Paul Industries installs data center liquid cooling in Virginia, retrofitting coolant distribution units, cold plate loops, rear-door heat exchangers and their facility water connections into halls that were built for air, from its headquarters in Kilmarnock, Virginia. In Loudoun and Prince William counties most of the opportunity sits inside existing buildings, because new data center sites now face a county special exception process and a grid that cannot always deliver new power on the owner’s schedule. Densifying a hall that already has its utility service is often a quicker route to high-density GPU capacity than a new building.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Existing data center buildings in Loudoun About 245, with 58.3 million sq ft built or underway
Loudoun zoning since March 18, 2025 New data centers need a special exception
Eastern Loudoun power, 2022 Constraints affected two-thirds of county substations
Value of 1 kW saved About $788 a year at 8.99 cents/kWh (EIA, 2024)
Reviewed November 2026

Why data center liquid cooling in Virginia is mostly a retrofit story

Data center liquid cooling in Virginia is driven as much by land use and power rules as by chip heat, because those rules make an existing, energized hall the scarcest asset in the market. On March 18, 2025 the Loudoun County Board of Supervisors voted 7 to 2 to remove data centers as a by-right use, so new projects outside the grandfathered pipeline now need a special exception approved after public hearings. Three years earlier, Dominion Energy had told developers that new connections in eastern Loudoun could wait years while transmission caught up.

Put those two facts together and the economics shift for owners in Data Center Alley, Virginia’s original concentration of hyperscale and colocation halls. An operator with a 234,000 square foot hall, roughly the average size of an existing Loudoun data center building according to the county, and a utility service already in place can add compute without a rezoning or a new substation, provided the cooling can handle racks at several times the density the building was designed for. Air alone usually cannot. Liquid can, if it is installed without disturbing the tenants already running in the room.

That is the work this page covers: surveying a live hall, choosing a liquid cooling architecture the building can support, piping it without outages, and tying it to a chilled water plant that was never designed for it. The national data center liquid cooling page explains the technology itself; here the subject is fitting it into Virginia’s existing stock.

What is Data Center Alley, and why does it matter for retrofits?

Data Center Alley is the name for the concentration of data centers in eastern Loudoun County, centered on Ashburn and Sterling, which Loudoun County traces to Ashburn’s network connectivity. The story begins with MAE East, an early commercial internet exchange point, created in Vienna, Virginia in 1992, and with AOL’s move to an Ashburn headquarters in 1996. Fiber, power and land followed, and the Northern Virginia Data Center Alley market grew outward from that core into Prince William and Fairfax counties.

The county now counts about 245 existing data center buildings, representing roughly 58.3 million square feet built or under construction as of September 2026, and it issued permits for more than 10 million square feet in 2025 alone. Where is Data Center Alley in Virginia, exactly? Any Data Center Alley map shows the buildings clustered around Ashburn and Sterling and along the Route 28 corridor, in office and industrial districts the county zoned for that use.

For a liquid cooling retrofit, the age profile of that stock is what matters, and the Loudoun County Data Center Alley corridor holds a deep stock of halls built for air cooling. Halls commissioned a decade or more ago were designed for a few kilowatts per rack, with raised floors, perimeter cooling units and chilled water plants running cold supply temperatures. Ashburn Data Center Alley halls of that era are the ones owners now most want to densify. The newer buildings, averaging closer to 339,000 square feet since 2023, are more likely to have been designed with liquid cooling headers or at least space for them.

Loudoun County data center zoning and the special exception process

Loudoun County data center zoning changes adopted in March 2025 converted data centers from a by-right use to one that requires a special exception wherever they had previously been permitted outright. By-right applications had been approved administratively without review by the Planning Commission or the Board; now a new building goes through public hearings, compatibility review and Board approval. Applications accepted before February 12, 2025 were allowed to continue under a grandfathering resolution, with exceptions for sites close to homes.

Is there a Virginia data center moratorium? The county states that it has no legal authority to impose a Loudoun County data center moratorium on new applications, and that each application must be judged on its merits. The practical effect is a slower, less certain path for new buildings rather than a ban. Owners of existing buildings face none of that review when they upgrade cooling equipment inside a permitted hall, though mechanical alterations still need building permits and inspections under the Virginia Uniform Statewide Building Code; data center commissioning in Virginia covers that inspection path.

Power already in the building: eastern Loudoun’s transmission limits

Eastern Loudoun’s transmission limits made existing utility capacity more valuable than new floor space, which is the second reason liquid retrofits pay in Data Center Alley. In 2022 a county staff report said Dominion’s constraints affected two-thirds of Loudoun’s substations and most of the projected data center growth, while confirming that operating data centers would not lose service. The main relief, a new 500 kV line in southern Loudoun, was planned for 2026, with interim upgrades to existing 230 kV lines and the Goose Creek substation.

Loudoun County data center capacity is therefore measured in megawatts delivered, not square feet available. Within a fixed allocation, adding IT load means spending less power on everything else, and fans are a large, easy target. Moving heat from chips straight into water removes most of the server and room fan energy for that load and lets the chilled water plant run warmer. Priced at 8.99 cents per kilowatt-hour, the 2024 Virginia industrial average reported by EIA, one kilowatt of fan or compressor power removed for a full year is worth about $788, and more importantly it is a kilowatt that can be sold as IT capacity.

Loudoun County data center growth will continue as transmission catches up, but the halls that already hold power are where densification starts. Liquid cooling is what lets a building designed at a few kilowatts per rack host racks at many times that density on the same utility feed.

Surveying an existing Loudoun or Prince William hall

Surveying an existing hall establishes what liquid cooling it can physically accept before any architecture is chosen. Every Sterling hall and every Prince William building of a given vintage has its own constraints, and the survey prevents a design that looks right on paper but cannot be installed around live equipment.

Retrofit survey items for an air-cooled hall and why each one decides the design
Survey itemWhat Paul checksWhy it matters
Floor constructionRaised floor depth, pedestal rating and underfloor obstructions, or slab on gradeDecides whether piping runs underfloor with leak trays or overhead above the aisles
Structural capacityFloor and slab loading against filled liquid-cooled racks and CDUsDense racks full of coolant are much heavier than the racks the hall was designed for
Overhead clearanceSpace between rack tops, cable trays, busway, sprinklers and ceilingOverhead headers need room for valves, slope, drains and access
Chilled water plantSupply temperature, spare tons, pump head and valve conditionSets whether CDUs can run on the existing plant or need a dedicated loop
Existing pipingMaterial, age, internal condition and isolation valves at tie-in pointsOld carbon steel lines carry debris that must not reach cold plates
ElectricalPanel capacity and redundant feeds for CDU pumps and controlsCDU pumps need power paths as reliable as the servers they cool
Humidity controlRoom dew point, makeup air and existing humidifiersCoolant must stay above the room dew point to avoid condensation
Access routesDoors, corridors, elevators and loading for CDUs and spoolsEquipment must reach the hall without crossing secure tenant space

Two survey findings decide most projects. The first is the chilled water plant’s spare capacity and temperature; the second is where pipe can physically run. A Loudoun, Virginia data center from the mid-2010s with an 18 to 24 inch raised floor packed with cable may leave overhead as the practical route, which changes valve access, drain points and leak protection completely.

Choosing a retrofit architecture for an air-cooled hall

A retrofit architecture is chosen by matching how much heat must go to liquid with what the building’s water, floor and power can deliver. Rear-door coils capture heat at the rack exhaust and leave servers unchanged; cold plate systems capture most of the heat at the chip but need servers built for them and a technology cooling loop to every rack.

Liquid cooling retrofit options and what each asks of an existing Virginia building
OptionHeat captured by liquidNeeds from the buildingFits when
Rear-door heat exchangers on chilled waterMost of the rack’s heat, as warm exhaust passes the coilChilled water branch to each rack, condensation control, door clearanceExisting servers stay; density rises moderately
Liquid-to-air CDU with cold platesChip heat to liquid, then back to room air inside the CDUPower and floor space only; no new facility waterA few dense racks in a hall with spare air capacity
Liquid-to-liquid CDU with cold platesChip heat to the facility water through the CDU’s exchangerFacility water supply and return to each CDU, TCS piping to each rackRows or pods of GPU racks at high density
Hybrid cold plate plus rear doorChip heat by cold plate, residual heat by rear coilBoth loops at the rackDense racks where residual air heat would overload the room
Immersion tanksNearly all heat, through dielectric fluidFloor loading for tanks, facility water, fluid handlingDedicated zones with structural capacity

Most Virginia Data Center Alley retrofits start with liquid-to-liquid CDUs serving a defined pod, because that concentrates the new piping in one zone, uses the facility water the building already has, and lets the rest of the hall keep running on air. Immersion is covered on the data center immersion cooling page; in older raised-floor halls the tank weight usually points toward slab-on-grade zones.

Piping a live hall: routes, joints and hot work

Piping a live data hall means installing new branches above or beside running servers without dust, heat, water or vibration reaching them. The method is as important as the material, and it is where a data center retrofit most often goes wrong.

  • Prefabrication: Paul fabricates welded stainless or carbon steel spools and manifold assemblies off the floor, cleans and pressure tests them, caps them and brings them in ready to bolt or couple, so cutting and welding inside the hall is minimized. See pipe fabrication.
  • Joining in place: grooved mechanical couplings or press fittings, where the specification allows them, avoid open flame and grinding dust in the white space; any field weld runs under a hot work permit with fire watch and smoke detection zones managed with the operator.
  • Isolation: every row branch gets isolation valves and a drain, so one pod can be worked on while its neighbors run.
  • Leak protection: drip trays under overhead valves and couplings, rope or spot leak detection under underfloor piping, and routing that keeps joints out of the space directly above rack tops wherever possible.
  • Supports: hangers anchored to structure rated for filled pipe, never to cable tray or ceiling grid.

Data center retrofitting in Virginia also runs into a scheduling reality: much of the work happens in the change windows tenants allow. Paul plans tie-ins to the existing chilled water mains for those windows, using hot taps or line stops where shutting a main is not acceptable, and stages the work so each window ends with the hall in a safe, documented state. Industrial welding in Virginia covers the weld procedures and records behind the spools.

Feeding the facility water side from a plant designed for air

The facility water side of a retrofit is usually the existing chilled water plant, and its operating temperature determines how the CDUs are controlled. Older Virginia plants built for perimeter air units often supply water in the low to mid 40s °F, far colder than liquid-cooled servers need. That is workable, but it brings two problems: wasted chiller energy, and condensation risk if any part of the technology loop runs below the room dew point.

Virginia’s humidity makes the second problem real. The Dulles weather record puts the 1% dehumidification design near a 73°F dew point outdoors, and a hall with weak humidity control can drift well above the 59°F dew point ceiling of the ASHRAE recommended envelope in summer. The CDU must hold the technology cooling loop above the room dew point at all times, which means its controls need a reliable room dew point signal and the hall’s humidity control has to be working before liquid racks go live.

Three facility water arrangements are common:

  • CDUs directly on existing chilled water: least new piping; the CDU’s exchanger and control valve set the technology loop temperature.
  • A blended or tempered loop: a mixing station or heat exchanger raises the water feeding the CDUs, which protects against condensation and lets the existing chillers see warmer return water.
  • A dedicated warm-water loop: new dry coolers or a separate heat exchanger to the condenser water serve the liquid load, so it can reject heat with little or no compressor energy for much of the year; the data center cooling in Virginia page covers how Virginia weather sets that split.

Whichever is chosen, the plant must have the capacity to absorb the new load, and its pumps the head to reach the new CDUs. Where the existing machines are tired, chiller repair in Virginia or replacement may belong in the same project.

Water quality and filtration in a retrofit loop

Water quality in a retrofit begins with keeping the old system’s debris out of the new one. A chilled water main that has run for ten years carries iron oxide, scale fragments and settled solids that would foul cold plate microchannels within weeks. The new technology cooling loop is therefore always a separate, clean circuit behind the CDU’s heat exchanger, and the new facility water branches are flushed on their own before they are opened to the main.

Inside the technology loop, Paul fills with the coolant the server and CDU specification requires, at the cleanliness and filtration rating it sets, and adds side-stream filtration where the specification calls for it. Stainless steel manifolds and spools are cleaned and, where specified, passivated to ASTM A967 or ASTM A380 before fill; passivation services in Virginia describes that work. The high-purity water filtration page covers filter housings and media used on these loops.

Phasing a retrofit in a Sterling, Virginia data center or an Ashburn hall

Phasing a liquid cooling retrofit means sequencing the work so the hall never loses cooling or redundancy for tenants already running. Each phase ends with every live system back in its normal state and a record of what changed.

Typical phase sequence for a liquid cooling retrofit in an operating hall
PhaseWorkWhat stays liveHold point
1. Survey and designSurvey, load and structural checks, architecture choice, method statementsEverythingOwner approval of design and methods
2. Enabling worksNew isolation valves, hot taps or line stops at tie-in points, electrical feedsAll cooling, with redundancy reduced only inside approved windowsTie-ins pressure tested and recorded
3. DistributionInstall prefabricated headers, branches, drip trays and leak detectionAll racks; work zones screened and dust controlledHydrostatic test of new piping
4. CDUs and rack manifoldsSet and connect CDUs, rack manifolds and hosesExisting rowsFlush and clean of new circuits to acceptance criteria
5. Fill and heat loadFill, vent, test controls, load banks or dummy loads on cold platesExisting rowsFunctional tests witnessed and signed
6. Server connectionRacks connected pod by podAir-cooled rows and remaining podsOperator acceptance of each pod

The same sequence applies whether the building is a Sterling, Virginia data center from the first wave of the Route 28 corridor or a newer shell in Prince William County. What changes from site to site is how much redundancy the existing plant has to give up during enabling works, which is why that phase is planned with the operator hour by hour.

What does data center liquid cooling cost in Virginia?

Data center liquid cooling cost in Virginia depends on how much heat moves to liquid, how far the new piping runs, what the existing chilled water plant can absorb and how tightly the work is constrained by live operations. In retrofits, labor windows and enabling works often cost as much as the equipment.

  • Architecture: rear-door coils on existing chilled water cost less per rack than cold plate systems with CDUs, and capture heat differently.
  • Distribution length and route: overhead headers with drip trays and leak detection cost more than open underfloor runs, but are often the workable route in a cable-filled floor.
  • Plant work: spare chiller capacity keeps cost down; a tempered loop, new dry coolers or chiller replacement adds to it.
  • Operating constraints: limited change windows, night work and redundancy restrictions stretch schedules.
  • Energy return: at 8.99 cents per kilowatt-hour, every kilowatt of fan and compressor power the retrofit removes is worth about $788 a year, plus the value of the IT capacity it frees.

Paul Industries gives a budget range from the survey and the target rack count, then a firm price once the architecture and routes are fixed.

Who installs data center liquid cooling in Virginia?

Paul Industries installs data center liquid cooling in Virginia, covering surveys, design-build delivery, prefabricated piping, CDU setting and connection, facility water tie-ins, flushing, fill, testing and service. Headquartered at 256 Shore Drive in Kilmarnock, Paul takes liquid cooling data center Northern Virginia projects in Loudoun, Prince William and Fairfax counties, plus work in Southside, Lynchburg, Roanoke, the Shenandoah Valley, Charlottesville, Hampton Roads, Henrico and Richmond, and across all 50 states.

  • Supply only: prefabricated manifolds, headers, pump and filtration skids, and valve assemblies delivered with test records.
  • Design-build: survey, architecture, drawings, methods and installation under one contract.
  • Complete installation: installing to the engineer of record’s design, from enabling works through server connection.

Campus-scale work, such as new central plants and site piping, is described on the data center mechanical contractor in Virginia page, and the wider Virginia picture is on the Virginia page.

Paul Industries on Virginia liquid cooling retrofits

Paul Industries turns air-cooled Virginia halls into liquid-ready ones: surveying what the building can carry, choosing rear-door, cold plate or hybrid architectures to fit, prefabricating and installing the piping around live equipment, tying it to the existing plant, and testing every circuit before a server is connected. Design, fabrication, supply, installation, testing, startup, service and maintenance of these systems all sit with Paul, for operators across the Commonwealth. To plan a retrofit, send the hall drawings, plant data and target rack density and request a quote, or call 201-450-8280.

Standards referenced: ASHRAE Thermal Guidelines for Data Processing Environments · ASHRAE TC 9.9 liquid cooling guidance · ASME B31.9 · ASTM A967 · ASTM A380 · 2021 Virginia Uniform Statewide Building Code · Virginia Mechanical Code

Frequently asked questions

Where is Data Center Alley?

Data Center Alley is in eastern Loudoun County, Virginia, centered on Ashburn and Sterling and running through the Route 28 corridor near Washington Dulles International Airport. Loudoun County counts about 245 existing data center buildings there and across the county. For liquid cooling, the area matters because it holds a large stock of air-cooled halls from the 2000s and 2010s that owners now want to densify for GPU workloads.

What is the Virginia Data Center Alley, and how did it start?

The name describes the cluster of data centers in Loudoun County that grew around Ashburn’s network connectivity. Virginia’s role started with MAE East, an early internet exchange set up in Vienna in 1992, and continued when AOL and other network companies moved to Ashburn in the 1990s. Fiber, available power, industrial land and a state sales tax exemption on data center equipment kept the cluster growing.

Can liquid cooling be added to an Ashburn Data Center Alley hall that is fully leased and running?

Retrofits in occupied Ashburn halls are planned around tenant change windows. Paul prefabricates piping off the floor, uses hot taps or line stops for tie-ins, screens work zones against dust and keeps redundancy inside approved limits. Each phase ends with the hall in a normal, documented state, and new circuits are pressure tested, flushed and proven with heat load before any server connects to them.

Does the Loudoun County special exception process apply to a cooling retrofit?

The special exception adopted in March 2025 governs new data center uses, not equipment upgrades inside an existing, permitted building. A cooling retrofit still needs mechanical and, where applicable, electrical permits and inspections from the county under the Virginia Uniform Statewide Building Code. Paul prepares the permit drawings and test records that the inspectors and the owner’s commissioning team require.

Is there a Loudoun County data center moratorium?

Loudoun County has said it lacks the legal authority to impose a moratorium on new data center applications. What it did instead, in March 2025, was end by-right approval, so new buildings now need a special exception with public hearings. For owners, that makes added density inside existing buildings comparatively easier to deliver, which is one reason liquid cooling retrofits are under study across the county.

Can our existing 44°F chilled water plant serve liquid-cooled racks?

Cold chilled water can feed a liquid-to-liquid CDU; the CDU’s heat exchanger and control valve raise the technology loop to the temperature the servers need. The risks are condensation if the loop ever drops below the room dew point, and wasted chiller energy. A tempering station or a dedicated warmer loop often solves both. Paul checks the plant’s spare tons, pump head and controls before recommending one.

How heavy are liquid-cooled racks compared with what an older raised floor was rated for?

Dense liquid-cooled racks carry more equipment, coolant and manifolds than the air-cooled racks older floors were designed around, so the floor and slab must be checked rack by rack. Raised floor pedestal ratings, stringers and tiles matter, as does the slab beneath. Paul includes structural checks in the survey and, where needed, routes dense pods to slab-on-grade areas or adds floor reinforcement.

Should new liquid cooling pipe run under the raised floor or overhead?

Both work. Underfloor routes keep joints below the equipment but compete with cable and airflow, and need leak detection along the runs. Overhead routes are easier to reach and inspect but need drip trays, careful joint placement and room above the racks. In many older Virginia halls the underfloor space is already full, which settles the question. Paul decides from the survey, not a default.

Who installs rear-door heat exchangers in Northern Virginia?

Paul Industries installs rear-door heat exchangers in Northern Virginia data centers, including the chilled water branches, isolation valves, hoses, condensation controls and leak detection each door needs. Rear doors suit owners who want higher density without changing servers. Paul surveys door clearances and chilled water capacity first, then installs and tests row by row while the rest of the hall runs. Call 201-450-8280 or request a quote.

Can Paul Industries handle a liquid cooling retrofit in Richmond or Henrico County?

Paul Industries takes liquid cooling retrofits in Richmond, Henrico, Chesterfield and across central Virginia, as well as in Hampton Roads and western Virginia. The process is the same as in Loudoun: survey, architecture choice, prefabricated piping, tie-ins in planned windows, flushing, fill and functional testing. Send the hall drawings, plant data and target rack density for a budget range.

How is water quality protected when a new loop connects to an old chilled water main?

The technology loop that reaches the cold plates is always a separate circuit behind the CDU’s heat exchanger, so old main water never touches the servers. New facility water branches are flushed on their own, with temporary strainers, before they are opened to the existing main, and strainers stay in place through early operation. The existing plant’s water treatment is reviewed so the CDU exchanger is not fouled by it.

Do CDU pumps need redundant power in a Virginia retrofit?

CDU pumps keep coolant moving through chips that can overheat in seconds without flow, so their power path should be as reliable as the servers’ own. Most designs feed CDUs from redundant sources, often UPS-backed, with automatic pump changeover. Paul Industries runs the CDU feeds and controls wiring as part of the mechanical package where the owner wants one contract, and tests the changeover during functional testing.

How long does a liquid cooling retrofit take in an operating hall?

Duration depends on pod size, routes and how often the operator can grant change windows. Survey and design come first, then enabling works such as valves and tie-ins, distribution, CDUs, flushing and functional testing, with each phase gated by an inspection or test. Equipment lead times for CDUs and rack manifolds often set the critical path, so Paul prefabricates piping while equipment is on order.

What does data center liquid cooling cost per rack in Virginia?

Per-rack cost varies with architecture, density, route length and the plant work needed, so Paul prices from the survey rather than a flat rate. Rear-door coils on existing chilled water are usually the lower-cost entry; cold plate pods with CDUs cost more and capture more heat. Operating savings help: each kilowatt of fan or compressor power removed is worth about $788 a year at Virginia’s 2024 industrial average rate.

Can a retrofit reuse the existing CRAH units in the hall?

Existing CRAH units usually stay to carry the residual air-side heat from liquid-cooled racks, plus the load of racks that remain air cooled. With less heat to remove, they can often run at lower fan speeds or warmer supply air, saving energy. Some units may be removed to free floor space for CDUs. Paul reviews airflow, containment and controls so the air and liquid systems work together.

What records does the owner receive after a liquid cooling retrofit?

Paul hands over as-built drawings of new piping and valves, pressure test records, flushing and cleanliness results, fill and coolant records, functional test results for CDUs and leak detection, valve tag lists, and operation and maintenance information. Those records support equipment warranties and the operator’s maintenance program, and they let the next phase of the retrofit start from known conditions.

Is direct to chip cooling in Virginia different from anywhere else?

The cold plate technology is the same everywhere; Virginia changes the surroundings. Humid summers make room dew point control critical, older Loudoun halls constrain routes and floor loading, and the grid makes freed power especially valuable. The heat rejection side can use cool Virginia winters for free cooling when the loop runs warm. Paul designs direct to chip cooling in Virginia around those site conditions.

What is a data center retrofit, and when does liquid cooling justify one?

A data center retrofit upgrades the cooling, power or structure of an operating building to support a new load, instead of building a new one. Liquid cooling justifies a retrofit when the owner needs rack densities that air cannot cool, the building already has utility capacity, and new construction would face zoning review or power delays, as it now can in Loudoun County. Paul scopes the retrofit from a site survey.

Densifying an air-cooled hall in Virginia?

Send hall drawings, chilled water plant data, the target rack density and the number of racks to convert, and Paul Industries will scope the retrofit. Call 201-450-8280 or request a quote.