Paul Industries is a data center mechanical contractor in Idaho, building chiller and heat rejection plants, chilled water and liquid cooling piping, air handling, generator fuel and cooling systems, and the controls that tie them together for campuses in the Treasure Valley, the Magic Valley, eastern Idaho and North Idaho. Idaho data center construction moves with utility capacity, a state sales tax exemption that names chillers and generators, a short outdoor season in the high desert and a set of state licensing and registration rules. Paul Industries designs, prefabricates, installs, tests and starts up the mechanical package, phase by phase.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Grid growth Idaho Power peak demand up nearly 1,000 MW in five years (2025 IRP)
Large loads Over 20,000 kW served by special contract with Idaho Power
Sales tax Chillers and generators listed as eligible server equipment (Idaho Code 63-3622VV)
State prevailing wage Repealed in 1985 (US Department of Labor)
Reviewed November 2026

Scope of a data center mechanical contractor in Idaho

The scope of a data center mechanical contractor in Idaho runs from the equipment yard to the rack: chillers, dry coolers and cooling towers; pumps, headers and chilled water or warm-water mains; computer room air handlers, fan walls and indirect evaporative units; coolant distribution units and secondary loops for liquid-cooled racks; generator fuel, exhaust and jacket water systems; and the building management controls that sequence it all.

Data center mechanical systems also include the parts that never appear on a rack diagram: makeup and drain piping, water treatment, glycol fill stations, heat tracing and insulation for outdoor runs, refrigerant piping for split equipment, and the supports, seismic restraints and penetrations that carry them. On an Idaho campus each of those is sized for the site’s elevation and protected for its winter. Paul Industries prices and builds the full list under one contract, so the owner deals with one schedule, one set of submittals and one turnover package. The national data center mechanical contractors page explains the work in general terms; the sections below are specific to Idaho.

What data centers are in Idaho, and are more coming?

Data centers in Idaho range from enterprise and colocation halls in the Boise area to hyperscale campus scale: Meta announced in September 2026 that its Kuna Data Center, begun in 2022 and listed by Meta at more than $1.2 billion of investment, is online and operational. Meta reported up to 1,600 skilled trade workers on that site at peak construction.

Are data centers coming to Idaho in larger numbers? The utility planning record points that way. In its 2025 Integrated Resource Plan, Idaho Power forecasts that system peak will climb by roughly 1,700 megawatts in two decades and close to 1,000 megawatts within five years, citing population and a wide range of commercial and industrial development; state regulators acknowledged that plan on February 17, 2026. Data centers planned for Idaho compete for that capacity with other large industrial loads, including Micron’s Boise memory fab, which Micron says is under construction with DRAM output scheduled to begin in 2027. Every new data center Idaho Power connects above 20,000 kilowatts takes service under a special contract, so the contract timeline and the mechanical schedule are linked from the start.

Idaho Power, Avista and Rocky Mountain Power: who energizes the campus

The utility that energizes an Idaho campus depends on where it sits: Idaho Power serves the Boise area and much of southern Idaho, Avista serves northern Idaho, and Rocky Mountain Power serves eastern Idaho, with municipal and cooperative systems in some towns. An Idaho Power data center above 20,000 kilowatts negotiates a special contract that the state commission reviews, and customers between 10,000 and 20,000 kilowatts may choose one.

Idaho Power states that new large-demand customers pay their own costs of interconnecting to its system, and its plan calls out new 500-kilovolt transmission, the Boardman to Hemingway and Southwest Intertie projects, to import energy at peak. For the mechanical contractor, that means power arrives in blocks on a contract schedule, and the mechanical package must be phased to match. Chiller plants, generator yards and headers are laid out for the final campus, but equipment is bought and installed in the increments the utility can serve, which keeps capital from sitting idle in a yard without power.

Idaho electric service areas and what each means for a data center build
RegionMain utilityCitiesMechanical planning point
Treasure Valley and southern IdahoIdaho PowerBoise, Meridian, Nampa, Kuna, Caldwell, Twin FallsSpecial contract above 20 MW; plant phased to contract deliveries
Eastern IdahoRocky Mountain Power, plus municipal systems such as Idaho FallsIdaho Falls, Pocatello, RexburgLong freeze season; outdoor work windows drive the schedule
North IdahoAvistaCoeur d’Alene, Post Falls, LewistonLower elevations; Avista interconnection process

The Idaho data center sales tax exemption and the mechanical equipment list

Idaho data center incentives center on Idaho Code 63-3622VV, the sales tax exemption in effect since July 1, 2020 for eligible server equipment and new data center facilities bought by qualifying business entities and by contractors building for them. The statute defines eligible server equipment to include servers, rack servers, chillers, storage devices, generators, cabling and integral software, and it defines a chiller as a cooling system used in data centers to remove heat from one element and deposit it into another.

A business entity qualifies by certifying to the State Tax Commission that it will invest at least $250 million in Idaho data centers within the first five years after construction starts and create at least 30 new jobs within two years after operations begin, which the statute ties to the certificate of occupancy. The exemption is provisional until those conditions are met, and taxes become due if they are not. For the mechanical contractor, the exemption shapes purchasing: equipment and materials bought for the exempt facility must be documented to it, invoices must separate exempt items, and the record has to survive an audit years later. Paul Industries sets up purchasing and invoicing with the owner’s tax team at contract award so each chiller, generator and material order carries the right documentation.

Idaho licensing, registration and wage rules on a mechanical package

Idaho licensing and registration rules attach to the work itself: Idaho Code 54-5204 makes it unlawful to act as a contractor in Idaho without registration under the Idaho Contractor Registration Act, and Idaho Code 54-5008 requires a state certificate of competency for anyone engaged in HVAC work. Under 54-5015, only the Division of Occupational and Professional Licenses issues those HVAC certificates, and cities and counties may not require added certification or fees for them.

Plumbing and electrical work follow their own state chapters, and public works, such as a state university or public agency data center, require a public works contractor license under Idaho Code 54-1902. Idaho has no state prevailing wage law; the U.S. Department of Labor lists it as repealed in 1985. Federally funded projects still carry federal wage requirements in their contracts. Permits follow Idaho Code 54-5016 for HVAC, and building permits come from the city or county where it enforces the building code under Idaho Code 39-4116, or from the state elsewhere. Paul Industries builds these requirements into the project’s permit and compliance plan from the first submittal.

Mechanical contractor vs plumbing contractor on an Idaho data center

The difference between a mechanical contractor vs plumbing contractor on an Idaho data center follows the state’s code split: HVAC systems, including chilled water, air handling and refrigerant piping, fall under the HVAC chapter and the 2018 International Mechanical Code, while domestic water, sanitary drainage and fixtures fall under the 2017 Idaho State Plumbing Code. Makeup water, drains from cooling equipment and backflow protection sit at the boundary and are coordinated on one set of drawings. Paul Industries carries both sides of that boundary on its mechanical package, so connections between them are designed, permitted and tested together.

Codes behind data center mechanical design in Idaho

Data center mechanical design in Idaho follows the state’s adopted codes: the 2018 International Building Code, the 2018 International Mechanical Code and 2018 International Fuel Gas Code with Idaho amendments, the 2023 National Electrical Code with amendments, the 2018 International Fire Code administered by the State Fire Marshal, and the 2018 IECC, whose Idaho amendment exempts spaces cooled exclusively for electronic equipment. The Building Code Board has been preparing a move to the 2024 editions.

Idaho rules that reach the mechanical package on a data center
RuleWhat it requiresWhere it shows up in the build
Idaho Code 54-5204Contractor registration to act as a contractor in IdahoContract award and every tier of the project
Idaho Code 54-5008 and 54-5016HVAC certificate of competency; HVAC permit for installation and alterationPermit submittals and inspections for every phase
2018 IMC with Idaho amendmentsMechanical design and installationChilled water, air handling, refrigerant piping, ventilation
2017 Idaho State Plumbing CodePlumbing systems and backflowMakeup water, drains, domestic water to support spaces
2018 IECC amendment C101.5.2Exempts spaces cooled exclusively for electronic equipmentData halls separated from offices by a complying envelope
Idaho Code 63-3622VVSales tax exemption for qualifying data center purchasesPurchasing, invoicing and records for chillers, generators and materials
IDAPA 58.01.01Air permit to construct unless an exemption appliesGenerator yard design, fuel type and run-hour limits
EPA Technology Transitions ruleGWP limit of 700 for data center cooling from January 1, 2027Refrigerant choice on CRAC units and packaged equipment

Data center construction in Idaho’s seasons

Data center construction, Idaho-wide, is planned around a short outdoor season in the high desert and hot afternoons in the valleys: the Idaho Falls airport averages 182 nights a year at or below 32 F, Boise 108, while Boise also averages about 55 days at 90 F or above. Yard work, underground piping, crane lifts and roof equipment fit best between spring thaw and autumn freeze.

Paul Industries schedules outdoor mechanical work into that window and moves as much as possible indoors or off site. Pipe spools, pump skids, headers and modular plant sections are fabricated and welded off site under controlled conditions, then set and connected on site. Underground and yard piping is installed and tested before the ground freezes. Piping tested in winter is drained or protected immediately, and equipment set before the building is closed in is kept heated and dry. That sequencing lets interior work in the hall continue through winter without waiting for weather.

Building a data center: Boise, Idaho and the Treasure Valley

Data center construction Boise, Idaho owners plan sits in the state’s busiest construction market, where a hyperscale campus at Kuna and Micron’s fab construction in Boise draw on the same pool of trades and equipment. Paul Industries plans long-lead equipment early and prefabricates heavily so field labor peaks are shorter.

Eastern Idaho, the Magic Valley and North Idaho

Sites around Idaho Falls, Pocatello and Twin Falls face longer freeze seasons and higher elevations, which shift more work off site and into the warm months. North Idaho sites in Coeur d’Alene and Lewiston sit lower and work with Avista on power.

Prefabrication on Idaho data center campuses

Prefabrication carries more weight on Idaho data center campuses than in milder states, because a high-desert winter shortens the outdoor season and the Treasure Valley’s construction market keeps skilled field labor in demand. Moving welding, assembly and testing off site turns weather-exposed field hours into controlled shop hours and shortens the time between setting equipment and starting it.

Paul Industries fabricates chilled water and condenser water spools, pump and heat exchanger skids, CDU headers and pipe rack modules off site, pressure tests them before shipment and labels each piece to its location on the drawings. On site, modules are set, bolted or welded at a small number of field joints, and tested again as a system. The approach also helps phasing: modules for a later phase can be built and stored while the earlier phase is still under construction, then installed as soon as power for that phase is scheduled.

Off-site and field work on an Idaho data center mechanical package
ElementBuilt off siteDone in the fieldIdaho reason
Pump and heat exchanger skidsFrame, piping, valves, instruments, wiring to terminal boxSetting, connection, alignment checkShorter field hours in a tight labor market
Chilled water and warm-water spoolsCut, welded, examined and pressure testedSetting on supports and field jointsWelding moved out of winter weather
Pipe rack modulesSteel, piping, cable tray and supports assembledLifting and connecting module to moduleFewer crane days in the warm season
CDU headers and rack manifoldsFabricated, cleaned and cappedInstalled above or below rows, flushed with the loopCleanliness kept for liquid-cooled racks
Underground and yard pipingSpools where practicalTrenching, bedding, installation, testingCompleted before the ground freezes

Phasing the mechanical plant with power and IT load

Phasing an Idaho data center’s mechanical plant follows the power contract and the IT deployment plan, because neither the chillers nor the generators earn anything until power and servers are in place. The first phase builds what every later phase depends on: yard layout, main headers sized for the final build, the central plant building or pads, and the first block of chillers, pumps and dry coolers.

Each later phase adds equipment modules and hall fit-outs that tie into valved connections left in the earlier phase, so live systems are never drained to add capacity. Paul Industries plans those tie-in points at design, prefabricates the connecting spools and tests each addition before it is opened to the live system. Generator yards follow the same modular approach, with fuel and exhaust systems laid out for the final count. The result is a campus that grows in step with Idaho Power’s deliveries without a shutdown of the halls already serving customers.

Long-lead equipment and the 2027 refrigerant limit

Long-lead mechanical equipment for an Idaho campus, such as large chillers, CRAC and CRAH units, dry coolers and generators, is ordered many months before it is set, so procurement has to look past the delivery date to the rules in force when the unit arrives. The EPA’s Technology Transitions rule caps refrigerant global warming potential at 700 for data center, computer room and IT equipment cooling from January 1, 2027.

Paul Industries writes compliant refrigerants into the equipment schedules, confirms manufacturing dates against the rule with each supplier, and records refrigerant type and charge for every unit in the turnover package. Releasing orders by phase keeps later phases free to use newer equipment while the first phase arrives on time.

Generators, fuel and air permits

Generator systems on an Idaho data center are mechanical work as much as electrical: fuel storage and piping, day tanks, exhaust and silencers, jacket water and radiator cooling, and ventilation of enclosures all sit in the mechanical package. Under Idaho DEQ’s air rules, a generator yard either qualifies for the exemption written for engines used only in emergencies and kept below 500 operating hours annually, or it goes through a permit to construct before work begins.

Fuel choice, engine count, run-hour limits and stack heights therefore get settled early, before equipment is ordered. Engine and radiator output falls with elevation, so generator selections are corrected for the site. Paul Industries designs and installs fuel, exhaust and cooling systems for the generator yard and prepares the mechanical data the air permit application needs.

What does a data center mechanical package cost in Idaho?

A data center mechanical package in Idaho is priced on the IT load and density, the cooling arrangement, redundancy, the generator count and fuel system, the number of phases and the site’s elevation and climate. Prefabrication, the sales tax treatment of equipment and the season in which yard work falls all move the number.

  • Plant: chillers, dry coolers or towers, pumps, headers and controls.
  • Distribution: chilled water and warm-water mains, CDUs and secondary piping.
  • Air side: air handlers, fan walls or indirect evaporative units corrected for altitude.
  • Generators: fuel storage and piping, exhaust and cooling.
  • Climate: glycol, heat tracing, insulation and winter protection.
  • Phasing: valved stub-outs, tie-ins and repeated testing.
  • Tax: documentation for purchases under Idaho Code 63-3622VV.

Running cost follows energy. Idaho’s 2025 industrial electricity averaged 7.88 cents per kilowatt-hour against 8.51 nationally, and commercial 9.29 against 13.37, according to the EIA, so a mechanical design that trims cooling energy pays back at Idaho rates as well as elsewhere. Early budgets come from comparable Paul Industries scopes, and the firm price follows when a phase is defined.

Who builds data center mechanical systems in Idaho?

Paul Industries builds data center mechanical systems in Idaho, from central plants and generator yards to liquid cooling loops in the halls, for owners from Caldwell and Kuna to Rexburg, and from the Magic Valley north to Post Falls. Paul Industries has its headquarters at 256 Shore Drive, Kilmarnock, Virginia, and takes work across Idaho, in all 50 states and at plants outside the United States through its international work.

When owners compare data center mechanical contractors, the questions that matter in Idaho are how phasing will follow the power contract, how the sales tax records will be kept, how winter will be handled on yard work, and how altitude corrections show up in submittals. Paul Industries answers each in its proposal. Mechanical contractors in Idaho also differ on prefabrication; Paul Industries fabricates spools and skids off site and welds to ASME B31.9 and B31.3 with structural steel to AWS D1.1. Related Idaho pages go deeper on single systems: heat rejection and air handling on data center cooling in Idaho, rack-level loops on data center liquid cooling in Idaho, startup and integrated tests on data center commissioning in Idaho, and welded mains on process piping in Idaho and industrial welding in Idaho. For comparison, see the headquarters-state page, data center mechanical contractors in Virginia, and data center mechanical contractors in Texas.

Paul Industries on Idaho data center campuses

For an Idaho data center, Paul Industries takes the mechanical package by the route the owner chooses: equipment supply, design-build, or complete installation with testing, startup and service. Scope covers the central plant, distribution piping, air handling, liquid cooling, generator mechanical systems, controls and maintenance after turnover. The Idaho page gathers Paul Industries’ work in the state. Send the campus plan, phase dates, IT load and power contract schedule, and request a quote.

Standards referenced: Idaho Code 54-5204 (Idaho Contractor Registration Act) · Idaho Code 54-5008 and 54-5016 (HVAC certificates and permits) · Idaho Code 54-1902 (public works contractors) · Idaho Code 63-3622VV (data center sales tax exemption) · 2018 International Building Code and 2018 International Mechanical Code with Idaho amendments · 2017 Idaho State Plumbing Code · IDAPA 58.01.01 (air permits to construct) · ASME B31.9 · ASME B31.3 · AWS D1.1

Frequently asked questions

Who builds data center chiller plants in Boise, Meridian and Kuna?

Paul Industries builds data center chiller plants, dry cooler yards and chilled water distribution in Boise, Meridian, Kuna and Nampa. Plants are laid out for the full campus and installed in phases that follow the power contract, with spools and skids fabricated off site to shorten field work.

Who handles mechanical work for eastern Idaho data halls?

Paul Industries builds data center mechanical systems in Idaho Falls, Pocatello and across eastern Idaho, with glycol outdoor loops, heat tracing and insulation for the long freeze season and equipment selections corrected for elevations above 4,400 feet. Yard work is scheduled into the warm months.

What data center opened in Kuna, Idaho?

Meta announced in September 2026 that its Kuna Data Center is online and operational. Meta lists the project at more than $1.2 billion of investment, with ground broken in 2022 and about 100 operational jobs once complete. The campus is a market example of the scale the Treasure Valley can host.

Does Idaho's sales tax exemption cover data center chillers?

Idaho Code 63-3622VV lists chillers and generators within eligible server equipment and also exempts new data center facilities, for qualifying business entities and contractors building for them. Qualification requires $250 million of investment within five years and 30 new jobs. Purchases must be documented to the exempt facility.

Does a contractor need to register to work on an Idaho data center?

Idaho Code 54-5204 requires registration under the Idaho Contractor Registration Act to act as a contractor in the state, and HVAC work requires a state certificate of competency under 54-5008. Public works projects need a public works contractor license. Paul Industries builds these requirements into its compliance plan.

Is there a prevailing wage on Idaho data center projects?

Private Idaho projects carry no state wage schedule, since the state law was repealed in 1985 according to federal labor records. Projects with federal funding carry federal wage requirements in their contracts. Private data center projects follow the wage terms of their own contracts.

How do data centers planned for Idaho get their power?

Customers above 20,000 kilowatts take service under a special contract reviewed by the state commission, and the contract sets when power blocks arrive. Paul Industries phases chillers, generators and halls to those dates, with headers and yards laid out for the final build.

Which codes govern data center mechanical work in Idaho?

The 2018 International Mechanical Code and Fuel Gas Code with Idaho amendments, the 2017 Idaho State Plumbing Code, the 2023 National Electrical Code with amendments, the 2018 International Fire Code and the 2018 IECC, whose amendment exempts spaces cooled only for electronic equipment. A move to 2024 editions has been in preparation.

Do data center generators in Idaho need an air permit?

That depends on how the engines are used and run. Engines reserved for emergencies, burning a listed fuel and kept below 500 hours a year, fall under an exemption in IDAPA 58.01.01 if the yard also meets the rule’s general tests. Yards outside it obtain a DEQ permit to construct before work starts.

How does winter affect data center construction in Idaho?

Freezing nights limit yard piping, underground work, crane lifts and roof equipment to the warmer months, especially in eastern Idaho. Paul Industries prefabricates spools and skids off site, tests and protects piping before freezes, and keeps interior work moving through winter.

Can an existing Idaho data center add capacity without a shutdown?

Yes, when the original plant left valved connections for expansion. Where it did not, hot taps, line stops or carefully staged tie-ins add capacity while live halls keep running. Paul Industries plans each tie-in with the operator and tests new sections before opening them to the live system.

What is the difference between data center mechanical and electrical scope?

Mechanical scope covers cooling plants, piping, air handling, liquid cooling, generator fuel, exhaust and cooling systems, and controls; electrical scope covers power distribution, switchgear, UPS and wiring. The two meet at equipment connections and controls. Paul Industries matches every mechanical connection to the electrical drawings.

How many months does the mechanical package for an Idaho hall run?

Duration depends on the campus size, phasing, equipment lead times and power dates. A single hall’s mechanical package can run many months from award to integrated testing, while campuses build in repeating phases over years. Season matters in Idaho, so yard work is placed in warm months.

Why do altitude corrections matter for Idaho mechanical equipment?

Thinner high-desert air, roughly 92 percent of sea-level density at Boise and 87 percent near Idaho Falls, cuts the capacity of air-cooled equipment, dry coolers and generator radiators. Selections are corrected for the site so the plant performs as designed on the hottest day.

What does a data center mechanical contractor cost in Idaho?

Price follows IT load, density, cooling arrangement, redundancy, generator count, phasing and climate protection. Sales tax treatment under 63-3622VV can change the equipment budget for qualifying owners. Paul Industries gives a budget range early and a firm price on the defined phase.

Which details start a mechanical estimate for an Idaho campus?

The campus plan and phases, IT load and density by phase, cooling concept if chosen, generator count and fuel, the power contract schedule, site elevation and whether the owner is qualifying under the sales tax exemption. Paul Industries returns a scope, budget and schedule.

Planning a data center campus or hall in Idaho?

Send the campus plan, IT load by phase, power contract dates and site elevation. Call 201-450-8280 or request a quote.