Paul Industries performs data center commissioning in Arkansas for the mechanical systems behind the white space: flushing and pressure testing cooling loops, starting chillers, pumps, dry coolers and coolant distribution units, checking out controls, and running the functional and integrated systems tests that show a hall holds temperature through a failure. An Arkansas data hall is permitted under the 2021 Arkansas Fire Prevention Code, built to the 2021 International Mechanical Code, and checked against an energy code that still rests on the 2009 IECC, so most of the test depth comes from the owner’s requirements rather than from state law. Paul Industries, an East Coast contractor based at 256 Shore Drive, Kilmarnock, Virginia, commissions projects across Arkansas, throughout the United States and at plants abroad.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Building code 2021 Arkansas Fire Prevention Code, administered by the State Fire Marshal
Energy code 2014 Arkansas Energy Code: 2009 IECC and ASHRAE 90.1-2007, in force since 2015
Generator testing Emergency engines: up to 100 hours a year for maintenance and readiness (40 CFR 60.4211)
Summer test window 753 hourly normals at or above 85 F in Little Rock; 331 in Fayetteville (NOAA)
Reviewed November 2026

What is data center commissioning, and what does Arkansas add to it?

Data center commissioning is the documented process of proving that every system in a data hall was designed, installed and started to meet the owner’s requirements, and that the systems work together when something fails. For the mechanical side, that means the chilled water or facility water plant, heat rejection, air handlers, liquid cooling loops, controls, and the generator support for all of them. The national outline of the process is on the data center commissioning page.

What Arkansas adds is a specific set of approvals, a grid split between two operators, and a climate that decides when a full-load test can be meaningful. The State Fire Marshal’s code governs building and fire safety; the state’s mechanical program governs mechanical work; the Division of Environmental Quality issues the air permits that govern generator operation; and Entergy Arkansas or another utility decides when the hall can draw full power. Paul Industries builds the commissioning schedule around those approvals as well as around equipment deliveries.

What are the 5 levels of data center commissioning on an Arkansas project?

The 5 levels of data center commissioning are a widely used sequence that moves from factory testing to a whole-building failure test: level 1 factory witness tests, level 2 delivery inspection and installation verification, level 3 equipment startup, level 4 functional performance tests of each system, and level 5 integrated systems testing. The levels of data center commissioning are an industry convention rather than an Arkansas rule, and owners often adjust them in their own data center commissioning plan.

Data center commissioning levels on an Arkansas mechanical scope
LevelMechanical workArkansas point to plan forRecord produced
Level 1: factory witnessChiller, CDU, pump skid and air handler performance tests at the factoryWitness dates set early, since equipment lead times often control the Arkansas scheduleFactory test reports signed by the witness
Level 2: delivery and installationReceipt inspection, setting, piping, supports, insulation, labelingVapor-sealed insulation checked on all cold piping in humid south and east ArkansasInstallation checklists and pressure test records
Level 3: startupFlushing, fill, pump rotation, chiller and dry cooler startup, controls point checkoutFreeze protection in place before winter startups in the OzarksStartup reports and point-to-point logs
Level 4: functional testsEach system tested through its sequences, alarms and failure modesEconomizer changeover tested at real outdoor conditions where the season allowsFunctional test scripts with results
Level 5: integrated systems testWhole hall under load bank heat with utility loss, generator start and transfersGenerator run hours counted against the permit and federal limits; utility energization timingIntegrated test report and trend data

Data center commissioning levels give the owner a common language, but the value lies in the scripts behind each level. Paul Industries writes those scripts from the sequence of operations, runs them with the controls contractor’s points live, and records every deviation and its correction.

The data center commissioning process from first submittal to turnover

The data center commissioning process on an Arkansas project starts before construction, when the owner’s project requirements and the basis of design are written, and ends after the hall is handed over, when deferred seasonal tests are complete. Between those points, the commissioning plan names who tests what, in which order and with what acceptance criteria.

The data center commissioning steps Paul Industries carries on the mechanical side run in a fixed order. Submittals are reviewed for testability, so test ports, isolation valves and flow meters appear where the scripts will need them. Piping is pressure tested section by section before insulation, flushed until the water runs clean and particle counts meet the specification, and filled with the treated water or glycol the design calls for. Equipment is started with the manufacturer’s procedure. Controls are checked point by point. Only then do functional and integrated tests begin.

A data center commissioning checklist for an Arkansas hall also carries items specific to the state. Insulation and vapor barriers on chilled water piping are inspected before ceilings close, because Little Rock alone averages about 925 hours a year with a dew point at or above 70 degrees. Freeze protection on outdoor coils and tower basins is proven before the first cold night in the north. Generator run time for testing is logged so the facility stays inside its air permit. Pressure tests on hydronic piping follow the mechanical code and the jurisdiction’s inspector.

Arkansas codes and approvals that shape the test plan

Arkansas codes shape the test plan through four separate programs. The 2021 Arkansas Fire Prevention Code, which combines the 2021 International Fire, Building and Residential codes with state amendments, is administered by the State Fire Marshal; mechanical work follows the 2021 International Mechanical Code through the state’s mechanical program at the Department of Labor and Licensing; plumbing and makeup water connections follow the 2018 Arkansas Plumbing Code from the Department of Health; and electrical work follows the 2020 Arkansas National Electrical Code.

Arkansas approvals that touch mechanical commissioning of a data hall
ProgramCurrent basisWhere it enters commissioning
Building and fire2021 Arkansas Fire Prevention Code, State Fire MarshalFire protection interfaces, smoke control, emergency shutdowns tested with the cooling plant
Mechanical2021 International Mechanical Code, Department of Labor and LicensingHydronic pressure tests, refrigerant safety, equipment access and ventilation
Plumbing2018 Arkansas Plumbing Code, Department of HealthMakeup water, backflow prevention, drains from towers and CDUs
Energy2014 Arkansas Energy Code, based on the 2009 IECC and ASHRAE 90.1-2007Controls, economizer and system balancing requirements of that edition
AirAPC&EC Rules 18, 19 and 26, Division of Environmental QualityGenerator permits and the run hours used for load testing
HVACR workArkansas Code Title 17, Chapter 33License classes required of individuals who install, start and service HVACR systems

The energy code deserves a closer look. Arkansas’s commercial energy code is still the 2014 Arkansas Energy Code, based on the 2009 IECC and ASHRAE 90.1-2007 and in force statewide since January 1, 2015. That edition predates ASHRAE 90.4, the energy standard written for data centers, so on an Arkansas hall the data center commissioning requirements come mostly from the owner’s project requirements, the insurer and the tenant’s lease. Paul Industries reads those documents first and builds the test plan to satisfy all of them in one sequence, rather than repeating tests for each audience.

Pressure testing, flushing and cleaning Arkansas cooling loops

Pressure testing, flushing and cleaning are the parts of data center mechanical commissioning that decide whether a cooling loop stays healthy for decades, because debris left in a new loop ends up in strainers, control valves, heat exchanger plates and, on liquid-cooled halls, cold plates. Paul Industries tests each piping section hydrostatically at the pressure set by the mechanical code and the project specification, holds it for the required time with the joints exposed, and records the gauge, pressure, duration and witness on a section-by-section certificate.

Flushing follows. Temporary bypasses take the flush around chillers, CDUs and coils so construction debris stays out of the equipment, and the loop runs at velocities high enough to lift weld slag and mill scale. Chemical cleaning removes oils and light rust, after which the loop is drained, refilled and treated. Paul Industries samples the water for turbidity, iron and particle counts until the results meet the specification, then installs the permanent strainers and records the final chemistry. Stainless loops that call for passivation get it at this stage, and makeup water connections are tested for backflow protection under the plumbing code. Further detail on testing methods sits on the hydrostatic testing page.

Data center commissioning checklist for Arkansas mechanical systems

A data center commissioning checklist for Arkansas mechanical systems lists every component and the test that proves it, with an acceptance figure and a place to record the result. The table below shows how Paul Industries structures the mechanical part of that checklist on an Arkansas hall.

Mechanical commissioning checklist items for an Arkansas data hall
SystemKey testsAcceptance basisArkansas note
ChillersStartup, capacity at load, staging, restart after power lossManufacturer data and design capacityPeak capacity proven in summer or deferred to the first summer
Cooling towers or fluid coolersFan staging, basin level, water treatment, approach at loadDesign approach and flowBasin heaters and freeze sequences proven in the north before winter
Dry coolersFan staging, glycol strength, freeze protection, capacityDesign leaving water temperatureGlycol checked against the site’s design low
PumpsRotation, flow, differential pressure, lead-lag and failoverPump curves and design flowRide-through tested on generator transfer
Air handlers and fan wallsAirflow, coil capacity, humidity control, filter pressureASHRAE inlet range and design airflowDehumidification proven on humid days in the south and east
CDUs and liquid loopsFlushing, chemistry, leak detection, failover under heat loadServer vendor limitsSupply kept above the room dew point
ControlsPoint checkout, sequences, alarms, trends, economizer changeoverSequence of operationsChangeover tested at real outdoor conditions in the shoulder months

Each line expands into its own script. A chiller script, for example, runs from pre-start checks through staging, load tracking, safeties and restart after power loss, with the trend data attached. The cooling plant equipment and design behind these tests is covered on the data center mechanical contractor in Arkansas page.

Generator testing, air permits and the 100-hour limit

Generator testing during Arkansas data center commissioning runs inside two limits: the facility’s air permit from the Division of Environmental Quality, issued under the Arkansas Pollution Control and Ecology Commission’s air rules, and the federal rule for emergency engines, which allows up to 100 hours a year of operation for maintenance checks and readiness testing. Integrated tests that start every generator, transfer the load and hold it for an hour or more use those hours quickly on a large campus.

Paul Industries plans the level 5 script so each generator run tests as many sequences as possible: utility loss, generator start, chiller restart, pump and CDU ride-through, and return to utility, all recorded on the same run. Load banks supply heat to the hall instead of servers, so the cooling plant is tested at design load while the generators carry it. Act 548 of 2025, which amended the state’s data center sales tax exemption, lists testing equipment and backup generators among data center equipment, which matters to owners tracking the costs of the test program.

Weather windows for Arkansas cooling plant tests

Weather windows matter for Arkansas cooling plant tests because a chiller plant tested on a mild day proves little about a July afternoon. NOAA’s 1991 to 2020 hourly normals count about 753 hours a year at or above 85 degrees Fahrenheit in Little Rock, 765 in Fort Smith and about 816 in El Dorado and Texarkana, nearly all of them between June and September; Fayetteville sees about 331.

When turnover falls in winter or spring, Paul Industries runs the plant at full load with load banks and simulated condenser conditions where the design allows, and writes a deferred seasonal test into the commissioning plan for the first summer: tower performance at peak wet bulb, chiller lift at peak condenser water temperature, and dehumidification on the most humid days. The reverse applies to economizer changeover and freeze protection, which are proven in the first cold season; Little Rock averages about 2,370 hourly normals at or below 50 degrees, and Fayetteville about 3,440.

Proving economizer changeover in the Arkansas shoulder months

Economizer changeover is the sequence most often left unproven at turnover, because it only runs when outdoor conditions cross the switch points, and in Arkansas those crossings cluster in March, April, October and November. Paul Industries tests changeover twice: once by forcing the sequence with simulated sensor values during functional testing, and again at real outdoor conditions in the first shoulder season, watching chilled water temperature, valve positions and chiller staging through the transition. A plant that hunts between modes on a mild humid morning wastes energy and wears valves, so the second test often leads to setpoint and deadband adjustments that the operators keep for the life of the plant. Those final values go into the turnover record alongside the original design settings.

Grid energization and the integrated test

Grid energization sets the date for the integrated test on many Arkansas projects, because a hall can only draw full load bank power once the utility has finished its interconnection. Entergy Arkansas, a member of the MISO grid, met the electrical requirements for the West Memphis campus announced in 2025, which includes its own substation; SWEPCO serves western Arkansas within the Southwest Power Pool, headquartered in Little Rock.

Paul Industries completes levels 1 through 4 on temporary or partial power wherever possible, so the integrated test can follow energization closely. When utility capacity arrives in stages, the integrated test is split by phase, and each phase’s script proves that the new equipment works with the systems already running.

Commissioning liquid cooling loops in Arkansas halls

Commissioning liquid cooling loops in Arkansas halls adds steps that air-cooled halls skip: flushing to the server vendor’s particle limits, coolant chemistry verification, leak detection tests at every manifold, CDU failover under load, and a check that the technology loop stays above the room dew point. Paul Industries tests CDUs with heat load units on the technology loop before servers connect, because a failed coupling found under load bank heat costs far less than one found under live processors. The loop design is described on the data center liquid cooling in Arkansas page.

Who performs data center commissioning in Arkansas?

Paul Industries performs data center commissioning in Arkansas on the mechanical systems it installs and on plants installed under earlier contracts, from level 2 installation checks through level 5 integrated systems testing. The data center commissioning services Paul Industries delivers include pressure testing, flushing and chemical cleaning, equipment startup, controls checkout, functional and integrated test execution, deficiency tracking, and the turnover records. Owners can buy those services alone, as part of a design-build plant, or with a complete installation.

Where the owner appoints a data center commissioning agent to write and witness the scripts, Paul Industries executes the tests, supplies the trend data and closes the deficiencies; where the owner wants one contract to carry the mechanical scope through testing, Paul Industries writes the scripts as well. The same work is described for the headquarters state on the Virginia data center commissioning page and across the river on the Tennessee data center commissioning page. In Arkansas, Paul Industries also tests the cooling plants it builds, described on the Arkansas data center cooling page.

Data center commissioning schedule for an Arkansas hall

A data center commissioning schedule for an Arkansas hall typically runs in parallel with the last third of construction and ends after the first full season of operation. Factory witness tests happen months before delivery; pressure tests and flushing follow each piping section; startup follows energization of each electrical feed; functional tests follow controls completion; and the integrated test follows utility energization and generator permitting.

Data center testing and commissioning time grows with the number of chillers, CDUs and air handlers, the redundancy level, and whether the hall is built in one phase or several. Paul Industries publishes a three-week look-ahead throughout commissioning so the owner, the controls contractor and the electrical team see which tests are coming and which deficiencies are blocking them.

Deficiencies, retesting and turnover records

Deficiencies found during Arkansas commissioning are logged the moment they appear, with the system, the test step, the observed result, the required result and the party responsible for the fix. Paul Industries closes mechanical deficiencies, retests the affected step and any step that depends on it, and records the closure with the retest data. The deficiency log is reviewed weekly with the owner so nothing reaches the integrated test unresolved.

Turnover records are built as the work proceeds, so the final package is a compilation rather than a reconstruction. Operators receive the tested sequences, setpoints, alarm limits and trend baselines they will use to judge the plant’s health, and the maintenance team receives a list of the seasonal checks that commissioning proved necessary, such as autumn glycol tests and spring tower cleaning.

What does data center commissioning in Arkansas cost?

The cost of data center commissioning in Arkansas depends on the number of systems and components tested, the levels included, the load bank capacity and rental period, generator fuel, the number of witness parties, deferred seasonal tests, and how much of the documentation Paul Industries prepares compared with what the owner’s agent provides. Load banks and fuel for a level 5 test are major variable costs on a big hall.

Paul Industries prices mechanical commissioning from the equipment list, the commissioning plan and the schedule; a budget range follows from those, and a firm price follows once the scripts and witness requirements are fixed.

Paul Industries and data center mechanical commissioning in Arkansas

Paul Industries carries data center mechanical commissioning in Arkansas from the first pressure test to the last seasonal test, with records an operator can use for the life of the plant. Related Arkansas work includes validation and commissioning in Arkansas for regulated plants and chiller repair in Arkansas once the plant is running; all of it is listed on the Arkansas page and the Southeast overview. Send the equipment list, the sequence of operations and the target turnover date, or request a quote.

Standards referenced: 2021 Arkansas Fire Prevention Code (2021 IBC and IFC with Arkansas amendments) · 2021 International Mechanical Code as adopted in Arkansas · 2020 Arkansas National Electrical Code · 2018 Arkansas Plumbing Code · 2014 Arkansas Energy Code (2009 IECC and ASHRAE 90.1-2007) · APC&EC Rules 18, 19 and 26 · 40 CFR 60.4211 · Arkansas Code 17-33 (HVACR) · ASHRAE Guideline 0 · ASHRAE TC 9.9 thermal guidelines · ASME B31.9

Frequently asked questions

Does Paul Industries commission data halls in West Memphis and the Arkansas Delta?

Yes. Paul Industries commissions the mechanical systems of data halls in West Memphis, Marion, Jonesboro and the rest of the Arkansas Delta, from pressure tests and flushing to integrated systems tests. Delta halls see long humid summers, so Paul Industries schedules full-load cooling tests or deferred seasonal tests for the hottest, most humid weeks, and checks insulation on all cold piping before it is enclosed.

Who handles data center commissioning around Little Rock and Conway?

Paul Industries handles data center commissioning around Little Rock, North Little Rock, Conway and Benton, for new halls and expansions of operating ones. Central Arkansas sites follow the 2021 Arkansas Fire Prevention Code and city permit reviews, and integrated tests are timed to the utility’s energization of the new load. Send the equipment list and the sequence of operations to scope the work.

Can Paul Industries test data center cooling systems in Bentonville, Rogers and Fayetteville?

Paul Industries tests data center cooling systems in Bentonville, Rogers, Springdale and Fayetteville, including economizers, dry coolers and liquid cooling loops. Northwest Arkansas has the coolest summers and coldest winters in the state, so freeze protection and economizer changeover are proven in the first winter, and peak cooling tests are often deferred to the first summer.

Does Paul Industries commission data center plants in Fort Smith, Texarkana and El Dorado?

Paul Industries commissions data center plants in Fort Smith, Texarkana, El Dorado and other western and southern Arkansas cities. These are among the hottest stations in the state, with about 816 hourly normals a year at or above 85 degrees in El Dorado and Texarkana, so cooling towers and chillers are proven at real peak conditions whenever the schedule allows.

Is commissioning required by the Arkansas energy code for a data center?

Arkansas’s commercial energy code is the 2014 Arkansas Energy Code, based on the 2009 IECC and ASHRAE 90.1-2007, and its provisions on controls, economizers and balancing apply to the cooling plant. It predates the data center energy standard, ASHRAE 90.4, so the full depth of testing usually comes from the owner’s requirements, the insurer and the lease. Paul Industries builds one test plan that satisfies all of them.

How do Arkansas air permits affect generator load tests?

Generators at an Arkansas data center operate under an air permit from the Division of Environmental Quality, and federal rules allow emergency engines up to 100 hours a year for maintenance and readiness testing. Integrated tests use those hours, so Paul Industries plans each generator run to test as many sequences as possible and logs run time for the owner’s permit records.

Which month suits a full-load cooling test in Arkansas?

July and August suit a full-load cooling test best, because Arkansas’s hottest and most humid hours fall then; Little Rock’s normal July high is about 92 degrees. When turnover happens in cooler months, Paul Industries runs load bank tests at design flow and writes deferred seasonal tests into the plan for the first summer, so tower and chiller performance is proven at peak.

How should an owner compare data center commissioning companies for an Arkansas project?

An owner should compare data center commissioning companies on the scripts they write, the trend data they deliver, how they track and close deficiencies, and whether the same team stays from startup through the seasonal tests. Paul Industries provides sample scripts and a turnover record outline with its proposal, so the owner sees the documentation before the work begins.

What data center commissioning services does Paul Industries deliver in Arkansas?

Paul Industries delivers pressure testing, flushing and chemical cleaning, equipment startup, controls point checkout, functional performance tests, integrated systems tests, load bank coordination, deficiency tracking, seasonal tests and turnover documentation in Arkansas. Owners can buy commissioning alone for a plant installed under another contract or as part of a Paul Industries design-build or installation package.

What does level 5 data center commissioning prove?

Level 5 data center commissioning, the integrated systems test, proves that the whole hall keeps the IT space within its temperature and power limits when things fail together: utility loss, generator start, chiller restart, pump and CDU transfer, and return to normal power. Load banks stand in for servers. Paul Industries records temperatures, flows and power through every event and reports any limit exceeded.

Which data center commissioning standards apply in Arkansas?

Data center commissioning standards used in Arkansas are the same national documents used elsewhere, chiefly the ASHRAE commissioning guidelines and ASHRAE thermal guidelines for data processing environments, applied through the owner’s project requirements. State codes set the pressure test, safety and energy provisions. Paul Industries cites the governing document for each acceptance criterion in its scripts.

Can an operating Arkansas data hall be recommissioned after an expansion?

Yes. Paul Industries recommissions operating Arkansas halls after expansions, chiller replacements or liquid cooling additions, testing the new equipment alone and then with the existing plant under a written method of procedure. Integrated tests on live halls are split into controlled steps so the operating load keeps its redundancy throughout.

Who is allowed to start up chillers on an Arkansas data center project?

Arkansas law requires every individual who installs, maintains, services or repairs an HVACR system in the state to hold one of the license classes in Arkansas Code 17-33-303, and the work is subject to city and county permits and inspections where those apply. Startup also follows the chiller manufacturer’s procedure. Paul Industries plans startups to meet both and records each one in the commissioning file.

How are liquid cooling loops tested during Arkansas commissioning?

Liquid cooling loops are pressure tested, flushed to the server vendor’s particle limit, filled with the specified coolant and sampled, then tested with heat load units for flow, temperature, leak detection and CDU failover before servers connect. Paul Industries also checks that the technology loop supply stays above the room dew point under every operating mode.

What records does an Arkansas owner receive at the end of commissioning?

The owner receives the commissioning plan, factory and startup reports, pressure test and flushing records, controls point checkout logs, completed functional and integrated test scripts with trend data, the deficiency log with closures, deferred seasonal test results and a recommended recommissioning interval. Paul Industries delivers them in an indexed electronic file.

Which project documents should an Arkansas owner send before commissioning is scheduled?

Paul Industries needs the owner’s project requirements, the basis of design, the mechanical equipment list, the sequences of operation, the electrical one-line, the generator permit conditions, the utility energization schedule and the target turnover date. With those, Paul Industries drafts the mechanical commissioning plan and a schedule tied to construction milestones.

Getting an Arkansas data hall ready for turnover?

Send the equipment list, sequences of operation, generator permit conditions and the target turnover date. Call 201-450-8280 or request a quote.