Paul Industries designs, builds and services data center cooling in Arizona: chilled water plants, cooling towers, dry coolers, adiabatic and hybrid heat rejection, pumps, piping and the liquid loops behind dense racks, for data halls in Phoenix, Mesa, Chandler, Tucson and the rest of the state. An Arizona plant has to throw heat into air that passes 110 degrees on dozens of summer days, keep working through monsoon dust storms, and do it in cities that are asking every large water user to cut back. Paul Industries plans the heat rejection around those three facts, then supplies, installs, starts up and maintains it.
Request a quote or call 201-450-8280
What data center cooling in Arizona has to reject, and into what air
Data center cooling in Arizona moves heat from the servers to Sonoran Desert air that averages 107 degrees Fahrenheit on a July afternoon in Phoenix and still sits at 85 degrees at dawn, so the plant gets almost no overnight relief for three months of the year. NOAA’s 1991 to 2020 normals give Phoenix 111 days a year at 100 degrees or more, and the hottest day of an average year reaches about 116 degrees. Every chiller, tower, dry cooler and fan in the yard is selected against that afternoon, with the annual average used only for energy estimates.
The national data center cooling systems page explains plant types, components and design temperatures in general. This page covers what Arizona changes: the dry heat of June, the humid monsoon of July and August, the dust that comes with it, the water picture in the Valley, and the utilities that power the plant.
Data centers in Arizona: where the cooling load sits
Data centers in Arizona are spread across the Phoenix metropolitan area, where two widely reported public campuses stand in the East Valley city of Mesa, with enterprise, university and colocation rooms through Phoenix, Tempe, Chandler, Tucson and Flagstaff. Google lists Mesa among its data center locations, and Meta reports operational buildings at its Mesa Data Center, where ground was broken in 2021 and Meta has stated an Arizona investment of $1.2 billion. Both are named here only as public market facts that show the scale of the cooling load arriving in the state.
Data centers in Phoenix, Arizona and its suburbs share one climate while drawing on different utilities and water providers. A campus in Mesa draws water from the City of Mesa and, in Meta’s case, power from the Salt River Project, while a hall a few miles away inside Phoenix city limits buys water from Phoenix and power from either SRP or Arizona Public Service. Those boundaries decide the water rules and electric rates the cooling plant has to live with, so they are settled before the heat rejection is chosen.
| Place | Summer condition | Other planning fact | What the plant must handle |
|---|---|---|---|
| Phoenix, Mesa, Chandler and Tempe | July 107 F high, 85 F low; 111 days a year at 100 F or more | 122 F on June 26, 1990; 70 days at 110 F or more in 2024 | Full capacity at 115 F and above, little night recovery, dust-loaded coils |
| Tucson | June 101 F high, 71 F low; July 100 F high, 76 F low | July nights about 9 F cooler than Phoenix | Hot afternoons with cooler nights, so storage and night economizing work better |
| Yuma and the lower Colorado River | Hottest afternoon of a typical July near 115 F | 124 F record high | Air-cooled equipment sized well above the published rating point |
| Flagstaff and the high country | Mild summers at high elevation | Freezing winters | Economizer hours most of the year, freeze protection on every outdoor loop |
How are data centers cooled in Arizona?
Data centers in Arizona are cooled by one of four kinds of heat rejection: water-cooled chillers with evaporative cooling towers, air-cooled chillers, closed-loop dry coolers serving warm liquid loops, or hybrid and adiabatic coolers that run dry most of the year and spray or wet a pad only on the hottest hours. The air side inside the hall is the familiar mix of computer room air handlers, fan walls and contained aisles, increasingly with coolant distribution units feeding liquid-cooled racks. What separates an Arizona plant from one in a milder state is which heat rejection wins once water and the 115 degree afternoon are both priced in.
Evaporative cooling is extremely effective in June, when Phoenix air averages a dew point near 39 degrees and relative humidity under 20 percent, because a tower or a wetted media pad can cool water or air far below the dry bulb. The same equipment loses part of that advantage in July and August, when the monsoon raises the average dew point to the mid to upper 50s and the wet bulb climbs with it. Dry equipment saves the water but has to reject heat into the dry bulb itself, which is the hottest number in the state. Many new Arizona designs end up using both, with controls that decide hour by hour which one carries the load.
| Option | Water use | Behavior on a 115 F afternoon | Where it fits in Arizona |
|---|---|---|---|
| Water-cooled chillers with cooling towers | Highest: evaporation plus blowdown | Lowest compressor lift, because the tower works off the wet bulb | Large plants with a firm water supply or reclaimed water available |
| Air-cooled chillers | None for heat rejection | Highest condensing pressure; capacity and efficiency drop as ambient rises | Smaller halls, edge rooms and sites where water is the binding limit |
| Dry coolers on a warm liquid loop | None in normal operation | Loop temperature follows the dry bulb plus the cooler approach, so trim cooling is needed at peak | Liquid-cooled racks designed for warm facility water |
| Adiabatic or hybrid coolers | Water only on the hottest hours | Pre-cooled inlet air restores much of the lost capacity at peak | The usual compromise for Phoenix-area campuses that ration water |
| Direct or indirect evaporative air handlers | Moderate, concentrated in the dry months | Strong in June, weaker on humid monsoon days | Air-cooled halls with filtration sized for dust events |
A single comparison table hides the part that matters most: the hours. Phoenix runs above 100 degrees on about a third of the days in a year, but the coldest months still offer long stretches of economizer operation, and Flagstaff offers far more. Paul Industries models the plant against hourly weather for the actual site, so the owner sees how many hours each mode runs and how much water and power each option uses over a full year rather than at a single design point.
Sizing chillers and dry coolers for the Phoenix afternoon
Sizing chillers and dry coolers in Phoenix starts from the hottest hours, because nameplate ratings are usually published at 95 degrees Fahrenheit ambient and a Phoenix yard regularly sits 20 degrees above that. The 1991 to 2020 normals put the hottest day of a typical Phoenix year near 116 degrees, the all-time record is 122 degrees, and 2024 set a record of 70 days at 110 degrees or more. An air-cooled machine selected at its catalog point will run short of capacity and on a high head pressure for much of July.
The yard itself adds heat. Rows of air-cooled chillers or dry coolers placed close together can draw in each other’s discharge air, raising the inlet temperature several degrees above the weather station reading, and screen walls built for sound or appearance trap that air further. Paul Industries lays out the yard with spacing and discharge height that keep recirculation down, selects equipment at an inlet temperature above the published extreme, and checks the selection against the redundancy rule so that the plant still carries full load with one unit out on the hottest afternoon.
Nights matter as much as afternoons. In an average summer the Phoenix normal low stays at or above 80 degrees on 74 days, so thermal storage charged at night, or a plant that counts on cool mornings to catch up, gains less in the Valley than it does in Tucson, where July nights fall to the mid 70s. Storage still earns its place for ride-through, but its value in Phoenix is reliability more than energy.
Adiabatic stages need their own care in the Valley. Pads and spray nozzles concentrate whatever minerals the supply water carries, so a hybrid cooler fed with untreated city water scales its media and its coil within a season or two. Paul Industries specifies the water treatment, bleed rate and drain arrangement for each adiabatic stage, sets the controls so water is used only above a chosen dry bulb, and meters that water separately so the owner can report it to the city and see exactly what the peak hours cost. The same metering shows when a pad bank is fouling, because its water use climbs while the temperature drop across it falls.
Arizona data center water usage and the Colorado River cuts
Arizona data center water usage is now a planning item in every Valley city, because the Colorado River supply that carries much of central Arizona is being cut and municipal providers are passing the pressure on to large users. Phoenix draws nearly 60 percent of its water from the Salt and Verde Rivers through the Salt River Project, about 40 percent from the Colorado River through the Central Arizona Project and about 2 percent from groundwater. The city has been under a Stage 1 Water Alert since June 2022, and on November 10, 2026 it announced it expects to enter Stage 2 in January, asking residents and businesses for a voluntary 5 percent cut and proposing a drought surcharge that would reach about 7 percent of commercial bills and 1 percent of industrial bills.
Phoenix data center water planning therefore starts with the cooling towers. The City of Phoenix states that nearly all large facilities in the Valley have cooling towers and that they consume substantial volumes of water, and it runs a Cooling Tower Efficiency Program that reviews systems on site. As a rule of thumb, a tower evaporates roughly 1 percent of its circulating flow for every 10 degrees of range, and blowdown adds to that in proportion to how few cycles of concentration the water chemistry allows. Raising the cycles, running the tower only when the dry coolers cannot keep up, and choosing warmer chilled water all reduce the number the city sees on the meter.
Where do data centers get their water in the Valley?
Where do data centers get their water? In the Phoenix area, the answer is usually the municipal provider for the site, whether Phoenix, Mesa, Chandler, Goodyear or another city, under that city’s rates and drought stage, with reclaimed water a growing option for cooling. Meta states that it pays the City of Mesa the full cost of water and wastewater service for its Mesa campus. Treated wastewater already carries a very large cooling load in the state: the Palo Verde Generating Station west of Phoenix cools with treated effluent from Valley cities, and Phoenix recycles nearly all of its highly treated wastewater for uses that include that cooling. A data hall that can take reclaimed water for tower makeup protects its potable allocation, at the price of tighter water treatment and filtration.
Arizona data center water decisions also run through the Arizona statewide framework of active management areas and assured supply, which the hub page covers. For the cooling plant itself, Paul Industries brings the water budget into the first design review, sizes towers, dry coolers and adiabatic stages to fit it, and pairs the plant with cooling tower water treatment that holds the cycles the budget depends on.
Monsoon dust, downbursts and the outdoor equipment yard
The Arizona monsoon brings the three hazards an outdoor cooling yard handles worst: dust, wind and sudden humidity. The National Weather Service in Phoenix issues a Dust Storm Warning when visibility drops to a quarter mile or less, usually with gusts of 40 to 60 miles per hour, and describes these storms arriving as an advancing wall of dust that can be miles long. That dust lands in condenser coils, dry cooler fins, adiabatic media, tower basins and air handler filters within minutes.
Coil fouling is the costly part. A dry cooler or air-cooled chiller with a dusty coil rejects less heat at the same fan speed, so the leaving water temperature rises on exactly the hot, humid afternoons that follow a storm. Paul Industries designs Arizona yards with coil access for washing, inlet screens or pre-filters where the equipment allows them, tower basins with sidestream filtration sized for dust loads, and air handler filter banks with pressure monitoring so the operator sees loading as it happens. The plant also needs a written storm procedure covering which units are cleaned first and how controls respond to a sudden rise in wet bulb.
| Season | Condition | Plant tasks |
|---|---|---|
| Late spring, before the first 110 F day | Dry heat building, low humidity | Coil washing, tower and adiabatic media inspection, controls and setpoint review, redundancy test at load |
| June | Extreme dry bulb with very dry air | Watch head pressures on air-cooled units; confirm adiabatic water supply and treatment |
| July through September monsoon | Higher wet bulb, dust storms, downbursts, power disturbances | Post-storm coil and filter checks, basin cleaning, restart verification after utility events |
| Autumn | Falling temperatures, economizer hours return | Economizer changeover tests, chemical cleaning of fouled exchangers, overhauls on redundant units |
| Winter | Mild days in the Valley, freezing nights in the high country | Major repairs and tie-ins in the Valley; glycol and heat trace checks in Flagstaff and other high sites |
Power for the cooling plant: SRP, APS and TEP
Power for a Phoenix-area cooling plant comes from one of two large utilities, the Salt River Project, which is an agency of the state, and Arizona Public Service, regulated by the Arizona Corporation Commission; Tucson Electric Power serves much of southern Arizona. All three take part in the Western Energy Imbalance Market, APS since 2016, SRP since 2020 and TEP since 2022. EIA reports that Arizona generated about 116 million megawatt-hours in 2024 against roughly 91 million sold to retail customers in the state, with natural gas the primary source.
Electricity in Arizona costs a little less than the national average for the customers that run data centers. EIA’s 2025 figures put the Arizona commercial average at 12.45 cents per kilowatt-hour and industrial at 8.05 cents, against 13.37 and 8.51 nationally. For a cooling plant, that means water savings often win the argument against a small energy penalty, the reverse of the trade in a state with expensive power and plentiful water.
Codes and standards behind an Arizona cooling plant
Codes for an Arizona data center cooling plant are set by whichever city or county permits the building, since Arizona leaves commercial building codes to its cities and counties. The City of Phoenix adopted the 2024 Phoenix Building Construction Code on June 18, 2025, effective August 1, 2025, bringing in the 2024 International Mechanical Code and the 2024 International Energy Conservation Code with city amendments; Mesa, Chandler, Tempe, Goodyear and Tucson each adopt their own editions and amendments. The energy code points computer rooms to ASHRAE 90.4 for mechanical efficiency, and refrigeration safety follows ASHRAE 15 through the mechanical code.
Inside the hall, ASHRAE’s thermal guidelines recommend server inlet air between 64.4 and 80.6 degrees Fahrenheit. Running at the warm end of that range raises the chilled water temperature the plant can supply, which in Arizona lengthens the hours the dry coolers carry the load alone and shortens the hours the towers or compressors run.
Expanding cooling in an operating Arizona hall
Expanding cooling in an operating Arizona hall is scheduled around the weather as much as the IT load. Tie-ins to live chilled water mains, new chillers set beside running ones, and controls cutovers carry the least risk from November through March, when the Valley plant runs well below its design afternoon and a unit can come out of service with margin to spare. Work that must happen in summer is staged one unit at a time, with temporary cooling connections and a written method of procedure for each step.
New capacity for liquid-cooled racks adds coolant distribution units, technology cooling loops and, often, a warmer facility water circuit with its own dry coolers. The specifics are on data center liquid cooling in Arizona, and the tests that prove the enlarged plant ahead of the new load are on data center commissioning in Arizona.
What does data center cooling cost in Arizona?
The cost of data center cooling in Arizona is set by the IT load and rack density, the heat rejection mix, the redundancy rule, how much of the plant is prefabricated, and the price and availability of water and power at the site. A plant that leans on dry coolers and adiabatic trim costs more in equipment and yard space than a tower plant of the same capacity, but it buys water security that may decide whether the city serves the site at all.
Operating cost is easier to frame. Every 1,000 kilowatts of cooling plant power running all year uses 8,760,000 kilowatt-hours, about $705,000 at Arizona’s 2025 average industrial price of 8.05 cents and about $1.09 million at the commercial average of 12.45 cents (EIA). That arithmetic is why efficiency and water use are weighed together on every Arizona design. Paul Industries sets a budget range against similar Arizona-scale plants as soon as the load schedule and site are known, then fixes the price when the design is complete.
Who builds and services data center cooling in Arizona?
Paul Industries builds and services data center cooling in Arizona for colocation, enterprise, university and hyperscale halls in Phoenix, Mesa, Chandler, Tempe, Goodyear, Casa Grande, Tucson and Flagstaff. Headquartered at 256 Shore Drive, Kilmarnock, Virginia, and formerly based in northern New Jersey, then Pennsylvania, the East Coast contractor takes data center work across Arizona, in all 50 states and at plants outside the United States. Owners choose supply-only delivery of chillers, coolers and prefabricated pump skids, design-build from a load and water budget, or complete installation through startup and service.
The same contract covers the heat rejection, the piping and the plant around it. Large campus packages are described on data center mechanical contractor in Arizona, repairs to existing machines on chiller repair in Arizona, and tower selection on data center cooling towers. For comparison, the humid-climate approach at the headquarters state appears under data center cooling in Virginia, and the split between arid West Texas and the Gulf Coast is on data center cooling in Texas. Neighboring desert markets appear on the Southwest page.
Arizona data hall cooling from Paul Industries
Paul Industries engineers, supplies, installs, commissions and keeps running the cooling plants of Arizona data halls, with heat rejection selected for the Phoenix afternoon, yards built for monsoon dust, and water use planned with the serving city before the first drawing is issued. Send the IT load schedule, rack densities, site plan, water provider and electric utility, and Paul Industries returns a plant concept and budget. Call 201-450-8280 or request a quote, and see data centers for the full range of data center work.
Standards referenced: ASHRAE TC 9.9 thermal guidelines for data processing environments · ASHRAE 90.4 · 2024 International Mechanical Code (2024 Phoenix Building Construction Code) · 2024 International Energy Conservation Code · ASHRAE 15 · City of Phoenix Drought Management Plan (Phoenix City Code Chapter 37)
Frequently asked questions
Which contractor puts in data hall cooling for Mesa and Chandler sites?
Paul Industries puts in data hall cooling in Mesa, Chandler, Gilbert and Tempe, from chilled water plants with towers to dry cooler and adiabatic yards. East Valley campuses face the same 115 degree afternoons as the rest of the metro, plus city water rules that differ from Phoenix. Paul Industries sizes the plant against the serving city’s water terms and the SRP or APS service, then supplies, installs and starts it up.
Does Paul Industries take data center cooling work in Goodyear, Buckeye and the West Valley?
Yes. Paul Industries takes data center cooling work in Goodyear, Buckeye, Avondale, Glendale and Peoria. West Valley sites tend to be large greenfield parcels, which leaves room for spread-out yards that keep hot discharge air from recirculating between units. Paul Industries plans the yard layout, heat rejection mix and phasing for each building, and delivers the plant as supply-only, design-build or complete installation.
Who provides data center cooling in Tucson and southern Arizona?
Paul Industries provides data center cooling in Tucson, Marana and the rest of Pima County, served by Tucson Electric Power. Tucson’s July nights average about 76 degrees, nine degrees cooler than Phoenix, so thermal storage, night economizing and dry coolers recover more overnight there. Paul Industries models the hourly weather for the Tucson site before choosing between towers, dry coolers and hybrid equipment.
Does data center cooling in Phoenix behave differently in the monsoon than in June?
Yes. June brings very hot, very dry air, so evaporative towers and pads work at their strongest. From July into September the monsoon raises the Phoenix dew point by nearly 20 degrees on average, which lifts the wet bulb and trims evaporative capacity, while dust storms foul coils and media. Plants are sized and controlled for both conditions, and post-storm cleaning is written into the maintenance plan.
What does a Phoenix Stage 2 drought declaration mean for a data center?
Phoenix expects to move from Stage 1 to Stage 2 of its Drought Management Plan in January. Stage 2 asks residents and businesses for a voluntary 5 percent reduction and adds a drought surcharge for the highest-volume customers, estimated to reach about 7 percent of commercial bills and 1 percent of industrial bills. A data center on Phoenix water benefits from tower cycle improvements and dry-first controls that cut use before any surcharge applies.
Roughly how many gallons does a Phoenix data hall tower lose to evaporation?
A common rule of thumb is about 1 percent of the circulating water flow for every 10 degrees Fahrenheit of range across the tower, plus blowdown that depends on the cycles of concentration. A tower circulating 10,000 gallons a minute with a 10 degree range therefore evaporates roughly 100 gallons a minute at full load. Paul Industries estimates annual use from hourly weather and load so the owner has a number to bring to the city.
Is treated effluent a workable makeup source for Valley data center towers?
Yes, where the serving city or a reclaimed water provider can deliver it. Treated effluent already cools the Palo Verde Generating Station west of Phoenix, and Phoenix recycles nearly all of its highly treated wastewater. Reclaimed water usually carries more dissolved solids, nutrients and suspended matter than potable supply, so the tower needs stronger filtration, biological control and corrosion protection. Paul Industries designs the makeup, filtration and treatment for the water the site will receive.
Are air-cooled chillers a good fit for a Phoenix data hall?
Air-cooled chillers fit Phoenix halls where water is the limiting resource or the load is moderate, provided they are selected for the real yard temperature. Catalog ratings are commonly published at 95 degrees, while Phoenix yards exceed 115 degrees on the hottest afternoons. Paul Industries selects air-cooled machines at an elevated inlet temperature, checks redundancy at that condition, and often pairs them with adiabatic pre-cooling for the peak hours.
How are dry cooler coils protected from Arizona dust storms?
Coils are protected with spacing that allows washing access, inlet screens or pre-filters where the manufacturer permits, and a cleaning schedule triggered by storms rather than by the calendar alone. Differential temperature across each coil is trended, so a fouled unit shows up as a rising approach before it limits capacity. Paul Industries builds the access and monitoring into the yard and can carry the cleaning under a service contract.
How warm can the chilled water run in a new Phoenix-area data hall?
New Arizona halls commonly run warmer chilled water than older plants, often in the 60s Fahrenheit for air cooling and higher still for liquid-cooled racks, within ASHRAE’s recommended server inlet range of 64.4 to 80.6 degrees. Warmer water lets dry coolers carry the load for more hours each year and cuts tower water use. The final setpoint is chosen with the IT equipment requirements and the hourly weather for the site.
Which utilities power data centers in the Phoenix area?
Phoenix-area data centers are served by the Salt River Project, an agency of the state, or by Arizona Public Service, regulated by the Arizona Corporation Commission. Meta, for example, states that it worked with SRP to plan the energy needs of its Mesa campus. The serving utility sets the rate structure the cooling plant’s efficiency is measured against, so it is identified at the start of design.
Do Arizona cities require a specific mechanical code for data center cooling?
Each city adopts its own code. Phoenix adopted the 2024 Phoenix Building Construction Code, including the 2024 International Mechanical Code and 2024 International Energy Conservation Code, effective August 1, 2025. Other cities in the Valley and Tucson set their own editions and amendments. Paul Industries designs to the code in force where the permit is issued and lists it on the drawings and turnover records.
How do new data centers in Arizona plan for the hottest summers on record?
New data centers in Arizona plan for summers like 2024, when Phoenix recorded 70 days at 110 degrees or more and 113 straight days at 100 or above. Designers select heat rejection above the published extreme, keep redundant capacity available at that temperature, space equipment to limit recirculation, and add adiabatic trim or storage for ride-through. Paul Industries reviews each selection against those conditions before equipment is released.
What does Arizona's electricity price mean for a cooling plant decision?
Arizona’s 2025 average commercial price was 12.45 cents per kilowatt-hour and industrial 8.05, both below the national averages of 13.37 and 8.51 (EIA). Power is moderately priced while water is tightly managed, so in Arizona a design that spends some fan or compressor energy to save water usually pays. Paul Industries prices both resources on the owner’s actual tariff before recommending a heat rejection mix.
Can a running Arizona data hall get new chillers without losing cooling?
Yes. New chillers, coolers and mains are tied into an operating plant one step at a time under a written method of procedure, with redundancy confirmed before each isolation. In the Valley, the cooler months from November through March leave the most margin for tie-ins and cutovers, and summer work uses temporary cooling connections where the margin is thin. Paul Industries plans the sequence with the facility team before work starts.
Can an Arizona owner order coolers, chillers and pump skids from Paul Industries as equipment only?
Yes. On a supply-only order Paul Industries delivers chillers, dry coolers, adiabatic coolers, cooling towers, prefabricated pump skids and piping assemblies for Arizona projects as supply-only orders, with submittals, test records and startup support. The same equipment is available under design-build or complete installation when the owner wants one contract from design through service.
Which inputs let Paul Industries budget an Arizona cooling plant?
The inputs are the IT load schedule by phase, planned rack densities including any liquid-cooled rows, the site plan, the water provider and any water budget it has set, the electric utility, the redundancy rule and the target schedule. Paul Industries uses those to prepare a plant concept, an hourly water and energy estimate and a budget range, then a firm price once the design is defined.
Planning a cooling plant for an Arizona data hall?
Send the IT load schedule, rack densities, site plan, water provider and electric utility. Call 201-450-8280 or request a quote.