Paul Industries carries out data center commissioning in Washington for cooling plants, liquid cooling loops and mechanical systems, from pressure testing and flushing through startup, functional testing and the records the state energy code requires before final inspection. Washington writes commissioning into its energy code, so a data hall in Quincy, Moses Lake, East Wenatchee or Seattle reaches final inspection only after a commissioning report reaches the owner. Paul Industries plans the mechanical side of that process from the first pipe test to the last signed checklist.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Energy code 2021 WSEC commercial, Section C408 commissioning, effective March 15, 2024
Final inspection Held until the owner confirms receipt of the Commissioning Report
Refrigerant program Chillers over 50 lb of GWP 150+ refrigerant registered with Ecology
Hydronic test 1.5 x design pressure, at least 100 psi for 15 minutes (IMC 1208.1)
Reviewed November 2026

What does data center commissioning in Washington require by code?

Data center commissioning in Washington is required by Section C408 of the 2021 Washington State Energy Code, which took effect on March 15, 2024 and makes building owners put mechanical, refrigeration, metering, lighting control and service water heating systems through a commissioning process that includes functional tests. The process must be led by a commissioning professional who meets the code’s certification requirement, and it has to be described in the construction documents before the work is bid.

Small buildings are exempt, but the thresholds are tiny next to a data hall. Section C408.2 lets mechanical systems skip the process only when the building’s installed cooling stays under 240,000 Btu per hour, roughly 20 tons, and its heating under 300,000. Every data center cooling plant in the state is far above that line, so Washington treats commissioning as part of getting the building approved rather than as an optional quality step. The national picture of levels, scripts and roles is on the data center commissioning page; this page covers what Washington adds.

The data center commissioning process under Washington’s energy code

The data center commissioning process under Washington’s energy code starts with commissioning provisions in the construction documents and ends with a signed report in the owner’s hands and a transmittal letter on the building official’s desk. In between, the code sets out what the plan must contain, how many systems must be tested and what the final report has to show.

  • Construction documents. A narrative of commissioning activities, the commissioning professional’s role and qualifications, and the list of equipment and systems to be tested (C408.1.1).
  • Commissioning plan. Organization, schedule, resources, documentation, the team’s roles and a description of each test (C408.1.2).
  • Disclosure plan. Where the commissioning professional is contracted through someone other than the owner, a disclosure and conflict management plan shows that issues can be reported straight to the owner (C408.1.2.1).
  • Functional performance testing. Written procedures with acceptance criteria, actual results and calibrated controls (C408.1.2.2).
  • Deficiencies. Corrected and retested before acceptance (C408.1.2.4).
  • Commissioning report. Test results, deficiency dispositions, procedures, the plan and the testing, adjusting and balancing report, with mechanical findings in their own section (C408.1.3).

Paul Industries works inside that structure as the contractor that builds, starts and proves the mechanical systems. Its startup records, pressure tests, flushing logs and balancing data become sections of the report, and its technicians run the functional tests alongside the data center commissioning agent who leads the process.

How Washington’s functional tests line up with commissioning data center levels

Washington’s functional tests line up closely with the industry’s commissioning data center levels, because Section C408.2.3 requires mechanical systems to be tested at full load and part load, in every mode of the sequence of operation, in redundant or automatic backup mode, for alarm performance and through a loss and restoration of power. Those last three conditions are the heart of Level 4 functional testing and Level 5 integrated systems testing on any data center.

Commissioning levels and the Washington energy code requirements they satisfy
LevelTypical scopeWashington code linkRecords Paul Industries supplies
Level 1: factory testingWitness tests of chillers, CDUs, air handlers, pump skidsSupports the equipment list and performance data in the commissioning planFactory test reports, nameplate data, refrigerant charge
Level 2: delivery and installationReceipt inspection, setting, anchorage, piping and wiring checksSeismic anchorage and installation per the Washington State Building Code and Mechanical CodeInstallation checklists, anchorage photos, torque and weld records
Level 3: startup and prefunctionalPressure test, flush, fill, rotation, first runs, controls point checksHydronic pressure test under the state mechanical code; balancing under C408.2.2Pressure test certificates, flushing logs, startup sheets, TAB data
Level 4: functional performanceEach system tested through its sequencesC408.2.3 full load, part load, all modes, alarmsCompleted test scripts with acceptance criteria and results
Level 5: integrated systemsUtility failure, generator pickup, cooling restartC408.2.3 redundant mode and loss and restoration of powerTrend data, restart timing, deficiency log and retests

Sampling, deficiencies and the size of a Washington test program

Sampling rules in Section C408.1.2.3 set the size of a Washington test program on large campuses, where dozens of identical air handlers, CDUs or pumps would otherwise each need a full functional test. Projects with seven or fewer similar systems test every one; larger projects test each unique combination of control types and at least 20 percent of each combination, and if 30 percent or more of the tested units fail, every remaining identical unit is tested.

That 30 percent trigger rewards careful installation. A hall with a recurring wiring or sensor error can turn a sampled test program into a full one, which costs days on a tight turnover. Paul Industries runs its own prefunctional checks on every unit before the sampled tests begin, so that the units the commissioning team picks behave like the rest.

Pressure testing and flushing under the Washington State Mechanical Code

Pressure testing of data center cooling water piping in Washington follows the International Mechanical Code as adopted through chapter 51-52 WAC, where Section 1208.1 calls for hydronic piping to be tested hydrostatically at one and a half times the maximum design pressure, at no less than 100 psi, for at least 15 minutes. Larger campus mains are often tested to the project’s ASME B31.9 or B31.3 specification as well, and the stricter of the two requirements governs.

Flushing follows the pressure test. Paul Industries flushes each loop at velocity through temporary strainers with sensitive equipment bypassed, checks turbidity and particle counts against the specification, then fills with treated water or glycol. On Columbia Basin sites the fill water itself needs treatment, because groundwater there is high in hardness and silica; a loop flushed with untreated well water can start its life with scale already forming.

Winter testing needs its own plan east of the Cascades. A hydrostatic test left full of water in an unheated shell or an outdoor pipe rack can freeze overnight, so Paul Industries schedules outdoor tests for daylight hours, drains or blows down test sections before nightfall, or tests with a glycol mix where the specification allows. Test gauges, recorders and relief settings are listed on each certificate, so the building inspector and the commissioning team can see exactly how each section was proven.

Data center commissioning in Quincy, Moses Lake and the Columbia Basin

Data center commissioning in Quincy and across the Columbia Basin runs on campuses that are built in phases, with new halls turned over beside buildings that are already running. The state’s 2025 Data Center Workgroup found that seven of the ten highest assessed properties in Grant County are data centers, six in Quincy and one in Moses Lake, which gives a sense of how much live load surrounds each new turnover.

Phased campuses change how integrated testing is done. A Moses Lake data center expanding into a new hall has to keep power on in its operating buildings while the new one is tested, so the new hall’s utility failure test is staged on its own switchgear, with tie-ins to shared chilled water mains isolated and proven first. Paul Industries plans those boundaries with the owner and the commissioning team, so that each test proves the new systems without putting the existing halls at risk.

Weather is the other Basin factor. Moses Lake’s July normals run to a 90 degree high, and winters bring hard freezes, so a January turnover leaves the summer peak test for July, and an August turnover leaves the freeze protection test for the first cold snap. The energy code allows tests that climatic conditions prevent to be deferred and recorded in the report; Paul Industries lists those deferred tests with their target dates and returns to run them in the right season.

Generators, refrigerants and other Washington checks before turnover

Generators, refrigerants and water systems bring extra Washington checks before a data hall is turned over, because each is regulated by the Department of Ecology as well as by the building code. Integrated tests that start emergency engines need to fit within the site’s air permit conditions, and the state’s Data Center Workgroup reported in 2025 that Ecology was developing a general order for data center emergency engine operations. Test hours for load bank and utility failure tests are therefore planned and logged rather than run open-ended.

New chillers bring Refrigerant Management Program duties from their first day. A plant holding more than 50 pounds of a refrigerant with a GWP of 150 or more must be registered with Ecology, inspected for leaks on the schedule for its size category, repaired within 14 days of any leak and supported by five years of records. Paul Industries records the refrigerant type and charge at startup, performs and documents the first leak inspection, and hands the owner a ready-to-file record set.

Many new chillers use A2L refrigerants, and the State Building Code Council has adopted and repeatedly extended emergency amendments to chapter 51-52 WAC since 2025 to coordinate the mechanical code with ASHRAE 15 for those refrigerants. Refrigerant detectors, alarms and machinery room ventilation are tested as part of the cooling plant’s functional tests, with the response to a detected leak demonstrated at the building management system.

A data center commissioning checklist for a Washington cooling plant

A data center commissioning checklist for a Washington cooling plant should cover the mechanical code tests, the energy code functional tests and the state’s refrigerant and climate concerns in one sequence, so that nothing is left for the week before occupancy.

Washington cooling plant commissioning checklist
StageCheckWashington reason
Before testingCommissioning plan accepted; disclosure plan in place where neededC408.1.2 and C408.1.2.1
PipingHydrostatic test at 1.5 times design pressure, minimum 100 psi, 15 minutes or project specificationIMC 1208.1 as adopted by chapter 51-52 WAC
WaterFlush to cleanliness target; treated fill water; glycol concentration for outdoor loopsHard Basin groundwater; freezing winters east of the Cascades
RefrigerantCharge recorded; first leak inspection; detectors and ventilation testedEcology Refrigerant Management Program; A2L amendments to the mechanical code
BalancingAir and hydronic balancing to specification tolerancesC408.2.2
Functional testsFull and part load, all modes, redundancy, alarms, power loss and restorationC408.2.3
Energy calculationAs-built equipment data matched to the ASHRAE 90.4 calculationC403.1.3
SeasonalDeferred summer or winter tests listed with datesException in C408.1.3 for climatic conditions
Close-outReport delivered; owner’s transmittal letter or compliance checklist to the building officialC408.1.4.1

Data center commissioning in Seattle and existing buildings

Data center commissioning in Seattle and other Puget Sound cities usually means proving new equipment inside a building that is already running, because Seattle paused new large data centers for a year in June 2026 and most of the region’s computer rooms sit in established buildings. A chiller replacement, a new waterside economizer or a row of liquid-cooled racks is an alteration under the energy code, and the altered systems are commissioned before the work is accepted.

Testing in an occupied building is planned around the operator’s change windows. Paul Industries writes a method of procedure for each test that touches live systems, confirms redundancy before anything is placed in a failure mode, and keeps temporary cooling ready where a test could reduce capacity. The phased acceptance allowed by Section C408.1.4.1 lets an alteration be accepted trade by trade, which suits buildings where work continues for months.

Commissioning liquid cooling loops in Washington halls

Commissioning liquid cooling loops in Washington halls adds steps that an air-cooled hall never needed: cleanliness and chemistry targets for the technology cooling system, CDU control tests, leak detection proof and a heat load test before any server connects. Cold plates hold only seconds of thermal reserve, so the response of each CDU to a pump failure, a valve closure or a loss of power is tested as carefully as the chiller plant behind it.

On Columbia Basin campuses the outdoor side of a liquid system is usually a glycol loop to dry coolers, and its freeze protection is proven with a measured concentration and an inhibitor test rather than assumed from the fill record. Paul Industries flushes and fills each loop, wets every leak sensor to prove alarms and isolation, runs load banks or heat load units to the design heat rejection, and records supply temperature stability through each failure test. The results become the liquid cooling section of the commissioning report.

Recommissioning older Columbia Basin and Seattle halls

Recommissioning older Columbia Basin and Seattle halls is often the first step before adding density, because many of the buildings put up after 2006 have sequences, setpoints and sensors that have drifted through years of changes. A recommissioning program tests what the plant does today against what the owner needs it to do next, and finds the gaps before new load arrives.

Paul Industries starts with the existing records, the controls database and trend logs, then field-verifies sensors, valves and sequences, retests redundancy and power restoration, and rebuilds missing pressure test, balancing and refrigerant records. Where an energy code alteration follows, the recommissioning results become the baseline for the new commissioning plan.

Roles in a Washington data center commissioning program
PartyRole under Washington rulesWhat Paul Industries provides to it
OwnerReceives the commissioning report and sends the transmittal letter or compliance checklist to the building officialThe mechanical records, as-builts and training the report and turnover depend on
Commissioning professionalLeads the process, writes the plan and certifies the report under C408Test readiness, test labor, startup data, deficiency corrections and retests
Design engineerSets sequences and the ASHRAE 90.4 calculation for C403.1.3As-built equipment data and confirmed setpoints
City or county building officialHolds final inspection until commissioning is acknowledged; may request the reportPressure test certificates and inspection-ready installations
Department of EcologyRuns the Refrigerant Management Program and engine and water permitsRefrigerant charge records, first leak inspection, test run logs

Controls and trend reviews after turnover

Controls and trend reviews after turnover catch the problems that functional tests miss, because a Washington cooling plant only meets its full range of weather over a year. A plant that tested well in a mild spring may hunt between economizer and mechanical cooling on its first 90 degree afternoon, or short-cycle on the first cold night.

Paul Industries reviews trends with the operator after the first summer and the first winter, adjusts setpoints within the design intent, and records each change in the controls documentation so that the commissioning report and the running plant stay in step.

Data center commissioning schedule in Washington

A data center commissioning schedule in Washington is set by equipment delivery, the season, the utility’s energization date and the time needed to correct deficiencies, and commissioning activities begin long before the last test. Factory tests run while the building is still being framed; pressure tests and flushing start as soon as piping sections are complete; startup follows permanent power; functional and integrated tests fill the final weeks before occupancy.

Two Washington factors deserve their own allowance: seasonal tests that may move a few months, and the time for the building official to receive the commissioning transmittal before the final mechanical inspection. Paul Industries builds both into its own schedule, so that test readiness, rather than paperwork, sets the turnover date.

What does data center commissioning cost in Washington?

Data center commissioning cost in Washington depends on the number of systems and their sampling plan, the commissioning levels in the contract, load bank and generator hours, seasonal retests and how much of the work happens inside operating buildings. The mechanical contractor’s share covers pressure testing, flushing, startup, balancing support, functional test labor, temporary equipment and records.

Location shifts the mix. A Columbia Basin campus spends more on seasonal retests, glycol verification and phased isolation of shared mains, while a Seattle alteration spends more on method of procedure writing, night work and temporary cooling during tests. Generator hours, load bank rental and the number of sampled units are the other large variables, and each is fixed once the commissioning plan is agreed.

Paul Industries prices commissioning as part of the mechanical scope or as a separate package for an existing installation. It gives a budget range from comparable work when it receives the equipment list, sequences and phasing, and a firm price once the commissioning plan is set.

Who commissions data center cooling systems in Washington?

Paul Industries commissions data center cooling systems in Washington, building, testing, starting and proving chilled water plants, evaporative systems, dry coolers, liquid cooling loops and their controls for campuses in Quincy, Moses Lake, East Wenatchee and Malaga and for rooms in Seattle, Tukwila and Spokane. Headquartered at 256 Shore Drive, Kilmarnock, Virginia, Paul Industries takes commissioning work across the state of Washington and in every other state, and on projects abroad.

Owners can bring Paul Industries in as the mechanical contractor whose startup and testing feed the commissioning report, on a design-build basis for the cooling plant and its commissioning, or to recommission an existing system and rebuild missing records. The commissioning program connects to the plant described under data center cooling in Washington, the loops on the data center liquid cooling in Washington page, the wider build covered under data center mechanical contractors in Washington, and the regulated clean utility work on validation and commissioning in Washington.

Commissioning Washington data halls with Paul Industries

Paul Industries supplies, installs, pressure tests, flushes, starts up and commissions data center mechanical systems across Washington, with the records the energy code, the mechanical code and Ecology expect. Related services include hydrostatic testing and the cooling plant repairs on chiller repair in Washington. For the same service in the headquarters state, see data center commissioning in Virginia; for another western code, see data center commissioning in California, along with the West Coast and Washington pages. Send the equipment list and sequences and request a quote.

Standards referenced: Washington State Energy Code, commercial provisions, Section C408 (chapter 51-11C WAC) · Washington State Mechanical Code (chapter 51-52 WAC, 2021 International Mechanical Code) · ASHRAE 90.4 · ASHRAE Guideline 0 · ASHRAE 15 · ASME B31.9 · Chapter 173-443 WAC, Refrigerant Management Program

Frequently asked questions

Who handles data center commissioning in Quincy and Grant County?

Paul Industries handles the mechanical commissioning of data halls in Quincy and across Grant County, including pressure testing, flushing, startup, balancing support, functional tests and integrated tests for chilled water plants, evaporative systems and liquid loops. Phased campuses are tested building by building with tie-ins to shared mains isolated first. The records go into the commissioning report the Washington energy code requires.

Who commissions data center cooling in Seattle, Tukwila and Bellevue?

Paul Industries commissions new and altered cooling systems in data rooms across Seattle, Tukwila, Bellevue and the rest of the Puget Sound area. Most of that work happens in operating buildings, so each test has a written method of procedure, confirmed redundancy and temporary cooling where needed. Altered systems are commissioned under Section C408 before the work is accepted.

How to commission a data center under the Washington State Energy Code?

Commissioning a data center under the Washington State Energy Code means writing commissioning into the construction documents, naming a commissioning lead who holds the certification the code calls for, preparing a commissioning plan, running functional tests including redundancy, alarms and power loss, correcting deficiencies and delivering a commissioning report to the owner before final inspection. Paul Industries carries out the mechanical tests and supplies the records each step needs.

What does a Moses Lake data center need to prove before final inspection?

A Moses Lake data center must show that its mechanical systems passed functional testing at full and part load, in every sequence mode, in backup mode, for alarms and through a loss and restoration of power. The building official then needs the owner’s letter confirming receipt of the commissioning report, or the completed compliance checklist. Tests that winter or summer conditions prevent are recorded as deferred.

Does Washington's energy code require a commissioning agent on data centers?

Section C408 requires the commissioning process to be led by a commissioning professional meeting the code’s certification requirement, which on data centers is usually the owner’s commissioning agent. Where that person is contracted through anyone other than the owner, the plan must include a disclosure and conflict management plan. Paul Industries works with the agent as the contractor that builds, starts and tests the mechanical systems.

How many identical air handlers or CDUs must be tested in a Washington data hall?

Under Section C408.1.2.3, projects with seven or fewer similar systems test every one, while larger projects test each unique combination of control types and at least 20 percent of each. If 30 percent or more of the tested units fail, all remaining identical units are tested. Careful prefunctional checks on every unit protect the sampled program.

What pressure test applies to chilled water piping in a Washington data center?

The International Mechanical Code, as adopted in Washington through chapter 51-52 WAC, calls for hydronic piping to be tested hydrostatically at one and a half times the maximum design pressure, at least 100 psi, for at least 15 minutes. Project specifications often add longer hold times or B31.9 and B31.3 requirements, and the stricter rule governs. Paul Industries records each test on a certificate signed by the witnesses.

Can commissioning tests be deferred for Washington weather?

The energy code allows tests that climatic conditions prevent to be deferred and noted in the commissioning report. In eastern Washington that usually means summer peak tests for halls turned over in winter, or freeze protection tests for halls turned over in summer. Paul Industries lists each deferred test with a target date and returns to complete it.

How are generator tests limited during Washington data center commissioning?

Generator runs for load bank and utility failure tests must fit the site’s air permit conditions, and Ecology was developing a general order for data center emergency engine operations according to the state’s 2025 Data Center Workgroup. Integrated tests are therefore planned to use as few engine hours as possible, with each run logged. Paul Industries plans mechanical test steps to fit those limits.

Do new data center chillers in Washington need Ecology paperwork at startup?

New chillers holding more than 50 pounds of refrigerant with a GWP of 150 or more fall under Ecology’s Refrigerant Management Program, with registration, scheduled leak inspection, 14-day leak repair and five years of records. Paul Industries records refrigerant type and charge at startup, performs the first leak inspection and gives the owner the records needed to register and report.

How are A2L refrigerant detectors tested in a Washington chiller plant?

Refrigerant detectors in a Washington chiller plant are tested by exposing each sensor to calibration gas and confirming that the alarm sounds, the machinery room ventilation starts and the building management system records the event. Washington’s mechanical code amendments for A2L refrigerants coordinate these requirements with ASHRAE 15. Paul Industries includes those tests in the cooling plant’s functional test scripts.

Which turnover documents go into the mechanical section of a Washington commissioning report?

The owner receives pressure test certificates, flushing and water quality logs, startup sheets, balancing reports, completed functional and integrated test scripts, the deficiency log with retests, refrigerant records, controls settings, as-built drawings and operating manuals. Those documents form the mechanical section of the commissioning report the code requires. Paul Industries assembles them in a consistent format across every phase.

Can an existing Washington data hall be recommissioned after adding liquid cooling?

An existing Washington hall can be recommissioned after adding liquid cooling, and the altered systems fall under the energy code’s commissioning requirements. Paul Industries tests the new loop, its CDUs and leak detection, and retests the parts of the existing plant whose sequences or loads changed, including redundancy and power restoration. Missing records from the original turnover can be rebuilt at the same time.

When should the mechanical contractor join a Washington commissioning program?

The mechanical contractor should join before equipment is ordered, so that factory tests, test ports, flushing connections and bypasses are designed in rather than added later. On Washington projects early involvement also lets the team plan seasonal tests and generator hours. Paul Industries reviews the commissioning plan at that stage and builds its test readiness into the construction schedule.

How long does data center commissioning take in Washington?

Mechanical commissioning on a Washington data hall usually runs through most of construction, with the most intensive period covering the final weeks of startup, functional testing and integrated testing. Seasonal tests can add a short visit months later. The duration depends on the number of systems, sampling, phasing and the energization date. Paul Industries gives a schedule with the commissioning plan.

What should a Washington owner send to scope mechanical commissioning?

Send the mechanical drawings and equipment list, sequences of operation, the commissioning plan or specification, the phasing and energization dates, generator and permit limits, and any existing records for buildings that are already running. With that, Paul Industries returns a commissioning scope, schedule and budget range, then a firm price once the plan is set.

Commissioning a data center cooling plant in Washington?

Send the equipment list, the sequences of operation, the commissioning specification and the phasing plan with energization dates. Call 201-450-8280 or request a quote.