Paul Industries carries out data center commissioning in South Carolina for cooling plants and liquid loops: hydrostatic testing, flushing, fill, equipment startup, functional testing and integrated systems testing, with records that satisfy county building officials, state boiler and air rules, and the owner’s commissioning agent. South Carolina sits between two code editions, keeps an older energy code by statute and treats boilers and pressure vessels differently from its neighbors, so the paperwork side of commissioning here has its own shape. Paul Industries, headquartered at 256 Shore Drive, Kilmarnock, Virginia, takes commissioning work across South Carolina on new halls, phased campuses and operating buildings.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Codes now 2021 SC Mechanical Code, in force since January 1, 2023
Next codes 2024 editions take effect January 1, 2027 (SC Building Codes Council)
Code pressure test Hydronic piping at 1.5 times design pressure and no less than 100 psi, held 15 minutes or more
Pressure vessels Exempt from the SC Boiler Safety Act, S.C. Code 41-14-60(C)
Reviewed November 2026

Where does data center commissioning in South Carolina sit between permit and turnover?

Data center commissioning in South Carolina runs alongside the county or municipal permit from rough-in through the certificate of occupancy, and then continues past it through integrated testing and turnover to the operator. The building official inspects to the state’s mandatory codes, which every South Carolina county and municipality must enforce, while the commissioning program proves that the cooling, power and controls perform as the owner’s project requirements demand. The two overlap at the pressure test, the final mechanical inspection and the life safety tests, and they diverge everywhere else.

That split explains much of how a South Carolina commissioning schedule works. Inspectors witness or accept records for code items such as hydronic pressure tests, and they sign off on the work they inspect. The owner’s commissioning program goes further: it asks whether a chiller holds its leaving water temperature at design load, whether a CDU fails over without a temperature excursion, and whether the whole plant rides through a utility outage. Paul Industries runs the mechanical side of both tracks, so test records serve the inspector and the commissioning agent from the same documents.

Which South Carolina building codes apply to a data center cooling plant in 2026 and 2027?

South Carolina building codes for data center work currently are the 2021 editions of the International Building, Fire, Plumbing, Mechanical and Fuel Gas Codes with South Carolina modifications, the 2020 National Electrical Code and the 2009 International Energy Conservation Code, all in force since January 1, 2023. On August 26, 2025 the South Carolina Building Codes Council, part of the Department of Labor, Licensing and Regulation, adopted the 2024 editions and the 2023 National Electrical Code with an implementation date of January 1, 2027. Projects permitted on either side of that date can end up on different code editions within the same campus.

South Carolina rules that reach data center commissioning work
RuleWhat it coversWhere it shows up in commissioning
2021 South Carolina Mechanical Code (2021 IMC with SC modifications)Hydronic piping, pressure vessels, equipment installationSection 1208.1 hydrostatic test; Section 1003.1 ASME construction for pressure vessels
2024 South Carolina codes, effective January 1, 2027Next edition of the building, mechanical, plumbing, fire and fuel gas codes, with the 2023 NECCode basis for phases permitted from 2027; check which edition each permit carries
2009 IECC through the Energy Standard ActBuilding energy efficiency, set by statuteBalancing and controls requirements of that edition; commissioning scope beyond it comes from the owner’s specification
Boiler Safety Act, S.C. Code Title 41 Chapter 14Boilers, with pressure vessels and several boiler types exemptInspection evidence for any heating boiler on site; ASME and National Board records for new boilers
SC DES Regulation 61-62.1, Section IIAir permit exemptions for emergency generatorsHour meters and run-hour logs for generator testing during integrated tests
S.C. Code Title 40 Chapter 11Contractor licensing for work over $10,000Mechanical work performed under the matching subclassification, such as Air Conditioning or Pressure and Process Piping

What South Carolina’s 2009 energy code means for commissioning

South Carolina’s energy code is the 2009 International Energy Conservation Code, adopted by statute through the Energy Standard Act rather than by the Building Codes Council’s regular cycle, and it predates the formal commissioning section, C408, that IECC editions carry from 2012 onward. In practice that means state law asks less of a commissioning program here than the energy codes in some neighboring states do, and the depth of data center commissioning in South Carolina is set mostly by the owner’s project requirements, the insurer and the commissioning agent’s specification.

Owners building in South Carolina rarely commission less because of it. Hyperscale and colocation operators bring their own commissioning levels, test scripts and acceptance criteria to every state, and lenders, insurers and tenants expect the same evidence. What the older energy code changes is the source of the requirement: the specification, not the permit, drives functional and integrated testing, so the specification has to be complete. Paul Industries reviews the commissioning sections of the specification at bid time and flags gaps in test scope, acceptance criteria or responsibility before work starts.

South Carolina Boiler Safety Act: which data center equipment it reaches

The South Carolina Boiler Safety Act, codified at Title 41, Chapter 14 of the state code, applies to boilers and expressly exempts all pressure vessels, so the chilled water expansion tanks, air and dirt separators, buffer tanks and CDU expansion vessels on a data center cooling plant fall outside the state inspection program. Boilers that do fall under the Act, such as a hot water heating boiler serving offices or a power boiler, need periodic inspection by a special inspector, with evidence of inspection filed with LLR.

Exemption from the state Act leaves construction rules in place. The 2021 South Carolina Mechanical Code requires pressure vessels to be constructed to the ASME Boiler and Pressure Vessel Code unless otherwise approved, and owners and insurers commonly expect National Board registration and manufacturer’s data reports in the turnover file. Paul Industries checks nameplates and data reports for every vessel during installation verification, so the commissioning record shows the vessel’s code of construction, rated pressure and relief valve setting next to the system it protects.

Data center plant equipment and the South Carolina rule that reaches it
EquipmentBoiler Safety Act statusWhat commissioning records
Chilled water expansion tanks and air separatorsPressure vessels, exempt under 41-14-60(C)ASME nameplate, data report, relief valve setting, precharge pressure
Buffer tanks and thermal storage vesselsPressure vessels where pressurized, exemptConstruction code, rated pressure, stratification or volume test where specified
CDU expansion vessels and accumulatorsPressure vessels, exemptPrecharge, relief setting, CDU maker’s startup checklist
Hot water heating boiler for offices or freeze protectionCovered; inspected every two years by a special inspectorNational Board registration, inspection evidence filed with LLR, burner startup report
Small hot water supply heatersExempt within 200,000 Btu/h, 210 F and 120 gallonsInstallation and relief valve checks under the plumbing and mechanical codes
Hydronic pipingOutside the ActSection 1208.1 hydrostatic test record, flushing and chemistry logs

Pressure testing hydronic loops to the South Carolina Mechanical Code

The South Carolina Mechanical Code requires hydronic piping to be tested hydrostatically at one and one-half times its maximum system design pressure, but at no less than 100 psi, for at least 15 minutes, and that test is the first commissioning milestone most building officials care about. On a data center cooling loop with a 125 psi design pressure, the code test is about 188 psi; on a low-pressure loop designed for 50 psi, the 100 psi floor governs. Equipment that cannot take the test pressure, such as some CDUs, coils and cold plate manifolds, is isolated and tested to its own rating.

Paul Industries writes a test plan for each loop that lists test boundaries, isolation points, gauge ranges and calibration, hold time and acceptance criteria, then records the test with gauge serial numbers and photographs. Owner specifications often ask for longer holds than the code minimum, and some liquid cooling specifications add a nitrogen or helium leak check on rack manifolds. A failed test is found, repaired and repeated before insulation goes on, because every hour of insulation removal costs more than the retest.

The data center commissioning process, step by step, on a South Carolina job

The data center commissioning process on a South Carolina job follows the five commissioning levels widely used on data center projects: factory witness testing, delivery and installation verification, startup and pre-functional checks, functional performance testing, and integrated systems testing, with the state’s inspections and records folded into levels two and three. Those are the data center commissioning steps; the order is fixed, and each level depends on the one before it.

At level one, Paul Industries attends factory tests for chillers, CDUs, pump skids and switchgear where the owner requires it. Level two covers receipt, setting and installation checks, including vessel nameplates and the hydronic pressure test. Level three is flushing, fill, water treatment, rotation checks, pump and fan startup, and the manufacturer’s startup for each machine. Level four proves each system against its sequence of operations: staging, failover, setpoint control and alarms. Level five runs the whole facility together, usually with load banks, through utility failure, generator start, transfer and recovery. The national data center commissioning page explains each level in more depth.

A sound data center commissioning plan, usually led by the data center commissioning agent and written at design development, names who performs, witnesses and signs each test, and Paul Industries contributes the mechanical scripts, test equipment list and record formats to that plan so that nothing waits on paperwork when the field is ready. The plan also sets the data center commissioning schedule, which on a phased campus repeats for each hall while earlier halls run live.

Seasonal test windows: South Carolina heat, humidity and freezing nights

Seasonal test windows matter in South Carolina because cooling tower and dry cooler capacity can only be proven near design conditions in mid-summer, while flushing and filling an unheated shell in winter risks freezing, and the two windows differ sharply between Charleston and the Upstate. To set realistic test calendars, Paul Industries tallied 2021 to 2024 hourly readings taken by the National Weather Service at Charleston, Columbia and Greenville-Spartanburg.

Average hours per month suited to tower capacity tests (wet bulb at or above 75 F) and hours at or below freezing, 2021 to 2024 (Paul Industries calculation)
MonthCharleston: high wet bulb / freezingColumbia: high wet bulb / freezingGreenville-Spartanburg: high wet bulb / freezing
June143 / 081 / 014 / 0
July457 / 0350 / 077 / 0
August421 / 0278 / 045 / 0
September108 / 045 / 03 / 0
December0 / 320 / 780 / 91
January0 / 340 / 810 / 120
February0 / 40 / 300 / 52

The pattern gives three practical rules. A Lowcountry tower can be tested close to its 80 F design wet bulb in July or August with good odds. An Upstate tower designed for about 76 F sees few hours near that point even in July, so its capacity test usually runs at lower wet bulb with results corrected to design using the manufacturer’s performance curves, or is deferred to a hot spell and repeated. Winter flushing in Greenville, Spartanburg or Columbia needs temporary heat, glycol fill or drain-down plans, because January brings over 80 hours below freezing at both airports.

Generators, SC DES air rules and integrated systems testing

Integrated systems testing on a South Carolina data center runs the emergency generators under load, and those run hours count under the state’s air rules: an emergency engine above 150 kW is exempt from a construction permit only when it is designated for emergency use and limited to 500 hours a year for testing and maintenance, with a way to record hours such as a non-resettable hour meter. The South Carolina Department of Environmental Services, which took over DHEC’s environmental programs on July 1, 2024, administers those rules, and federal engine standards apply as well.

Commissioning load bank runs, utility failure tests and retests all add hours, so the commissioning agent and the owner’s environmental lead should track them per engine from the first start. Paul Industries logs generator run time alongside the cooling plant data during integrated tests, so the record shows both how the chillers, pumps and CDUs recovered after transfer and how many hours each engine ran to prove it. Cooling recovery is usually the critical result: chillers restart on a timed sequence after power returns, and the chilled water or facility water loop has to hold the hall within limits during that gap, often with help from thermal storage or pumps on UPS power.

Data center commissioning checklist for a South Carolina turnover

A data center commissioning checklist for a South Carolina turnover gathers the records that the building official, the state, the insurer and the operator each need, and it is easiest to assemble when every test produces its record in a fixed format from the start. Paul Industries hands over the mechanical portion as a single indexed file. A typical set includes:

  • Hydrostatic test reports for every loop and section, with test pressure, hold time, gauge serials and witness signatures
  • Flushing logs, strainer inspections, water sample results and chemical cleaning and passivation records
  • Fill records with fluid type, glycol concentration and volume, and water treatment startup readings
  • Pressure vessel nameplates, manufacturer’s data reports and relief valve settings
  • Boiler inspection evidence and National Board registration for any covered boiler
  • Equipment startup reports, vibration and alignment readings, and motor rotation checks
  • Functional test scripts with results, the issues log and closure evidence
  • Integrated test trends for chilled water, facility water and hall temperatures, with generator run hours
  • As-built drawings, valve tag charts and operation and maintenance manuals

Licensing, wages and contract terms behind a South Carolina commissioning scope

South Carolina contractor law requires mechanical work costing more than $10,000 to be carried out under a mechanical contractor license in the matching subclassification, such as Air Conditioning, Heating, Refrigeration or Pressure and Process Piping, and the state has no prevailing wage law of its own, with federal Davis-Bacon rates applying only on federally funded work. Both facts affect how commissioning is bought. Flushing, testing and startup are mechanical work, so owners typically place them in the mechanical package rather than in a separate testing contract, and labor pricing follows the market rather than a state wage schedule.

Paul Industries prices commissioning support as part of the mechanical scope or as a stand-alone testing scope on an existing building, with the deliverables listed line by line: test plans, temporary pumps and strainers, chemicals, load banks where included, technician days for functional and integrated testing, and the record set.

Data center construction in South Carolina and where commissioning fits

Data center construction in South Carolina is concentrated in phased campuses, so commissioning becomes a repeating cycle rather than a single event at the end of the project. Google’s announcements show the scale: $3.3 billion in September 2024 for Berkeley and Dorchester counties, with sites in Ridgeville and St. George, and a further $9 billion in October 2025 for the Berkeley expansion and the two Dorchester campuses. On a phased campus, each new hall is flushed, tested and commissioned while earlier halls run at full load on shared plant, which raises the stakes on every tie-in.

Paul Industries plans phased commissioning with isolation built in from the first phase: valved and capped connections for future halls, separate flushing loops so new pipe never sends debris into live systems, and integrated tests scripted so that a new hall’s failover test cannot trip the plant serving its neighbors. The same discipline applies to enterprise rooms in the Upstate and the Midlands that add liquid cooling or a new chiller while staying online.

What does data center commissioning in South Carolina cost?

The cost of data center commissioning in South Carolina depends on the commissioning levels in scope, the number of systems and test scripts, the size and number of loops to flush and fill, load bank capacity and duration, the number of phases and whether the work happens in an operating building. Paul Industries prices each scope from the specification and gives a budget range from comparable work once the systems are known, then a firm price.

Energy is a smaller line than many owners expect at South Carolina rates. A 24-hour heat run on a 20 MW hall uses about 480 MWh, roughly $32,800 at the state’s 2024 industrial average of 6.84 cents per kWh, while an 8-hour run of a 2 MW load bank uses about 16 MWh, under $1,100. Load bank rental, cabling, labor and schedule usually outweigh the electricity.

Who handles flushing, testing and data center commissioning in South Carolina?

Paul Industries handles flushing, pressure testing, fill, startup and functional and integrated testing for data center commissioning in South Carolina, on cooling plants, facility water and liquid cooling loops, from factory witness tests to turnover. Paul Industries works to the commissioning agent’s plan and scripts where one is in place, and it writes the mechanical test plans and scripts on projects that need them, supplying temporary pumps, strainers, chemicals and test equipment. Its data center commissioning services also cover recommissioning of operating halls after upgrades and the recovery of incomplete records on existing installations.

Owners can buy commissioning as part of a complete installation, under a design-build contract, or as a testing scope on its own. Related South Carolina pages cover data center cooling in South Carolina, data center liquid cooling in South Carolina, data center mechanical contractors in South Carolina and validation and commissioning in South Carolina for regulated life science plants, and the boiler repair in South Carolina page covers boilers under the Boiler Safety Act.

Formerly based in northern New Jersey and then Pennsylvania, Paul Industries now has its headquarters in Kilmarnock, Virginia, and works as an East Coast contractor. It commissions data centers in Virginia, its headquarters state, and data center commissioning in North Carolina and Georgia, and it brings the same records and methods to South Carolina and every other state along the East Coast.

Paul Industries commissioning for South Carolina data halls

Paul Industries tests, flushes, fills, starts up and commissions data center cooling plants and liquid loops across South Carolina, from Berkeley and Dorchester County campuses to Columbia and Upstate enterprise rooms, with test records built for the building official, the insurer and the operator. Send the specification or commissioning plan, the system list, the phasing and the target dates, and Paul Industries will set out the mechanical test scope and a budget range. For the wider list of systems Paul Industries builds in the state, see the South Carolina page; to start, request a quote.

Standards referenced: 2021 South Carolina Mechanical Code (2021 IMC with SC modifications), Sections 1003.1 and 1208.1 · 2024 South Carolina building codes (implementation January 1, 2027) · 2009 International Energy Conservation Code (South Carolina Energy Standard Act) · South Carolina Boiler Safety Act, S.C. Code Title 41 Chapter 14 · SC DES Regulation 61-62.1, Section II (air permit exemptions) · S.C. Code Title 40 Chapter 11 (contractor licensing) · ASME Boiler and Pressure Vessel Code, Section VIII · ASME B31.9 · ASHRAE Guideline 0 · ASHRAE Standard 202 · NFPA 110

Frequently asked questions

Who commissions data center cooling plants in Berkeley County and around Charleston?

Paul Industries flushes, pressure tests, fills, starts up and functionally tests cooling plants and liquid loops for data halls in Berkeley, Dorchester and Charleston counties. Coastal plants suit tower capacity testing in July and August, when Charleston averages over 400 hours a month at or above 75 F wet bulb. Call 201-450-8280 or request a quote with the specification and phasing.

Does Paul Industries provide data center commissioning in Greenville, SC and Spartanburg?

Paul Industries provides data center commissioning Greenville SC and Spartanburg owners need for new rooms, chiller additions and liquid cooling refits, from hydrostatic tests to integrated testing. Upstate schedules have to plan for winter: Greenville-Spartanburg averages about 120 hours at or below freezing in January, so flushing in an unheated space needs temporary heat, glycol or a drain-down plan.

Can Paul Industries test and start cooling loops for halls in Columbia, Rock Hill or Aiken?

Paul Industries tests, flushes and starts cooling loops for data halls in Columbia and the Midlands, Rock Hill and York County, and Aiken and the Savannah River area. Each county or municipality enforces the state’s mandatory codes and sets its own inspection procedures, so the test plan lists which tests the inspector witnesses and which records the permit file needs.

Which South Carolina building code edition will a data center permitted in 2027 use?

The South Carolina Building Codes Council adopted the 2024 editions of the building, mechanical, plumbing, fire and fuel gas codes, with the 2023 National Electrical Code, for implementation on January 1, 2027. Permits issued before then generally stay on the 2021 editions. A phased campus can therefore carry two code editions, and commissioning records should state which edition applied to each phase.

Does South Carolina law require a commissioning agent on a data center?

South Carolina’s energy code is the 2009 IECC, which predates the C408 commissioning section of later editions, so the requirement for a commissioning agent normally comes from the owner, the lender or the insurer rather than the permit. Data center owners commonly appoint one regardless. Paul Industries works under the agent’s plan or prepares mechanical test plans where the owner has none.

Are expansion tanks and air separators covered by the South Carolina Boiler Safety Act?

The Act exempts all pressure vessels, so expansion tanks, air separators and buffer tanks on a cooling plant fall outside the state’s boiler inspection program. The 2021 South Carolina Mechanical Code still requires pressure vessels to be built to the ASME code unless otherwise approved, and insurers usually want data reports and relief valve records, which Paul Industries collects during installation verification.

Who keeps the inspection evidence for a heating boiler at a South Carolina data center?

The owner or operator files evidence of each inspection with the Department of Labor, Licensing and Regulation, either an insurer’s certificate or a special inspector’s report. Hot water heating boilers covered by the Act are inspected every two years and power boilers every year. Paul Industries adds the boiler’s National Board registration and startup report to the commissioning file so the first inspection has what it needs.

Do generator load tests during commissioning affect a South Carolina air permit exemption?

They count toward it. An emergency engine above 150 kW keeps its construction permit exemption only when it is designated for emergency use and limited to 500 hours a year for testing and maintenance, with recorded hours. Commissioning runs, retests and load bank work all add hours, so Paul Industries logs run time per engine during integrated testing.

What is commissioning a data center supposed to prove?

Commissioning proves that the installed cooling, power and controls meet the owner’s project requirements under real operating conditions, including failures. Inspections confirm code compliance; commissioning confirms performance: that chillers hold setpoint at load, that redundant equipment takes over without a temperature excursion, and that the facility recovers after a utility outage. Records from each test become the operator’s baseline.

How to commission a data center hall that is already running after adding liquid cooling?

Recommissioning an operating hall follows the same levels on a smaller footprint: pressure test and flush the new loop while isolated, fill and start the CDUs, then run functional tests on the new equipment and its interaction with the existing plant. Integrated testing is scripted so failover tests on the new loop cannot disturb live racks. Paul Industries plans each test around the operator’s change windows.

Which data center commissioning standards apply in South Carolina?

The common references are ASHRAE Guideline 0 and ASHRAE Standard 202 for the commissioning process, the owner’s commissioning level definitions, ASME B31.9 and the 2021 South Carolina Mechanical Code for piping tests, ASME Section VIII for pressure vessels and NFPA 110 for emergency power testing. Paul Industries aligns its mechanical test records to whichever set the specification names.

Can a Lowcountry cooling tower be capacity tested outside of summer?

It can be tested at lower wet bulb and corrected to design using the manufacturer’s performance curves, but the most convincing results come near design. Charleston averages about 457 hours at or above 75 F wet bulb in July and 421 in August, against almost none from October to April. Many owners accept a corrected autumn test with a summer retest in the following year.

How should cooling loops be flushed in an unheated Upstate shell during winter?

Flushing in a cold shell needs a plan for freezing nights: temporary heat in the building, a glycol solution for the flush and fill where the specification allows it, or a drain-down procedure after each day’s work. Greenville-Spartanburg averages about 91 hours at or below 32 F in December and 120 in January. Paul Industries sets the method with the owner before water goes into the pipe.

Does South Carolina's lack of a state prevailing wage law change commissioning bids?

Commissioning labor on privately funded South Carolina data centers is priced at market rates rather than a state wage schedule, which keeps the pricing basis simple. Federally funded projects still follow Davis-Bacon rates. The larger price drivers remain the number of systems, test levels, phases and load bank hours in the scope.

Can Paul Industries recommission an existing South Carolina data hall and rebuild missing records?

Yes. Paul Industries surveys the installed systems, verifies nameplates and vessel data, retests where records are missing or doubtful, and runs functional tests against the current sequences of operation. The result is a record set that reflects the hall as it actually operates, which helps with insurer reviews, tenant audits and the next expansion.

Does a South Carolina building inspector witness the hydronic pressure test?

Practice varies by jurisdiction, since each county or municipality sets its own inspection procedures under the state’s mandatory codes. Some inspectors witness the test, while others accept a signed record. Paul Industries confirms the arrangement with the building department before testing, so the record meets the inspector’s requirements on the first attempt.

What should a South Carolina owner send to scope commissioning work?

Send the specification or commissioning plan, the mechanical drawings and system list, the commissioning levels required, the phasing and target dates, and whether load banks are in the scope. For an operating hall, add change window rules and existing records. Paul Industries returns a mechanical test scope and budget range. Call 201-450-8280 or request a quote.

Commissioning a data center cooling plant in South Carolina?

Send the specification or commissioning plan, the system list, the commissioning levels and the target dates. Call 201-450-8280 or request a quote.