17, saving roughly 4,900 MWh, or about $337,700 a year at South Carolina’s 2024 industrial average of 6.84 cents per kWh. That figure assumes constant full load and a chiller carrying the whole load during trim hours, so treat it as an upper bound for comparison rather than a forecast.

How does data center liquid cooling work in a South Carolina hall?

Data center liquid cooling works by carrying heat from the processor to water through a cold plate, rear door coil or immersion bath, then moving that heat through a coolant distribution unit into the facility water loop and out to dry coolers, towers or chillers. The technology cooling loop on the rack side is small, clean and tightly controlled, usually a propylene glycol and water mixture or treated water with fine filtration. The facility water loop is larger and connects to the building plant. The data center liquid cooling CDU sits between them with a plate heat exchanger, pumps, filters, an expansion tank and controls that hold supply temperature and pressure.

In a South Carolina hall, the plant side of that chain is where the climate enters. Facility water held at W27 or W32 temperatures stays well above the indoor dew point, so the piping in the hall runs dry even when outdoor air is saturated. The outdoor heat rejection then sees warm return water, often in the mid 90s to low 100s F, which is easy to cool with outdoor air for most of the year. The comparison of data center liquid cooling vs air cooling in this climate therefore turns less on the hall than on the plant: air cooling needs cold chilled water through every humid summer, while warm-water liquid cooling lets the plant work against the weather rather than fight it.

Keeping facility water pipe dry in Lowcountry humidity

Facility water piping in a Lowcountry building stays dry only if every surface colder than the surrounding air dew point is insulated with a sealed vapor retarder, and Charleston’s outdoor dew point sits at 70 F or above for about 2,149 hours a year. Inside a conditioned hall the indoor dew point is lower, but the same pipe often passes through mechanical yards, service corridors, ceiling spaces and loading areas that see outdoor air. Any run of chilled water feeding a CDU through those spaces can drip, rust hangers and wet electrical gear.

Paul Industries designs the routing and insulation together: closed-cell insulation with sealed seams on cold lines, vapor-sealed hangers and supports, insulated valve bodies and strainers, and condensate-safe routing that keeps cold piping away from switchgear. Warm facility water loops above the dew point remove much of the problem, and that alone is a reason many coastal owners raise their facility water temperature when they add liquid cooling.

Data center liquid cooling options for South Carolina rooms

The data center liquid cooling options a South Carolina room usually compares are rear-door heat exchangers, direct to chip cooling through in-row or in-rack CDUs, direct to chip cooling through facility CDUs on a central loop, and immersion tanks. The right one depends on rack density, the IT vendor’s requirements, the existing building plant and how many racks will follow the first ones. Paul Industries supplies and installs the data center liquid cooling equipment for each route, including CDUs, manifolds, hoses, valves, filters and leak detection.

Liquid cooling methods and how each fits a South Carolina room
MethodWhat the building must provideSouth Carolina considerationTypical fit
Rear-door heat exchangersChilled water branch to each door, condensate protectionWater must stay above the room dew point; coastal humidity punishes cold doorsEnterprise rooms adding moderate density to existing racks
Direct to chip, in-row or in-rack CDUFacility water taps at the row, power for CDU pumpsWorks off existing chilled water through a mixing or tertiary loopFirst GPU rows in an air-cooled Columbia or Upstate hall
Direct to chip, facility CDUs on a central loopDedicated facility water headers, CDU gallery, warm-water heat rejectionW32 design lets dry coolers carry nearly all hours even in CharlestonNew halls and hyperscale phases in Berkeley and Dorchester counties
Single-phase immersionTank floor loading, fluid storage and handling, facility water to tank heat exchangersWarm return fluid suits dry coolers; fluid handling needs its own proceduresDense specialized compute in purpose-built rooms

Coolant, filtration and freeze protection for South Carolina loops

Coolant for the rack-side loop is chosen by the cold plate and CDU makers, most often a 25 percent propylene glycol mixture or treated water, and the facility loop is chosen by the plant designer, with freeze protection added wherever piping or coils sit outdoors. South Carolina winters are short but real: Greenville-Spartanburg logged about 314 hours a year at or below 32 F in 2021 through 2024 and a low of 7 F, Columbia 225 hours and 12.9 F, and Charleston 76 hours and 18 F. Dry coolers with water-only fluid freeze in those conditions unless they drain down or carry glycol.

Paul Industries sizes glycol concentration for the site’s record low with margin, installs strainers and side-stream filters at the rating the CDU maker requires, and flushes new pipe until the discharge meets the cleanliness the cold plate warranty demands. Filling follows a written procedure with air removal at high points and sampling before IT equipment is connected. Pressure testing follows the 2021 South Carolina Mechanical Code, which requires hydronic piping to hold 1.5 times its maximum design pressure, and at least 100 psi, for 15 minutes or longer.

Retrofitting liquid cooling into an air-cooled hall in Columbia or the Upstate

A liquid cooling retrofit in an operating South Carolina hall starts with a survey of four limits: spare chilled water capacity at the right temperature, routes for new pipe above or below the racks, floor loading for heavier racks and CDUs, and the electrical capacity for CDU pumps on protected power. Most Columbia and Upstate rooms were built around chilled water at 45 to 55 F for air handlers, so the first liquid-cooled racks usually connect through a mixing station or a dedicated heat exchanger that raises the supply temperature for the IT equipment.

Paul Industries prefabricates headers and branch spools off site, installs isolation valves at every future tap so later racks connect without draining the loop, and schedules hot work and tie-ins inside the operator’s change windows. Each new section is pressure tested, flushed and filled before it is valved into the live system. The data center cooling in South Carolina page covers the central plant and heat rejection side of these upgrades, and data center commissioning in South Carolina covers the testing that proves the finished loop.

Flushing, fill and startup on a South Carolina liquid loop

Flushing, fill and startup turn installed pipe into a liquid cooling system for data centers that the IT vendor will accept, and the sequence matters as much as the equipment. Debris left from fabrication, cutting oil or weld scale can block the narrow channels inside a cold plate, and trapped air starves CDU pumps and hot spots the rack. Paul Industries runs each South Carolina loop through the same documented order, with a hold point and a record at every step, before any server is connected.

Sequence for bringing a new facility water and CDU loop into service
StepWhat happensRecord produced
Hydrostatic testLoop held at 1.5 times design pressure, at least 100 psi, for 15 minutes or longer, with CDUs and cold plates isolatedTest report with gauge serials, pressures and hold time
Bypassed flushTemporary jumpers and strainers route water around CDUs and racks at flushing velocity until screens stay cleanFlushing log with strainer inspections and water samples
Cleaning and passivation where specifiedChemical clean for steel or mixed-metal loops, then rinse to the target conductivityChemistry log and final rinse readings
Fill and ventingLoop filled with the specified fluid, air removed at high points, concentration checkedFill record with fluid batch, concentration and volume
CDU startupPumps, valves, sensors and alarms proven; leak detection tested; setpoints enteredStartup sheets and alarm test list
Heat load testLoad banks or the first racks run at design heat to prove flow and temperature at every branchTrend data for supply, return and flow

CDU pumps, storms and power ride-through

CDU pumps need power through a utility outage because cold plates have very little thermal mass, and a direct to chip loop that stops circulating can push processors to throttle or shut down within seconds to minutes. In a state where hurricanes and summer thunderstorms interrupt grid power, the CDU pumps and the controls that run them belong on UPS-backed power, with the facility water pumps carried through the generator start sequence. Paul Industries designs the pump power arrangement, control logic and restart sequences into the electrical plan so the liquid loop keeps moving while the plant transfers to generators.

What does data center liquid cooling in South Carolina cost?

The cost of data center liquid cooling in South Carolina depends on the number of racks and their heat load, the liquid cooling method, the facility water temperature, the condition of the existing plant, and whether the work happens in a new hall or an operating one. Published per-rack prices vary too widely with those factors to quote fairly, so Paul Industries prices each project from its scope and offers a budget range from comparable work, then a firm price once drawings and IT requirements are fixed. Energy is part of the comparison too: as the trim-hour figures above show, choosing a warmer facility water class can save hundreds of thousands of dollars a year in chiller energy on a multi-megawatt load.

Who installs and maintains data center liquid cooling in South Carolina?

Paul Industries installs and maintains data center liquid cooling in South Carolina, from the outdoor dry coolers and chillers to the facility water headers, CDUs, row manifolds and the flushing and fill that come before IT equipment is connected. For anyone asking who does liquid cooling for data centers in the state, Paul Industries designs the loops or builds to the engineer’s design, fabricates pipe spools and pump skids, supplies the data center liquid cooling systems and components, installs and tests the piping, fills and starts the loops and services them after turnover. Owners choose supply-only, design-build or complete installation.

Related South Carolina work includes data center mechanical contractors in South Carolina for the full mechanical package, chiller repair in South Carolina for the plants that feed CDU loops, and process piping in South Carolina for plant utilities. Research rooms are covered on the research labs and universities page, and the national data center liquid cooling page explains CDUs, cold plates and pressure testing in more depth.

Paul Industries is an East Coast contractor that was formerly based in northern New Jersey and then Pennsylvania and is now headquartered in Kilmarnock, Virginia. It builds data center liquid cooling in Virginia, its headquarters state, and data center liquid cooling in North Carolina to the same standard it brings to South Carolina and the rest of the Southeast.

Liquid cooling from Paul Industries for South Carolina halls

Paul Industries designs, supplies, installs, flushes, fills and maintains liquid cooling loops for South Carolina data halls, choosing facility water temperatures that let Charleston, Columbia and Upstate plants run on outdoor air for as many hours as the IT equipment allows. Send the rack count and heat load, the IT vendor’s facility water requirements, the existing plant data and the schedule, and Paul Industries will set out the route and a budget range. The South Carolina page lists Paul Industries’ other work in the state, and the next step is to request a quote.

Standards referenced: ASHRAE TC 9.9 liquid cooling guidelines (W17, W27, W32, W40, W45, W+ classes) · ASHRAE TC 9.9 Thermal Guidelines for Data Processing Environments, 5th edition · 2021 South Carolina Mechanical Code (2021 IMC with SC modifications), Section 1208.1 · ASME B31.9

Frequently asked questions

Who does liquid cooling for data centers in Charleston, Summerville and Berkeley County?

Paul Industries designs and installs liquid cooling for data halls around Charleston, Summerville, Moncks Corner and the rest of Berkeley and Dorchester counties, from CDU galleries and row manifolds to the dry cooler or hybrid yard outdoors. Coastal loops are designed around high summer dew points, with warm facility water that keeps hall piping dry. Call 201-450-8280 or request a quote with the rack count and heat load.

Who installs liquid cooling for research computing rooms in Clemson, Greenville and the Upstate?

Paul Industries installs tertiary loops, mixing stations, CDUs and rack manifolds for university and enterprise research computing rooms across the Upstate, including Clemson, Greenville, Spartanburg and Anderson. These rooms usually draw from an existing campus or building chilled water plant, so the work centers on holding the right supply temperature, protecting the plant’s other loads and fitting tie-ins into academic calendars.

Can Paul Industries pipe liquid-cooled racks in Columbia and the Midlands?

Paul Industries pipes liquid-cooled racks for state, insurance, health care and colocation rooms in Columbia, Lexington and the rest of the Midlands. Columbia has the hottest afternoons of the three main South Carolina airports, so warm facility water classes matter: a W32 loop there needs dry cooler help for only about 1,082 hours a year, against about 6,296 for a W17 loop.

Do data centers use liquid cooling in South Carolina yet?

Yes. University research computing at Clemson already uses a liquid cooling tertiary loop, according to the university, and enterprise rooms across the state are adding liquid-cooled GPU servers. The large Berkeley and Dorchester County campuses announced since 2024 are being built at a time when many high-density server platforms are designed for direct to chip cooling. Paul Industries designs and installs these loops statewide.

Are data centers liquid cooled when they sit in humid coastal air?

Increasingly, and humid coastal air is one reason. Air cooling needs cold chilled water and heavy dehumidification through a Charleston summer, while liquid cooling can run facility water near 90 F, well above any indoor dew point, and reject heat with dry or adiabatic coolers for nearly every hour of the year. Halls usually keep some air cooling for memory, storage and network equipment alongside the liquid loop.

How are data centers liquid cooled when the building plant also serves air handlers?

The usual answer is a mixing or tertiary loop. Cold chilled water from the existing plant is blended with warm return water so the CDUs receive water at the temperature the IT equipment wants, while air handlers keep their own colder supply. As liquid-cooled racks multiply, a dedicated warm-water loop with its own dry coolers often follows, freeing chiller capacity for the remaining air-cooled load.

Which ASHRAE water class suits a dry cooler plant in Charleston?

W32, with supply water up to about 89.6 F, is a practical target where the IT equipment accepts it. Paul Industries’ count of 2021 to 2024 hourly data shows a Charleston dry cooler at a 7 F approach needs help for about 1,069 hours a year at W32, and an adiabatic stage reduces that to nearly zero. At W27 the dry cooler alone needs help for about 3,352 hours.

How many hours a year does a Greenville-Spartanburg liquid loop need chiller trim?

At W32, about 754 hours a year on dry coolers alone and essentially none with adiabatic assist, based on 2021 to 2024 hourly observations at the airport. At W27 the figures are about 2,129 hours dry and 328 with adiabatic help. Upstate sites therefore suit warm-water liquid cooling well, although winter freeze protection needs more attention than on the coast.

Does a South Carolina liquid loop need glycol?

Any loop with coils or piping outdoors needs freeze protection, because every part of the state sees freezing hours: about 314 a year at Greenville-Spartanburg, 225 at Columbia and 76 at Charleston, with lows of 7 F, 12.9 F and 18 F in 2021 to 2024. Glycol, drain-down or a heat exchanger that keeps glycol outdoors and water indoors are the usual answers. Paul Industries sizes the concentration for the site’s record low.

Can existing chillers serve a new CDU loop in a South Carolina hall?

Often, if the plant has spare capacity at peak and a way to deliver warmer water to the CDUs. Paul Industries checks chiller loading on the hottest days in the plant’s records, pump and header capacity, and control sequences, then designs a mixing station or heat exchanger connection. Where spare capacity is thin, a dedicated dry cooler loop for the liquid-cooled racks can relieve the chillers instead.

What happens to CDU pumps during a hurricane power outage?

If they stop, cold plates lose cooling almost immediately, so CDU pumps and their controls belong on UPS-backed power that carries them until generators take over. The facility water pumps and heat rejection must restart in sequence after the transfer. Paul Industries plans pump power, restart logic and alarms with the electrical design, and tests the sequence during commissioning before IT equipment is loaded.

Is immersion cooling a practical choice for South Carolina data halls?

Immersion cooling suits dense, specialized compute in purpose-built rooms, and its warm return fluid fits South Carolina dry coolers well. It asks more of the building in floor loading, fluid storage and handling procedures, and maintenance access. Most South Carolina owners adopting liquid cooling today choose direct to chip, but Paul Industries designs and installs facility water connections for immersion tanks where owners choose them.

Which data center liquid cooling options suit a mid-size enterprise room?

Rear-door heat exchangers and in-row CDUs suit mid-size rooms adding a few dense racks, since both connect to existing chilled water through a short branch. Rear doors need water above the room dew point. In-row CDUs feed direct to chip servers and scale row by row. Paul Industries compares them against the room’s plant capacity, floor and power before recommending one.

Who provides liquid cooling for data centers on a supply-only basis in South Carolina?

Paul Industries supplies CDUs, manifolds, pump skids, dry coolers, valves and filtration to South Carolina projects on a supply-only basis, and it prefabricates headers and spool pieces off site for delivery to the job. The same items are available under design-build or complete installation contracts, with flushing, filling, testing and startup included.

What test and flushing records come with a South Carolina liquid loop?

Paul Industries hands over pressure test records showing the test pressure and hold time under the 2021 South Carolina Mechanical Code, flushing logs with filter and sample results, fill records with fluid type and concentration, valve and instrument tags, and startup data for CDUs and pumps. Those records support the IT vendor’s warranty and the owner’s commissioning file.

How long does a liquid cooling refit take in an operating South Carolina hall?

A first phase of a few liquid-cooled rows typically takes weeks of site work once equipment is on hand, while CDU and dry cooler lead times often set the overall schedule. Off-site prefabrication shortens the time in the live hall, and valved taps installed in the first phase let later rows connect without another shutdown. Paul Industries builds the schedule around the operator’s change windows.

Which details help Paul Industries scope a liquid cooling project for a South Carolina room?

Send the number of liquid-cooled racks and their heat load, the IT vendor’s facility water class and fluid requirements, existing plant drawings and capacity data, the site location and the target schedule. For an operating hall, add outage and change window rules. Paul Industries returns a budget range from comparable work, then a firm price. Call 201-450-8280 or request a quote.

Bringing liquid-cooled racks into a South Carolina hall?

Send the rack count and heat load, the IT vendor’s facility water class, existing plant data and the schedule. Call 201-450-8280 or request a quote.