Paul Industries designs, fabricates and installs process piping in Hawaii for food and beverage plants, hospitals and hotels, utilities, fuel terminals and the Kapolei refinery district, building ASME B31.3 plant lines and the B31.1 steam and boiler piping that Hawaii’s boiler rules regulate. Spools are fabricated and pressure tested before they reach the plant, then installed in planned outages with tie-ins grouped to keep production running. Supply-only spools, design-build systems and complete installation are each offered under one contract.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Boiler piping rules HAR 12-222.1-8 and 12-220-9.1 (HIOSH, effective November 1, 2024)
Power piping code adopted ASME B31.1-2020
UST piping containment By July 15, 2028 for piping installed before August 9, 2013
Refinery district Kapolei, 93,500 barrels a day of distillation (EIA, 2026)
Reviewed November 2026

Process piping definition in Hawaii’s codes and rules

A working process piping definition for a Hawaii plant is the piping that carries product, chemicals, utilities and fuels inside the fence line and is designed to ASME B31.3, as distinct from building plumbing, which follows the state plumbing code, and from steam and boiler piping, which follows ASME B31.1. Hawaii draws one more line that mainland plants rarely meet: some steam, hot water and closed-loop piping falls under the state’s boiler and pressure system rules, with an application to the department before work starts.

Those rules sit in Part 10 of Title 12 of the Hawaii Administrative Rules, which took effect in their current form on November 1, 2024 and adopt ASME B31.1-2020 by reference. A Hawaii piping job therefore starts by sorting each line into its code family, because the code decides the design basis, the welding and examination, the test and the paperwork. Design rules, materials and spool practice for B31.3 work in general are on the process piping service page, while the sections below stay with Hawaii.

Piping code families at a Hawaii plant and the authority behind each
PipingDesign codeHawaii authority or ruleStep before work
Product, chemical, utility and compressed air lines inside the plantASME B31.3Owner’s specification; county building permit for the building work around itOwner’s design review; county permit where the building changes
Boiler external pipingASME Section I and B31.1HAR 12-222.1-8 and 12-220-9.1Application for an installation permit to the HIOSH Boiler and Elevator Inspection Branch
Non-boiler external piping (steam and feed beyond the boiler code break)ASME B31.1 and NBICHAR 12-222.1-8(b) and 12-220-9.1(b)Application by an authorized organization before work
Pressure systems and geothermal pipingASME BPVC and B31.1HAR chapter 12-225.1Installation permit application for vessels; BEP application for well piping
Underground fuel pipingListed double-wall piping systemsHAR 11-280.1, Department of HealthUST permit; secondary containment
Refrigeration pipingASME B31.5, ASHRAE 15, IIAR 2 for ammoniaExempt from the HIOSH permit, but welded repairs follow HAR 12-220-8.1Owner’s mechanical integrity program
Building plumbingState Plumbing Code (2018 UPC as adopted)County plumbing permitCounty permit and inspection
Hygienic product linesASME BPE and B31.3 Category M or normal service as specifiedOwner’s quality system; FDA rules for food and drug plantsSpecification and turnover package agreed

Process piping vs plumbing at a Hawaii plant

Process piping vs plumbing is a question of what the pipe serves: plumbing delivers potable water and removes sanitary waste for the people in the building and is permitted by the county under the Hawaii plumbing code, while process piping serves the production equipment and is designed, examined and tested to the owner’s chosen ASME code. The State Plumbing Code is the 2018 Uniform Plumbing Code as adopted by the State Building Code Council, and the counties administer it, so a food plant may hold a county plumbing permit for its restrooms and floor drains while its CIP and product lines are built to B31.3 and ASME BPE.

The boundary shows up most at backflow protection, where process water, boiler feed and chemical dosing connect to the potable supply, and at drains, where process waste meets sanitary sewer. When do you need a contractors license in Hawaii for that work? The Contractors License Board states that anyone who offers, bids or contracts to perform commercial, residential or public works construction, alterations or improvements needs a contractor license, with a small-job exemption limited to $1,000 and no building permit, and never for plumbing or electrical work that needs a permit. Paul Industries draws those boundary points on the piping drawings so the county reviewer and the plant engineer each see their own systems, and sanitary product lines are covered in more depth on the sanitary process piping in Hawaii page.

Boiler external piping and the Hawaii piping application

Boiler external piping in Hawaii, the steam, feed, blowoff and drain piping from the boiler up to the code break, must be designed, fabricated, installed and stamped to ASME Section I and B31.1 under HAR 12-222.1-8, and an application for an installation permit goes to the department before installation starts. Welded repairs or alterations to boiler external piping are made under the National Board R program.

Piping beyond the code break, called non-boiler external piping, is designed, fabricated, installed, altered or repaired under B31.1, the NBIC and the state rules by organizations holding an ASME S, PP or A designator, a National Board R certificate, or a Hawaii NBEP certificate of authorization, which the department issues after reviewing and approving the applicant’s quality control program. Each application carries the project and installer details, the National Board number of the boiler served, its data report, a floor plan with clearance dimensions and a piping and instrumentation diagram.

Repairs and alterations to non-boiler external piping follow NBIC Part 3 and B31.1, and the rule allows the repair inspector’s involvement to be waived and makes stamping optional for that piping. That flexibility shortens the paperwork on a steam header repair, but the application still comes first. Paul Industries prepares those applications with the drawings, then fabricates, installs and tests the piping, so boiler room work moves through the department as a single package. Related boiler work is on the boiler repair in Hawaii page.

Pressure systems and geothermal piping under chapter 12-225.1

Hawaii regulates closed pressure systems as a category of their own in chapter 12-225.1: unfired vessels and pressure pipe components of any closed liquid or vapor distribution system that runs above 15 psig or 250 degrees Fahrenheit and takes its heat from something other than burning fuel or electricity. The same chapter also takes in geothermal energy systems running above 15 psi, with their boiler external piping designed and built to ASME B31.1 and installed under the department’s BEP application.

High-temperature water loops heated through an exchanger, steam generated from waste heat and geothermal brine and steam lines are the kinds of piping that plant engineers check against that definition. Paul Industries reviews each closed loop against the rule at the design stage, routes vessel work through the pressure vessel fabrication in Hawaii scope, and builds the piping with the isolation, drains and relief protection the chapter calls for.

Process piping in Hawaii’s industries

Process piping in Hawaii serves a mix of industries that sit close together on Oahu and spread across the neighbor islands: fuel refining and terminals, food and beverage production, hospitals and hotels with central plants, water and wastewater utilities, and federal installations. Each brings its own fluids, materials and shutdown pattern.

At Kapolei, the EIA’s 2026 refinery capacity survey lists Par Hawaii Refining at 93,500 barrels per calendar day of atmospheric distillation and 40,000 barrels per stream day of vacuum distillation, and the surrounding Campbell Industrial Park holds fuel terminals and industrial plants. Refinery and terminal piping is built to B31.3 with the owner’s material and examination specifications, and most of it is replaced or tied in during turnarounds. Honolulu food and beverage plants run stainless product and CIP lines, glycol and chilled water, steam and condensate and compressed air. Hospitals and hotels carry steam, hot water, chilled water and medical gases, and water utilities run chemical feed and treatment piping. Neighbor island sites, from Kahului to Lihue and from Hilo to Kona, run the same systems at smaller scale in food plants, hotels, hospitals and utilities.

Process piping fabrication before the plant shuts down

Process piping fabrication for a Hawaii plant is front-loaded: spools are cut, welded, examined, pressure tested, cleaned and labeled before the outage, so the time inside the operating plant goes to setting and bolting rather than welding. Every weld is made to a qualified procedure under ASME Section IX, and every spool is tagged to its isometric drawing and packed in installation order.

Front-loading matters more on an island, where every fitting, gasket and spool should be on hand before the shutdown starts. Paul Industries field-measures tie-in points before fabrication, adds field-fit allowances where existing piping is out of position, and stages spare gaskets, bolting and fittings for each tie-in. For pipe fabrication, Hawaii plants also need materials suited to salt air, discussed below.

How a Hawaii process piping project runs, with the record each stage produces
StageWorkRecord delivered
Survey and code sortWalk-down, laser or tape measurement of tie-ins, each line assigned to B31.3, B31.1, plumbing or UST rulesLine list with code, fluid service and test medium
Design and applicationsIsometrics, supports, stress checks where needed, material take-off; HIOSH applications for boiler piping; UST permit work for fuel pipingIssued-for-construction drawings and filed applications
FabricationSpools welded to qualified procedures, examined to the code and specificationWeld map, welder log, examination reports, material test reports
Pressure test and cleaningHydrostatic or pneumatic test of each spool; cleaning, and passivation of stainless where specifiedTest charts and cleaning records
InstallationSpools set, supported and bolted during the outage; closure welds made and examinedTie-in records and closure weld examinations
System test and turnoverFinal leak or service test, labeling, insulation and coatingAs-built isometrics, test packages, data books

Salt air, materials and support design on island piping

Salt air on Hawaii sites attacks piping from the outside, so material choice, coating and support detail decide service life as much as the fluid inside. Outdoor carbon steel needs a coating system rated for marine exposure, galvanized or stainless supports and U-bolts, and insulation jacketing sealed against water, because corrosion under insulation is a common failure on humid, salty sites.

Stainless piping exposed to chloride air is usually specified in 316L rather than 304, its welds cleaned and passivated once fabricated, and duplex stainless is chosen where seawater or brackish cooling water flows inside. Supports are spaced and detailed to avoid crevices that trap salt and water. Paul Industries sets the material and coating list from the site’s exposure and the fluid service, and passivation restores the stainless surface after welding.

Rooftop and exposed pipe racks need support design for wind as well as weight and thermal movement. The State Building Code Council publishes wind topographic factor maps for use with the State Building Code, and ridge, hillside and coastal sites on every island see higher design wind loads than sheltered ones. Paul Industries sizes guides, anchors and rack steel for those loads, keeps supports from trapping salt water, and documents the support design with the piping drawings so the county reviewer sees both together.

Piping materials matched to Hawaii service and exposure

Piping materials for Hawaii plants are chosen twice, once for the fluid inside and once for the air outside, and the second choice often decides the service life of outdoor and rooftop lines. The table below sets out common pairings on island sites, which Paul Industries adjusts to each plant’s fluid data and exposure survey.

Common piping material and protection choices for Hawaii services
ServicePipe materialOutside protection on island sitesJoining and examination
Food product and CIP316L stainless tube, polished to the plant’s finish specificationIndoor; stainless supports and clamps near washdownOrbital autogenous welds with borescope records
Steam and condensateCarbon steel to B31.1, with stainless or alloy at high-erosion pointsInsulation with sealed metal jacketing; coated hangersWelded or flanged; examination per B31.1
Chilled water and glycolCarbon steel or copper indoors; stainless or coated steel outdoorsClosed-cell insulation with vapor barrier and UV-rated jacketingWelded, grooved or brazed per the specification
Compressed airAluminum, stainless or galvanized steelStainless or galvanized supportsMechanical joints or welds; leak test
Seawater and brackish coolingDuplex stainless, copper-nickel or lined pipeCoatings and isolation at dissimilar metal jointsWelded to qualified procedures; hydrostatic test
Fuel transfer abovegroundCarbon steel to B31.3Marine-grade coating; galvanized or stainless supportsWelded; radiography to the owner’s specification
Chemical feedStainless, alloy or plastic as the chemical requiresContainment where the chemical demands it; UV-stable plastics outdoorsWelded, solvent-cemented or fused per material

Steam and condensate piping in Hawaii hospitals, hotels and food plants

Steam and condensate piping in Hawaii serves sterilizers, kitchens, laundries, cookers and domestic water heaters, and it is designed to ASME B31.1, the power piping code that the state rules adopt in its 2020 edition. Because the boiler room end of that piping is regulated, a steam project often starts with the department applications described above before any pipe is cut.

Condensate return is where island steam systems lose the most money: failed traps blow live steam into the return, carbonic acid corrodes carbon steel return lines from the inside, and lost condensate means more make-up water and chemical treatment. A repair program replaces failed traps, re-pipes corroded returns in heavier wall or stainless, adds return pumps where lifts are needed and recovers flash steam where the load supports it. Paul Industries surveys traps and returns, prices the replacement in priority order, and installs the work around the facility’s steam demand, using the steam piping practice it applies nationwide.

Tie-ins and outages at operating Hawaii facilities

Tie-ins at operating Hawaii facilities are planned around the fact that few island plants have a spare line or a parallel unit, so each shutdown has to accomplish as much as possible. The plan lists every tie-in point, the isolation and draining each needs, the blinds and temporary connections, and the closure welds and tests that follow.

Refinery and terminal work follows the owner’s turnaround schedule and permit-to-work system. Hospitals and hotels need temporary services or staged changeovers so patients and guests keep heat, hot water and cooling. Food plants group tie-ins into sanitation breaks. Paul Industries writes the outage plan with the facility’s operations staff, stages all spools, gaskets and bolting before the shutdown begins, and tests each tie-in before the system returns to service.

Underground fuel piping and the 2028 containment date

Underground fuel piping in Hawaii counts as part of the underground storage tank system under HAR 11-280.1, so its design, permit and containment follow the Department of Health rules rather than the owner’s piping specification alone. Lines put in before August 9, 2013 need a containment system in place by July 15, 2028, except suction piping that meets the rule’s conditions.

Replacing single-wall piping with listed double-wall piping, containment sumps at the tank top and under dispensers, and interstitial monitoring is the usual route to that date. Piping associated with field-constructed tanks larger than 50,000 gallons is excepted from the 2038 containment requirement for older field-constructed systems. Paul Industries builds and replaces fuel piping with the tank work described on the tank fabrication in Hawaii page.

How often are pipes replaced at a Hawaii plant?

How often are pipes replaced at a Hawaii plant depends on the fluid, the material, the outside exposure and the inspection program; there is no fixed state interval for process piping, so replacement follows measured wall loss, leaks and the owner’s mechanical integrity findings. Carbon steel condensate return, outdoor compressed air headers and uninsulated lines exposed to salt spray tend to come up first, while well-specified stainless product lines last far longer.

Thickness surveys at elbows, tees and low points, inspections under damaged insulation and a review of leak history show which lines are near the end. Paul Industries uses those findings to price replacement section by section, so the worst lines are replaced first and the rest are scheduled into later outages.

What does process piping in Hawaii cost?

The cost of process piping in Hawaii follows the length and diameter of pipe, the material, the number of welds and fittings, the examination and test requirements of the code and specification, supports and insulation, the permits involved, and how much work falls inside the plant’s outage. Stainless sanitary lines with orbital welds and borescope records cost more per foot than carbon steel utility lines, and boiler piping adds the HIOSH application.

Public piping contracts let by the state or a county above $2,000 carry chapter 104 prevailing wage rates. For a budget range, send the island and site, P&IDs or a sketch, line sizes and materials, the fluid service and design conditions, the outage window and photographs of the tie-in points. Paul Industries returns a range from comparable work, then a firm price after the line list is fixed.

Who installs process piping in Hawaii?

Paul Industries installs process piping in Hawaii for refinery and terminal operators, food and beverage producers, hospitals, hotels, utilities and federal facilities on Oahu, Maui, Kauai and Hawaii Island. Among mechanical contractors, Hawaii plant owners look for one that handles the code sort, the HIOSH applications, fabrication, installation, testing and turnover under one contract, and that is the scope Paul Industries carries. Paul Industries is headquartered at 256 Shore Drive, Kilmarnock, Virginia, and is an East Coast contractor taking Hawaii projects alongside work in all 50 states and abroad; see the process equipment contractor in Hawaii page for plant systems beyond piping.

Owners comparing mechanical contractors in Hawaii for a multi-site program can read how the same scope runs elsewhere: the Florida process piping page covers coastal corrosion and acid service, and the process piping in Virginia, the headquarters state page covers the home market. The West Coast page covers the neighboring Pacific states, and welding methods are on the industrial welding services in Hawaii page.

Process piping from Paul Industries for Hawaii plants

Paul Industries designs, fabricates, installs, tests and turns over process, utility, steam, fuel and sanitary piping for Hawaii plants, and replaces and repairs piping already in service. For piping contractors, Hawaii’s rules add boiler piping applications, pressure system checks and UST containment, and Paul Industries builds those steps into each project schedule. Commissioning of finished systems is covered on the validation and commissioning in Hawaii page. Send the island, the system and the outage window through request a quote, or phone 201-450-8280.

Standards referenced: ASME B31.3 Process Piping · ASME B31.1-2020 Power Piping (adopted by HAR 12-220-1.1) · ASME Boiler and Pressure Vessel Code, Section I and Section IX · National Board Inspection Code, Part 3 · Hawaii Administrative Rules 12-220-9.1, 12-222.1-8 and chapter 12-225.1 (effective November 1, 2024) · Hawaii Administrative Rules chapter 11-280.1 (underground storage tank piping) · Hawaii State Plumbing Code (2018 Uniform Plumbing Code as adopted) · ASME BPE · ASHRAE 15 and IIAR 2

Frequently asked questions

Who installs process piping at Kapolei and Campbell Industrial Park plants?

Paul Industries installs process piping at Kapolei and Campbell Industrial Park plants, including refinery and terminal piping to ASME B31.3, fuel transfer and loading lines, steam and condensate to B31.1, and utility and compressed air headers. Spools are fabricated and tested before turnarounds and shutdowns, then installed with closure welds examined and test packages assembled for the owner’s mechanical integrity records.

Does Paul Industries build piping for Honolulu food plants, hospitals and hotels?

Paul Industries builds piping for Honolulu food and beverage plants, hospitals and hotels: stainless product and CIP lines, glycol and chilled water, steam and condensate, hot water and compressed air. Hospital and hotel work is staged so patients and guests keep service, and food plant tie-ins are grouped into planned sanitation or production breaks.

Who handles piping projects in Hilo, Kona, Kahului and Lihue?

Paul Industries handles piping projects for plants, hospitals, hotels and utilities around Lihue, Kahului, Kona and Hilo. Spools are prefabricated, tested and packed in installation order, with spare gaskets, bolting and fittings staged for each tie-in, so the work inside the facility is short and predictable.

Who designs high-temperature water and heat recovery loops for Hawaii plants?

Paul Industries designs and builds high-temperature water, heat recovery and closed steam-heated loops for Hawaii plants, hospitals and hotels, checking each against the state’s pressure system definition in HAR 12-225.1-1, which covers closed systems above 15 psig or 250 degrees Fahrenheit heated from a non-combustion source. Vessels, relief protection, isolation and drains are built to the chapter and the ASME codes.

What does the Hawaii plumbing code cover in an industrial building?

The Hawaii plumbing code, the 2018 Uniform Plumbing Code as adopted by the State Building Code Council and administered by each county, covers potable water supply, sanitary drainage, venting and fixtures for the people in an industrial building. Process lines serving production equipment are designed to ASME B31.3 or B31.1 instead. Paul Industries marks the boundary points, such as backflow preventers and process drains, on the drawings.

Does steam piping in Hawaii need a state permit?

Boiler external piping in Hawaii needs an application for an installation permit to the HIOSH Boiler and Elevator Inspection Branch before installation, and non-boiler external piping needs an application by an authorized organization before work starts, under HAR 12-220-9.1. Steam distribution in the rest of the plant follows the owner’s B31.1 specification. Paul Industries prepares those applications with the drawings.

What is a Hawaii NBEP certificate of authorization?

A Hawaii NBEP certificate of authorization is issued by the department to an organization whose quality control program it has reviewed and approved, allowing that organization to design, fabricate, install, alter or repair non-boiler external piping within ASME B31.1 and NBIC Part 3. Organizations with ASME S, PP or A designators or a National Board R certificate qualify under the same rule.

Is ammonia refrigeration piping in Hawaii under the boiler rules?

Hawaii’s rules leave refrigeration vessels and their piping off the permit to operate list, yet any welded repair or alteration on that piping goes through HAR 12-220-8.1 like boiler work. Ammonia systems follow IIAR 2 and ASHRAE 15 for design, and the owner’s process safety program where quantities require it. Paul Industries fabricates, installs and repairs ammonia piping to those standards.

What test does process piping get before a Hawaii plant starts it up?

Process piping in a Hawaii plant gets the leak test its code requires before startup: a hydrostatic test for most B31.3 lines, a pneumatic test where water cannot be used, or an initial service test for Category D lines, with test pressure, medium and hold time recorded. B31.1 piping follows its own test rules. Paul Industries runs those tests and hands over signed test packages.

How does salt air change pipe and support selection in Hawaii?

Salt air in Hawaii makes coatings, supports and insulation jacketing as important as the pipe material. Outdoor carbon steel needs a marine-grade coating, supports and U-bolts are galvanized or stainless, and jacketing is sealed against water to prevent corrosion under insulation. Stainless often moves to 316L. Paul Industries specifies each item from the site’s exposure and the fluid service.

Can new piping be tied into a live system at a Hawaii plant?

New piping can be tied into a live system at a Hawaii plant by hot tapping, where a branch is welded onto a pressurized line and drilled through a valve, when the line’s fluid, pressure, temperature and wall thickness allow it under the owner’s procedures. Other tie-ins are grouped into planned shutdowns. Paul Industries plans each tie-in method with the plant’s operations staff.

Which records come with a finished piping job in Hawaii?

A finished Hawaii piping job comes with as-built isometrics, the line list, weld maps and welder logs, welding procedure and qualification records, examination reports, material test reports, test packages with pressure charts, cleaning and passivation records where specified, and, for boiler piping, the filed applications and permit records. Paul Industries delivers them as one indexed turnover package.

Does a federal facility at Pearl Harbor follow the Hawaii boiler piping rules?

Pressure retaining items under the jurisdiction of the United States government are exempt from the Hawaii boiler and pressure vessel rules, so piping at federal installations such as those around Pearl Harbor follows the federal owner’s specifications and inspection program instead. The ASME codes still apply. Paul Industries builds to the owner’s specification and delivers the test records federal owners require.

Do fuel lines at a Hawaii generator plant fall under the UST rules?

Fuel lines that are part of an underground storage tank system, including connected underground pipes, fall under the Department of Health rules in HAR 11-280.1, which cover tanks storing fuel solely for emergency generators. Piping installed before August 9, 2013 needs secondary containment by July 15, 2028. Aboveground day tank piping follows the fire code. Paul Industries builds both.

What does replacing a corroded compressed air header involve?

Replacing a corroded compressed air header at a Hawaii plant involves surveying the existing header and drops, sizing the new header for current demand, choosing aluminum, stainless or coated steel for the site’s exposure, prefabricating sections, and installing them with valves that let parts of the system stay in service. Paul Industries plans the changeover so production keeps the air it needs.

Is there prevailing wage on piping work for a Hawaii state or county owner?

Hawaii law requires state and county construction projects over $2,000 to pay prevailing wages to laborers and mechanics and to file payroll records with the contracting agency, under chapter 104 of the Hawaii Revised Statutes. Piping work for those owners is priced on that basis. Private plant work outside public contracts follows the contract terms. Paul Industries prices each job to its owner’s requirements.

What should a Hawaii plant send to get process piping priced?

Send the island and site, P&IDs or a sketch, line sizes, materials and fluid service, design pressure and temperature, the code or specification the plant uses, photographs of tie-in points and the outage window. A budget range comes back first, built from similar piping jobs, and a firm figure follows when the line list is settled. Call 201-450-8280 or request a quote.

New lines, a tie-in or a steam piping repair at a Hawaii plant?

Send the island, the P&ID or sketch, the fluid service and the outage window. Call 201-450-8280 or request a quote.