Paul Industries designs, installs, starts up and maintains data center cooling in Iowa, from chilled water plants and cooling towers to dry coolers, economizers and the piping that ties them to the white space. Iowa gives a cooling plant two hard seasons: summer afternoons with wet bulb temperatures near 79 degrees Fahrenheit and winter cold snaps that hold below freezing for more than two weeks. Paul Industries sizes every plant for both, and for the Iowa Department of Natural Resources water rules that decide where the makeup water comes from.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Summer design wet bulb About 79 F at Des Moines (0.4%, ASOS 2021 to 2025)
Free cooling weather Wet bulb at or below 45 F in about 46% of Des Moines hours
Water permit trigger Use above 25,000 gallons a day (Iowa DNR)
Generation mix Wind made 63% of Iowa electricity in 2024 (EIA)
Reviewed November 2026

What does data center cooling in Iowa have to handle?

Data center cooling in Iowa has to reject a steady IT heat load through humid summers, use cold air and water for free cooling during roughly half the year, survive multi-week freezes without splitting a coil, and do all of that on a water supply that is permitted, metered and in some aquifers capped. Those four conditions shape every choice that follows: the type of heat rejection, the chilled water temperature, the glycol plan and the water treatment program.

The national overview of plant types, components and design steps is on the data center cooling systems page. The Iowa page covers the state’s process industries. This page stays on the Iowa specifics: weather measured station by station, the state’s water permit rules, the electricity behind the plant and the codes that apply to the work.

Humid Iowa summers and the cooling tower

Iowa summers are humid enough that cooling towers, not chillers, set the limit on many plants. Hourly airport observations for 2021 through 2025 put the 0.4 percent wet bulb temperature at about 79.0 degrees Fahrenheit in Des Moines, 79.1 in Cedar Rapids, 79.2 in Davenport and 79.7 in Sioux City. A tower can only cool water toward the wet bulb, so a tower selected with a 7 degree approach is returning condenser water near 86 degrees on those afternoons, and the chillers carry their highest lift of the year.

The practical consequence is that an Iowa plant sized from dry bulb temperature alone comes up short in July. Paul Industries selects towers, condensers and fluid coolers against a measured wet bulb for the site, adds margin for the fouling that builds over a season, and checks the chillers at the resulting condenser temperature before the equipment is ordered. Where the owner wants an air-cooled or adiabatic design, the same check is run against dry bulb peaks, which reached 101 degrees in Des Moines in 2021 and 102 in Sioux City in 2023.

Economizer weather in Sioux City, Des Moines, Cedar Rapids and the Quad Cities

Economizer hours in Iowa are generous because the cold half of the year is long and dry. With a wet bulb at or below 45 degrees, a waterside economizer feeding 60 to 65 degree chilled water carries most or all of a hall’s load with the compressors idle, and every Iowa station studied sees that condition in roughly 46 to 49 percent of hours. Dry bulb at or below 59 degrees, a useful test for air-side economizers and dry coolers, occurs in 55 to 60 percent of hours.

Cooling design weather at four Iowa airports, hourly observations 2021 to 2025
Station0.4% wet bulbHours a year with wet bulb at or below 45 FHours a year above 90 F99.6% cold dry bulbLongest run below freezing
Des Moines (DSM)79.0 FAbout 4,000About 86-6 F391 hours, February 2021
Cedar Rapids (CID)79.1 FAbout 4,180About 37-9 F431 hours, February 2021
Sioux City (SUX)79.7 FAbout 4,270About 92-9 F424 hours, February 2021
Davenport (DVN)79.2 FAbout 4,040About 36-5 F406 hours, February 2021

Wet bulb values were calculated from each station’s temperature, humidity and elevation. The table shows why eastern Iowa sites at Cedar Rapids and Davenport see fewer hot hours than Des Moines or Sioux City, while all four share nearly the same humid design peak. A plant designed in Iowa therefore plans for two extremes: a short, intense humid season and a long, cold economizer season.

The February 2021 freeze and what it teaches a cooling plant

The February 2021 cold wave held all four Iowa stations below freezing for 16 to 18 days without a break, with Sioux City reaching minus 27 degrees Fahrenheit. A plant that relies on draining outdoor coils, on heat tracing alone or on a tower that keeps running at minimum load is tested hardest in a stretch like that, because there is no afternoon thaw to recover from a mistake.

Paul Industries designs Iowa plants so a long freeze is a normal operating mode. Dry coolers and outdoor fluid coolers run on propylene or ethylene glycol mixed for the site’s record low plus margin. Towers that stay in service get basin heaters, bypass to the basin, fan control that ramps down before ice forms, and isolation of idle cells. Economizer heat exchangers sit indoors on the glycol side, and makeup lines, drain legs and instrument taps that cannot be avoided outdoors are traced, insulated and alarmed. Startup testing includes a cold weather check so the controls prove they hold supply temperature with the compressors off.

Iowa data center water usage and the DNR permit

Iowa data center water usage is regulated through the Department of Natural Resources water use permit, which is required for any use, withdrawal or diversion of more than 25,000 gallons a day. Permits run for ten years, carry conservation conditions, and can be cut back during a declared shortage. A campus that draws from its own wells or from a river above that threshold needs the permit before the wells are drilled or the intake is built.

Groundwater adds a second layer. In the Cambrian-Ordovician aquifer, known in Iowa as the Jordan, DNR rules cap new industrial withdrawals at 2,000 gallons a minute at a single plant, issue permits on a five-year cycle and prohibit once-through cooling. Groundwater used as a heat exchange medium in a heating or cooling system also comes with a requirement to plan for reinjection. Those rules push Iowa designs toward closed loops, high cycles of concentration in towers and treated recycle streams.

Permitted users also report their water use to the DNR, so the plant needs reliable metering on makeup, blowdown and any recycle stream from the first day of operation. Paul Industries installs those meters with the plant and ties them to the building management system, which gives operators the same numbers the permit reports rely on.

Where an Iowa cooling plant’s water comes from and the rules that follow it
Water sourceRule that appliesDesign effect on the cooling plant
Municipal waterUtility service agreement and the city’s capacityMakeup demand is negotiated early; storage and peak day use are sized together
Owner wells, alluvial aquiferDNR water use permit above 25,000 gallons a day, ten-year termWell field, pretreatment and metering are part of the plant scope
Owner wells, Jordan aquifer2,000 gpm cap for new industrial use, five-year permits, no once-through coolingClosed loops or high-cycle towers with treated blowdown
River intakeDNR permit with protected flow conditionsBackup source or storage for low-flow periods
Closed loop with dry coolersLittle or no permitted volume after the initial fillLarger heat rejection footprint and more compressor hours in July

Three Iowa data center clusters and the cooling conditions at each

Iowa’s data center building is concentrated in three areas, and each one brings its own weather, water and power conditions to the cooling design. The western cluster is anchored by the Google data center Council Bluffs has hosted since 2007, and Google announced in May 2025 a further $7 billion for Iowa covering an expansion there and a new data center in Cedar Rapids. A Council Bluffs Iowa data center sits on the Missouri River side of the state, where the Council Bluffs airport logged 102 degrees in 2021 and minus 20 degrees the same winter.

The central cluster runs through West Des Moines, Altoona and the suburbs around Des Moines, where Microsoft and Meta operate large campuses. Des Moines data center water usage draws on a metro supply taken largely from the Raccoon and Des Moines rivers, the sources Des Moines Water Works uses to serve about 600,000 central Iowans, so makeup water is one of the first items discussed with the water utility. The eastern cluster is forming around Cedar Rapids, where QTS and Google are developing large campuses, on a slightly cooler site with fewer hot hours than Des Moines.

A cooling design that works well in one cluster is a starting point for another, never a copy. Paul Industries reruns the weather analysis, the water balance and the tariff comparison for each data center Council Bluffs, Des Moines or Cedar Rapids owners plan, because a few degrees of wet bulb or a different water source changes the tower size, the glycol strength and the annual operating cost.

Water-cooled, waterless and hybrid plants at Iowa campuses

Iowa’s large campuses show the full range of heat rejection. Google, which has operated its Council Bluffs data center since 2007, runs cooling towers there, while QTS, which is building its Cedar Rapids campus, states that its data centers use a closed-loop design that does not consume water for cooling. Microsoft has operated data centers in West Des Moines since 2012. These are market facts about the state; each site’s cooling choice reflects its own water, power and climate tradeoffs.

For an Iowa owner, the choice comes down to a few measurable numbers. A tower plant uses water to save power during the humid weeks and runs dry or nearly dry in winter on a waterside economizer. A dry cooler plant uses almost no water but needs more compressor energy during the roughly 1,800 hours a year when the Des Moines wet bulb is above 65 degrees, and more fan power through the warm months. A hybrid plant with adiabatic coolers or a small tower for peak trimming sits between them. Paul Industries prices the options against the site’s water source, its tariff and the IT load profile, so the owner chooses on real figures.

Which data center cooling options fit an Iowa hall?

Data center cooling options for an Iowa hall run from air-side economizers to warm-water liquid cooling, and most new plants combine two or three of them. The right mix depends on rack density, the chilled water temperature the IT equipment accepts, and how much water the site can permit.

Common data center cooling equipment and how each suits Iowa conditions
ApproachStrength in IowaWatch point in Iowa
Water-cooled chillers with towers and waterside economizerLowest power on humid peak days; long economizer seasonPermitted makeup water, tower freeze control, blowdown treatment
Air-cooled chillers with integral free coolingNo tower water; simple winter operation on glycolCapacity at 100 F condensing air; snow and ice on coils
Dry coolers feeding warm-water liquid coolingCompressor-free for most of the year at high supply temperaturesGlycol strength for minus 27 F lows; trim cooling for July
Direct air-side economizerCold dry air for much of the yearHumidity control, filtration during harvest dust, frost on intakes
Adiabatic or hybrid coolersWater only on the hottest hoursWater quality on the wetted media; freeze drain-down sequence

Each data center cooling unit in the white space, whether a computer room air handler, a fan wall or a coolant distribution unit, is selected to the supply temperature the plant delivers. Raising that temperature is the single strongest lever for Iowa economizer hours, which is why Paul Industries settles the IT supply range in the first design meeting. Halls that add dense racks connect through the data center liquid cooling in Iowa scope, which runs warmer water than an air-cooled room.

Redundancy and phasing shape the plant as much as the climate does. Most Iowa campuses open one hall at a time, so the central plant, the headers and the yard are laid out for the final build while only the first chillers, towers or dry coolers are set. Paul Industries sizes headers and valved stubs for future phases, places isolation valves so a new module ties in without draining live piping, and arranges N+1 or concurrently maintainable equipment so one unit leaves service for repair in July while the hall keeps its setpoint. Planning those tie-ins on day one keeps every later expansion an outage-free job.

How do data centers keep cool on wind-heavy Iowa power?

Data centers keep cool in Iowa on a grid where wind produced about 63 percent of the state’s electricity in 2024, according to the Energy Information Administration, and where the average industrial price was 6.80 cents per kilowatt-hour against a national 8.13. MidAmerican Energy and Interstate Power and Light were the two largest electricity retailers in the state that year. Cheap, low-carbon power changes the cooling math in two ways.

First, the cost of each compressor hour is smaller than in high-price states, so an Iowa design can accept a little more mechanical cooling in exchange for less water. Second, the cooling plant is a large share of the controllable load on a campus, and a plant that can coast on thermal storage or a warmer setpoint for an hour gives the owner room when the utility asks for demand response. Paul Industries designs controls and storage to take advantage of both, without compromising the inlet temperatures the IT equipment needs.

Iowa codes behind the cooling plant

Data center cooling requirements in Iowa start with the state mechanical code, which since March 26, 2025 has been the 2024 International Mechanical Code as amended by the Plumbing and Mechanical Systems Board. Cities and counties administer the permits and inspections and may add amendments that are stricter, but they adopt no other mechanical code, so the same rule book applies from Council Bluffs to Davenport. Refrigeration machinery rooms follow the code’s refrigeration chapter and ASHRAE 15, and chilled water piping is built and tested to ASME B31.9 or the owner’s specification.

Refrigerant choice has a specific Iowa provision. Iowa Code section 103A.24, added in 2023, bars a building regulation from prohibiting a refrigerant that the EPA has designated acceptable, provided the equipment is listed and installed under the conditions of that designation. That clears the way for the lower global warming potential refrigerants now required in new chillers, as long as the machinery room, detection and ventilation meet the safety standard. Paul Industries documents those items in the submittal so the inspection runs cleanly.

Running the plant through an Iowa year

An Iowa data center cooling loop changes its operating mode several times a year, and each transition is where problems start. The calendar below is the maintenance and checking rhythm Paul Industries uses for Iowa plants.

Seasonal checks for an Iowa data center cooling plant
SeasonPlant conditionChecks and work
March and AprilEconomizer to partial mechanical coolingTower startup, basin cleaning, chemistry reset, chiller oil and refrigerant checks
May and JuneRising wet bulb and pollen seasonStrainer and coil cleaning, condenser approach trending, controls tuning
July and AugustPeak humid loadDaily approach and lift review, tower fan and drift eliminator inspection, spare capacity confirmed
September and OctoberHarvest dust, falling wet bulbFilter and coil cleaning, economizer changeover test, glycol concentration check
November to FebruaryFull economizer, freeze riskBasin heater and trace checks, idle cell isolation, cold weather alarm testing

Data center water treatment runs through all five seasons. Tower water is controlled for scale, corrosion and biological growth while it runs, and the closed glycol and chilled water loops are sampled for inhibitor level, conductivity and bacteria at intervals set in the treatment plan. Iowa’s agricultural watersheds carry nitrate and organic matter from farm runoff into surface water supplies, and their levels move with the seasons, so a treatment plan built on one January sample rarely holds in June.

What is the data center cooling system cost to run in Iowa?

The data center cooling system cost to run in Iowa is set by the plant’s power draw, its water use and its maintenance, and the power share is easy to estimate. At the 2024 Iowa industrial average of 6.80 cents per kilowatt-hour, every 250 kilowatts of cooling power drawn around the clock costs about $148,920 a year. A design change that trims 40 kilowatts from the average cooling draw is worth about $23,800 a year at that rate, before any water savings.

Installed cost depends on the data center cooling load in megawatts, the redundancy level, the heat rejection type and how much of the work is prefabricated. Paul Industries prices Iowa plants from the IT load schedule, the target supply temperatures, the site water source and the redundancy basis, and shows equipment, piping, controls and startup separately so the owner can compare options line by line. Owners choose between supply-only equipment packages, design-build delivery and complete installation by Paul Industries.

Who installs data center cooling in Iowa?

Paul Industries installs data center cooling in Iowa, from the yard equipment through the piping and controls to the units in the hall, headquartered at 256 Shore Drive in Kilmarnock, Virginia. Paul Industries is an East Coast contractor that takes work across Iowa, in all 50 states and at plants abroad, and the same firm that installs the plant tests it, starts it up and services it afterward.

On an Iowa project that usually means chillers, towers or dry coolers, pumps, heat exchangers, the data center cooling tower package, glycol systems and the distribution piping. Paul Industries also handles data center commissioning in Iowa, the data center mechanical contractor scope in Iowa across a whole campus, and chiller repair in Iowa once the plant is running. The same approach is applied at the company’s home base on data center cooling in Virginia and in the neighboring market of data center cooling in Illinois.

Data center cooling from Paul Industries across Iowa

Paul Industries designs, supplies, installs, starts up and maintains data center cooling plants for Iowa campuses, enterprise halls and colocation sites in Des Moines, West Des Moines, Council Bluffs, Cedar Rapids, the Quad Cities, Sioux City and Iowa City. The scope includes chilled water plants, cooling towers, dry coolers, economizers, glycol systems, pumps and piping, and the cooling tower water treatment and treated water systems that support them. For multi-state owners, the Midwest page shows the neighboring states covered under the same contract terms. Send the IT load schedule, the supply temperature range, the site water source and the redundancy basis, and request a quote.

Standards referenced: 2024 International Mechanical Code (Iowa state mechanical code, 481 IAC 426) · Iowa Code 103A.24 (refrigerants) · Iowa Code 455B and 567 IAC 50 (water use permits) · ASHRAE Thermal Guidelines for Data Processing Environments · ASHRAE 15 · ASHRAE 90.1 · ASME B31.9

Frequently asked questions

How much water will the Cedar Rapids data center use?

Water use depends on which campus and which cooling design. QTS, which is building a campus in Cedar Rapids, states that its data centers use a closed-loop system that does not consume water for cooling, while tower-based plants elsewhere use makeup water that rises with the summer wet bulb. Cedar Rapids data center water usage for any new tower plant would also fall under the Iowa DNR permit threshold of 25,000 gallons a day if drawn from owner wells or the river. Paul Industries sizes makeup, storage and treatment for whichever design an owner selects.

What does Council Bluffs data center water usage depend on?

The heat rejection design, the cycles of concentration in the towers and the weather. Google operates cooling towers at its Council Bluffs data center, and tower makeup in that part of Iowa peaks in July and August when the wet bulb approaches 80 degrees. During the long cold season a waterside economizer sharply cuts evaporation. Paul Industries estimates annual makeup for Council Bluffs plants from hourly weather data, the planned cycles and the IT load.

What cooling do data centers in Des Moines and West Des Moines rely on?

Data centers in Des Moines and the western suburbs use chilled water plants with towers or air-cooled chillers, economizers and, increasingly, liquid cooling for dense racks. West Des Moines data center water usage is tied to the municipal supply, so new demand is planned with the utility early. Paul Industries designs Des Moines area plants around the 79 degree summer wet bulb and the roughly 4,000 hours a year of economizer weather.

Who builds cooling plants for data centers in Sioux City and northwest Iowa?

Paul Industries builds and services cooling plants for data centers in Sioux City and across northwest Iowa. Sioux City recorded the lowest temperature of the four stations studied, minus 27 degrees Fahrenheit in 2021, and also the most hours above 90 degrees, so glycol strength, tower freeze protection and condenser capacity all need margin there. Send the load and site details and Paul Industries will scope the plant.

Can Paul Industries handle data center cooling in the Quad Cities and Dubuque?

Yes. Paul Industries designs, installs and maintains data center cooling in Davenport, Bettendorf, the rest of the Quad Cities and Dubuque. Davenport’s records show about 36 hours a year above 90 degrees but a 79 degree design wet bulb, so a plant there can lean hard on economizers while still sizing towers for humid peaks.

Are data centers water cooled in Iowa?

Many are, through cooling towers that reject heat by evaporation, while others use air-cooled chillers or dry coolers with almost no water. The choice in Iowa often turns on where the water comes from. A site on a municipal supply negotiates capacity with the utility, and a site on its own wells needs a DNR permit above 25,000 gallons a day. Paul Industries designs both kinds of plant and prices them side by side.

Where do data centers get their water in Iowa?

From municipal utilities, from their own wells in alluvial or bedrock aquifers, or from rivers, each with different rules. Withdrawals above 25,000 gallons a day from owner sources need an Iowa DNR water use permit, and the Jordan aquifer carries extra limits, including a 2,000 gallon per minute cap on new industrial withdrawals and a ban on once-through cooling.

Do data centers use a lot of water in Iowa winters?

Far less than in summer. With the wet bulb at or below 45 degrees for close to half the year, a tower plant on waterside economizer evaporates much less water, and a plant on dry coolers uses almost none. Iowa data center water usage therefore peaks for a few humid months and falls sharply from November through March.

How cold should glycol be rated for an Iowa dry cooler?

Below the lowest temperature the site is likely to see, with margin. Hourly records from 2021 to 2025 show lows of minus 17 degrees in Des Moines and minus 27 in Sioux City, so Paul Industries protects outdoor coils at Iowa sites to minus 30 degrees or lower. Higher glycol strength reduces heat transfer and raises pumping power, so Paul Industries balances freeze protection against those costs and documents the mixture for operators.

What chilled water temperature suits an Iowa data hall?

As warm as the IT equipment allows. Supply at 60 to 65 degrees lets a waterside economizer carry the load whenever the wet bulb is near 45 degrees or below, which in Iowa is close to half the year. Warmer supply for liquid-cooled racks extends compressor-free hours further. Paul Industries confirms the range with the IT team before equipment is selected.

Which Iowa code governs chillers and cooling piping in a data center?

The Iowa state mechanical code, which adopts the 2024 International Mechanical Code with state amendments and applies statewide. Cities and counties issue permits and inspect the work and may add stricter amendments. Machinery rooms follow ASHRAE 15, and Iowa Code 103A.24 keeps building rules from banning EPA-accepted refrigerants when equipment is listed and installed to its use conditions.

How do Iowa harvest seasons affect data center cooling equipment?

Harvest and fall tillage put dust and chaff in the air every autumn, and that debris loads condenser coils, dry coolers, tower fill and outside air filters. Paul Industries schedules coil and filter cleaning around harvest, trends condenser approach to catch fouling early, and selects filters and intake locations for air-side economizers with the season in mind.

How do data centers keep cooling running when a winter storm cuts power in Iowa?

Generators carry the pumps, controls and heat rejection, and the plant is designed so it restarts in winter without freezing anything during the transfer. Thermal storage tanks bridge the gap while chillers restart, and economizer mode often carries the load on its own in cold weather. Paul Industries tests the restart sequence in cold conditions during commissioning.

What water treatment does an Iowa data center cooling tower need?

Scale, corrosion and biological control matched to the makeup water, which in Iowa ranges from treated municipal water to hard well water with seasonal nitrate and organics from farm runoff. Higher cycles of concentration save water but need tighter scale control and blowdown treatment. Paul Industries sets up the program with continuous conductivity control and periodic lab testing.

Does Paul Industries maintain Iowa data center cooling plants after startup?

Yes. Paul Industries offers scheduled maintenance covering chillers, towers, dry coolers, pumps, heat exchangers, glycol and water treatment, with seasonal changeover checks for spring and autumn and freeze readiness checks before winter. Contracts include operating log review and a report after each visit, so trends are caught before they become failures.

How long does an Iowa data center cooling plant take to build?

The schedule is set by long-lead equipment such as chillers, switchgear and large cooling towers, by the permitting path for water and building work, and by the winter. Prefabricated pump skids and pipe racks shorten field time, and outdoor work is sequenced so piping is closed, filled and protected before the first hard freeze. Paul Industries builds the schedule from equipment lead times at the time of order.

What should be sent to price data center cooling for an Iowa site?

Send the IT load by phase, the target supply temperatures, the redundancy basis, the water source and any permit status, the electrical service and tariff, and site drawings showing the equipment yard. Paul Industries uses that package to compare tower, dry cooler and hybrid plants and to price the selected route with equipment, piping, controls and startup shown separately.

Planning data center cooling at an Iowa site?

Send the IT load by phase, supply temperatures, redundancy basis and water source. Call 201-450-8280 or request a quote.