Paul Industries designs, fabricates, installs and maintains plants for data center cooling in Alaska, building economizer-first chilled water, glycol and dry cooler systems that hold server inlet temperatures through Anchorage summers and Fairbanks winters. Alaska turns the usual data hall problem upside down: outdoor air is cold enough to carry most of the heat for most of the year, so the hard engineering is freeze protection, humidity control and recovering waste heat for buildings that need heating nine months a year. Paul Industries carries the plant from design through startup, and supplies equipment on its own where an owner already has a design.
Request a quote or call 201-450-8280
What does data center cooling in Alaska have to deliver?
Data center cooling in Alaska has to deliver a steady server inlet temperature from outdoor conditions that swing from summer afternoons in the seventies to winter nights far below zero, using as little purchased electricity as possible in a state where every kilowatt-hour costs well above the national average. A hall in Anchorage, Fairbanks or Juneau has the same internal heat as a hall anywhere else: almost every watt drawn by the servers ends up as heat in the room. What changes is the outside half of the system, where the heat is rejected, and how many hours of the year a compressor has to run at all.
For a cooling plant designer the Alaska brief therefore reads differently from a Gulf Coast or Mid-Atlantic one. The design questions become: how to keep glycol and water from freezing in exposed coils, how to temper air that is too cold and too dry to put straight onto servers, how to shed snow and frost from heat rejection equipment, and where to send the heat that would otherwise be thrown away. The national principles are covered on the data center cooling systems page; this page goes into what Alaska weather, power, codes and logistics add.
How cold are data centers in Alaska, and how cold is the air outside them?
Data halls in Alaska run the same supply air range as halls elsewhere, while the air outside them sits below the recommended server inlet range for much of the year. ASHRAE’s recommended inlet envelope for most server classes runs from 18 to 27 degrees Celsius (64.4 to 80.6 degrees Fahrenheit), and the NOAA normals for Alaska’s main cities show how seldom outdoor air climbs above it.
| City | July normal high | January normal low | Annual cooling degree days (base 65 F) | Cooling plant consequence |
|---|---|---|---|---|
| Anchorage | 66.2 F | 11.0 F | 7.6 | Outdoor air or glycol free cooling carries nearly the whole year; compressors trim summer peaks |
| Fairbanks | 72.7 F | Minus 17.2 F | 68.2 | Warmer summers than the coast and deep winter cold; freeze protection and air tempering dominate the design |
| Juneau | 64.0 F | 23.8 F | 3.1 | Mild, wet maritime air; moisture management and corrosion control matter more than cold |
Anchorage’s July normal high of 66.2 degrees Fahrenheit sits barely above the bottom of the ASHRAE recommended band, which is why air-side economizer halls there spend more effort warming and mixing outdoor air than cooling it. Fairbanks is the interior exception: its July normal high is 72.7 degrees, and its warmest afternoons run well above the normal, so a Fairbanks plant still needs sized mechanical cooling for the design day even though it will run that equipment for a small share of the year. Normals are averages, so every Alaska plant is sized on design-day conditions rather than on the July mean.
Data center cold aisle temperature in an Alaska hall
A sensible data center cold aisle temperature for an Alaska hall is the same as anywhere: most operators hold supply air in the low to mid seventies Fahrenheit, inside the ASHRAE recommended band, with containment keeping hot exhaust out of the cold aisle. The difference in Alaska is the direction of the control problem. On a January night the economizer dampers or the glycol bypass valves are working to keep the cold aisle from falling too low, and a controls fault that would overheat a hall in Texas tends to overcool one in Fairbanks. Low-limit alarms, mixing dampers that fail to a safe position and freeze stats on every coil are part of the base design from the first drawing.
Are there data centers in Alaska?
Alaska has data centers today, most of them enterprise, carrier and public sector rooms serving the state’s telecommunications networks, hospitals, government agencies, utilities, military installations and the university system, along with colocation space in Anchorage. Large hyperscale campuses of the kind built in Virginia, Texas and Oregon have so far stayed proposals in Alaska, and the state and Anchorage have both started writing rules for them.
Three recent developments define the market for proposed data centers in Alaska. In March 2026 the Anchorage Assembly adopted ordinance AO 2026-27, which gives data centers of 20 megawatts or more peak demand their own land use category, keeps them out of residential zones, requires conditional use approval and asks applicants to show that electric, water and wastewater capacity exists. At the state level, SB 250, a bill on utility service for data centers, passed the Alaska Senate in May 2026 and was last listed in the House Community and Regional Affairs Committee. In November 2026 the Alaska Department of Natural Resources approved a 50-year state land lease for a proposed natural gas powered data center (North Slope, Alaska) near the Dalton Highway, a project that still needs further permits, including a state air quality permit, before construction.
The Anchorage data center ordinance and the cooling plant
For mechanical design, the most practical part of the Anchorage data center ordinance is its utility capacity showing. A data center Anchorage reviewers consider under AO 2026-27 has to show where its power, water and wastewater come from, which favors cooling plants that use little or no evaporated water and that can describe their peak electrical demand with confidence. Closed glycol loops with dry coolers, air-side economizers and chillers sized for a short trim season all make that showing simpler than an evaporative tower plant would.
Why not build data centers in Alaska? The engineering side of the question
People ask why not build data centers in Alaska because the climate looks ideal for cooling, and the honest engineering answer is that cooling is the easy part. Power supply and price, fiber connectivity, construction seasons and freight decide where large campuses go. The cooling plant can be designed to run on free cooling for almost every hour of the year; what it cannot change is the cost of the electricity the servers themselves draw. For an owner who has already settled those questions, a data center Alaska’s Railbelt utilities can serve rewards a cooling design that leans hard on outdoor air and glycol and treats compressors as summer backup.
How are data centers kept cool in Alaska’s climate?
Data centers in Alaska are kept cool with the same three families of systems used elsewhere, chosen and arranged for cold: air-side economizers that bring filtered, tempered outdoor air into the hall; water-side economizers that use a glycol loop and dry coolers to chill water without compressors; and mechanical chillers or direct expansion units that carry the warmest hours. Data centers in cold climates usually combine two of the three so that a single failure never leaves the hall without a path to reject heat.
| Arrangement | How it works in Alaska | Strengths | Alaska design watch points |
|---|---|---|---|
| Air-side economizer with mixing | Outdoor air is filtered, mixed with warm return air and delivered to the cold aisle | Least fan and compressor energy for most of the year | Snow and ice at intakes, very dry winter air, smoke and dust events, filter frosting |
| Water-side economizer with glycol dry coolers | A glycol loop rejects heat to outdoor coils and cools the chilled water through a plate heat exchanger | Keeps outdoor air out of the hall; works with chilled water and liquid cooling | Glycol concentration for the coldest site temperature, coil defrost and snow clearance |
| Data center air cooled chiller with integral free cooling | Packaged chiller with free cooling coils that bypass the compressors in cold weather | Compact plant; one machine covers summer and winter modes | Low-ambient controls, crankcase heaters, glycol in the outdoor circuit |
| Water-cooled chillers with towers | Evaporative towers reject heat in summer; plate exchangers give free cooling in winter | Efficient on the warmest days | Tower basin freezing, plume icing, water and wastewater capacity under municipal review |
| Direct expansion computer room units | Refrigerant-based units with outdoor condensers, sometimes with pumped refrigerant economizers | Simple for small enterprise rooms | Low-ambient head pressure control and the 2027 refrigerant limit for new equipment |
For most new Alaska halls above a few hundred kilowatts, Paul Industries starts the comparison with a glycol water-side economizer feeding chilled water or liquid cooling distribution, backed by compressors sized for the design day. Air-side economizers win on energy where the building and the site allow large intakes and the owner accepts humidification and filtration duty. The choice is made on the owner’s load, redundancy level and site, priced both ways, rather than by habit.
Keeping heat rejection running through an Alaska winter
Heat rejection in an Alaska winter fails in predictable ways: glycol mixed too weak for the coldest night, coils buried by drifting snow or coated in frost, fans iced to their shrouds, and condensate or tower water left standing in a line that freezes. Each failure has a design answer, and the answers are cheaper to build in than to retrofit after the first January.
- Glycol strength. The outdoor loop carries propylene or ethylene glycol mixed for burst protection below the site’s extreme minimum, with a written test interval, because a freeze in a dry cooler splits tubes and drains the loop.
- Snow and drift. Dry coolers and condensers sit on raised steel with clearance above the expected snowpack, oriented so prevailing winds do not pack their intakes, with access left for clearing.
- Low-ambient control. Fan speed, glycol bypass and mixing valves keep the loop from overcooling the hall, and compressors that must run in winter have the head pressure controls and heaters to start cold.
- Drainable and traced piping. Exposed water lines are either drainable or traced and insulated, using heat tracing sized for the coldest design temperature rather than an average.
- Air tempering. Outdoor air coils and filters see subzero air; Alaska’s adoption of the mechanical code adds an exception allowing filters downstream of a coil when conditions upstream would degrade performance, which helps where frosting filters are a risk.
The glycol side of the plant is described in more depth on the glycol cooling systems page, and the piping that carries it on process piping in Alaska.
Data center cooling regulations that apply in Alaska
Data center cooling regulations in Alaska come from the state building codes adopted by the Department of Public Safety, federal refrigerant rules from the EPA, and municipal land use rules where a municipality has written them. The state adopts the 2021 International Mechanical Code through 13 AAC 50.023, and plans covering mechanical systems and fuel storage tanks go to the Division of Fire and Life Safety for review under 13 AAC 50.027, except in communities with a deferral that run their own plan review.
| Rule or authority | What it covers | What it means for the cooling plant |
|---|---|---|
| 13 AAC 50.023 (2021 IMC) | Mechanical systems in all occupancies, with Alaska amendments | Refrigeration machinery rooms, ventilation and equipment installation follow the IMC, with refrigerant safety drawing on ASHRAE 15 |
| 13 AAC 50.027 plan review | Plans for mechanical systems, fuel tanks and fire protection before construction | Submittal timing is built into the schedule; deferred communities include Anchorage, Fairbanks, Juneau, Kenai, Kodiak, Ketchikan, Palmer, Seward, Sitka and Soldotna |
| 13 AAC 50.020 (2021 IBC) | Buildings, including construction manufactured off site | Prefabricated cooling modules carry plans sealed by an Alaska registered design professional before they are set on a foundation |
| EPA Technology Transitions | Refrigerants allowed in new equipment | Data center and computer room cooling equipment manufactured or imported from January 1, 2027 uses refrigerant with a GWP of 700 or less |
| EPA leak repair, 40 CFR 84.106 | HFC appliances holding 15 pounds or more, from January 1, 2026 | Leak rate calculated at every refrigerant addition; comfort cooling threshold 10 percent |
| Anchorage AO 2026-27 | Land use for data centers of 20 megawatts or more | Conditional use review and a showing of electric, water and wastewater capacity |
One more feature of the state adoption is worth knowing early: 13 AAC 50.023 deletes the mechanical code’s references to the International Energy Conservation Code, so the efficiency target for a hall reviewed at the state level is usually written into the owner’s basis of design rather than imposed by a state energy code. Paul Industries writes that target into the design documents, so the economizer hours and plant efficiency the owner expects are the ones the controls are tested against.
Electricity prices and the cooling plant’s share of the bill
Electricity prices in Alaska make the cooling plant’s share of the bill a first-order design input: the state’s average commercial price was 22.35 cents per kilowatt-hour in 2025 against 13.37 cents nationally, and the industrial average was 19.86 cents against 8.51, according to the EIA. Natural gas is the state’s primary energy source for electricity, and the Railbelt grid that serves Anchorage, the Mat-Su, the Kenai Peninsula and Fairbanks now has its own electric reliability organization, the Railbelt Reliability Council.
As an illustration, take a 1,000 kilowatt IT load and two cooling designs whose total facility overhead differs by 0.3 in power usage effectiveness, or 300 kilowatts running all year. That difference is 2,628,000 kilowatt-hours annually: about $587,000 at the 2025 Alaska commercial average, against about $351,000 at the national average. The figure uses stated assumptions and a statewide average; Paul Industries runs the same calculation on the owner’s tariff and load profile before recommending a plant. The point holds across Alaska: fan power, pump power and compressor hours all cost more to run here, and economizer hours are worth more.
How much cooling does a data center need?
A data center needs cooling equal to the heat its IT equipment, power distribution losses, lighting and people release into the conditioned space, and the IT load accounts for most of it. One ton of cooling removes 12,000 BTU per hour, or about 3.517 kilowatts, so a hall with 1,000 kilowatts of IT load needs about 284 tons of cooling at the racks before redundancy, losses and growth are added.
In Alaska the sizing exercise has a second half that matters as much as the tonnage: how many of those tons the economizer can carry at each outdoor temperature, and at what outdoor temperature the compressors must start. Paul Industries builds that bin analysis from the site’s weather data and the chosen supply temperature, so the owner sees how many hours a year the plant runs in full free cooling, partial free cooling and mechanical cooling. Raising the chilled water or supply air temperature within the ASHRAE range shifts hours out of the third column and into the first, which is why the supply temperature decision is made at the start of design.
Recovering data hall heat for Alaska buildings
Recovering data hall heat is more valuable in Alaska than in almost any other state, because the buildings around a hall need heat for most of the year. NOAA normals put Anchorage at about 9,979 heating degree days a year and Fairbanks at about 13,420, so a steady heat source at the data hall can displace boiler fuel for offices, warehouses, greenhouses or a campus heating loop for nine months or more.
Air-cooled halls deliver return air in the eighties Fahrenheit, which suits space heating in adjoining buildings through heat exchangers or heat pumps. Liquid-cooled racks return water warm enough to feed heating coils more directly; that route is covered on data center liquid cooling in Alaska. Paul Industries sizes the heat recovery side against the actual heating load it will serve, because recovered heat saves money when a building is there to use it.
Water use, wastewater and the choice of heat rejection
Water use is a smaller question for Alaska data halls than for halls in the Southwest, but it still shapes the cooling choice, because evaporative towers need makeup water, chemical treatment and blowdown to sewer, and towers in subzero weather need basin heaters, plume management and careful winter operation. Anchorage’s ordinance asks large data centers to show water and wastewater capacity, and smaller communities may have limited treatment capacity to offer.
Closed glycol loops with dry coolers avoid almost all of that, at the cost of more coil surface and somewhat higher summer compressor energy. Where an owner prefers towers for their summer efficiency, Paul Industries designs them with heated basins, drain-down for idle cells and a water treatment program, and prices the closed-loop alternative alongside so the trade is visible.
Building a cooling plant around Alaska’s construction season and freight
Alaska’s construction season and freight schedule shape a cooling plant’s build as much as its design does. Outdoor work on pads, pipe racks and roof equipment goes most smoothly from late spring to early autumn, and large equipment arrives by barge, rail or road on fixed sailings and routes, so the long-lead chillers, dry coolers and switchgear are ordered to meet a delivery window rather than a calendar date.
Paul Industries answers that with prefabrication. Pump and heat exchanger skids, pipe rack modules and glycol fill stations are built and pressure tested before shipment, labeled to the drawings and sized for the transport mode the site uses, so the field season goes into setting, connecting and testing. Plans for those modules carry the Alaska seal that 13 AAC 50.020 requires for construction manufactured off site, and the fabrication records ship with the module documentation. Mechanical scope at the campus scale is described on data center mechanical contractor in Alaska.
What does data center cooling in Alaska cost?
The cost of a cooling plant for an Alaska data hall depends on IT load, redundancy level, the cooling arrangement chosen, the amount of heat recovery, freeze protection and snow design, freight to the site and how much of the plant can be prefabricated. A small enterprise room with direct expansion units and a modest economizer is a different budget from a multi-megawatt hall with a glycol plant, chillers and liquid cooling distribution.
Operating cost deserves the same attention as first cost in Alaska, because the 2025 commercial power price is roughly two thirds higher than the national average. Paul Industries prices the plant with its expected annual energy use at the owner’s tariff, and gives a budget range from comparable scope once the load, redundancy and site are known, followed by a firm price when the design is set.
Who installs data center cooling in Alaska?
Paul Industries installs data center cooling in Alaska, designing, fabricating, supplying, installing, testing and maintaining chilled water, glycol, economizer and liquid cooling plants for enterprise, carrier, utility, hospital, government and colocation halls in Anchorage, the Mat-Su, Fairbanks and the Interior, Juneau and Southeast, the Kenai Peninsula and the North Slope. From its headquarters at 256 Shore Drive, Kilmarnock, Virginia (the company was formerly based in northern New Jersey, then Pennsylvania), Paul Industries takes cooling work across Alaska and in all 50 states.
Three routes are on offer. Supply-only covers skids, dry coolers, chillers and prefabricated piping for an owner who has a design and an installer. Design-build carries engineering, fabrication, installation and startup under one contract. Complete installation builds an engineer’s existing design. Commissioning of the finished plant is set out on data center commissioning in Alaska, and repairs to the machines once they run on chiller repair in Alaska. For the headquarters state’s version of this service, see data center cooling in Virginia; the hot-climate contrast is on data center cooling in Texas.
Cold-climate data hall cooling from Paul Industries
Paul Industries plans, builds and maintains data hall cooling for Alaska sites, from a single computer room upgrade to a multi-megawatt glycol and chiller plant with heat recovery, and supports the same owner at sites in the rest of the West Coast region and nationwide. To start, send the site location, the IT load and growth plan, the redundancy target, any heating load that could use recovered heat, and drawings of the building or pad. Call 201-450-8280 or request a quote. The Alaska page lists the other process, water and piping work Paul Industries takes on across the state.
Standards referenced: ASHRAE Thermal Guidelines for Data Processing Environments (TC 9.9) · ASHRAE 15 · 2021 International Mechanical Code as adopted by 13 AAC 50.023 · 2021 International Building Code as adopted by 13 AAC 50.020 · 13 AAC 50.027 plan review · EPA Technology Transitions rule (40 CFR Part 84, Subpart B) · EPA leak repair rule, 40 CFR 84.106 · ASME B31.9 · ASME B31.1
Frequently asked questions
Who designs data center cooling plants in Anchorage and the Mat-Su?
Paul Industries designs and builds data center cooling plants in Anchorage, Eagle River, Palmer and Wasilla, from enterprise computer rooms to colocation halls. Anchorage’s July normal high is 66.2 degrees Fahrenheit, so most of the work goes into economizer controls, freeze protection and heat recovery rather than compressor capacity. Paul Industries also follows the Anchorage land use rules for large data centers adopted in 2026 when laying out heat rejection and water use.
Does Paul Industries build data center cooling in Fairbanks and the Interior?
Paul Industries takes data center cooling work in Fairbanks, North Pole and the Interior. Fairbanks has a January normal low of minus 17.2 degrees Fahrenheit and a July normal high of 72.7, the widest swing of Alaska’s main cities, so plants there need full freeze protection on every outdoor circuit and still need mechanical cooling sized for summer design days. Heat recovery is especially valuable in Fairbanks, where heating demand runs most of the year.
Who builds cooling for computer rooms in Juneau, Ketchikan and Southeast Alaska?
Paul Industries builds and upgrades cooling for computer rooms and small data halls in Juneau, Ketchikan, Sitka and the rest of Southeast. The maritime climate there is mild, with a Juneau July normal high of 64.0 degrees Fahrenheit, but wet, so coil corrosion, moisture control and drainage matter more than extreme cold. Equipment for island communities is prefabricated and tested before it ships by sea.
How many data centers are in Alaska today?
Alaska keeps no public registry that counts every data center in the state. Most existing facilities are enterprise, carrier, utility, hospital, government and military rooms, plus colocation space in Anchorage, and no hyperscale campus has been built. Paul Industries works on rooms of every size, from a single computer room’s cooling upgrade to a new multi-megawatt plant, and sizes each design on the owner’s own load and growth plan.
What does the proposed North Slope data center mean for cooling design in the Arctic?
A plant on the North Slope would face long periods of extreme cold, high winds and drifting snow, and its cooling design would center on glycol strength, coil protection and keeping outdoor air from overcooling the hall. The project approved for a state land lease in November 2026 remains a proposal that needs further permits. Paul Industries designs Arctic heat rejection with drift clearance, freeze-safe piping and prefabricated modules sized for the routes that serve the Slope.
Can an Alaska data hall run on free cooling all year?
Many Alaska halls can run on economizer cooling for nearly every hour, especially in Anchorage and Southeast, where cooling degree days are in single digits. Most owners still install mechanical cooling sized for the summer design day and for redundancy, because a warm spell or an economizer fault must never leave the hall without cooling. Paul Industries models the hours in each mode from site weather data before the plant is sized.
How dry does Alaska winter air get inside a data hall, and does it need humidification?
Outdoor air at subzero temperatures holds very little moisture, so once it is warmed to server inlet temperature its relative humidity can fall well below the levels many operators want. Halls that use air-side economizers in Alaska often add humidification or limit outdoor air on the coldest days to protect against static discharge. Water-side economizer plants keep outdoor air out of the hall and avoid most of the problem.
What glycol mix protects an Alaska dry cooler loop?
The mix is chosen for burst and freeze protection below the coldest temperature the site can reach, which in the Interior and on the North Slope means a stronger concentration than coastal plants use. Higher glycol strength reduces heat transfer and raises pump energy, so the loop is designed for the chosen fluid from the start. Paul Industries sets the concentration, writes the test interval into the maintenance plan and checks it at each service visit.
Do data center cooling towers work in a Fairbanks or Anchorage winter?
Cooling towers can operate in winter with heated basins, variable-speed fans, bypass and drain-down for idle cells, but icing and plume fog add operating work, and towers need makeup water and blowdown. Many Alaska owners choose closed glycol loops with dry coolers instead and accept a little more summer compressor energy. Paul Industries prices both options for the site so the owner can compare first cost, energy and water.
Which refrigerants can new data hall cooling units in Alaska use?
Under EPA’s Technology Transitions rule, cooling equipment for data centers and computer rooms manufactured or imported from January 1, 2027 must use refrigerant with a global warming potential of 700 or less, and new comfort cooling chillers already face that limit. Existing units keep running on their current refrigerant. Paul Industries selects compliant equipment and records refrigerant charges for the EPA leak repair rule that took effect in 2026.
Does the Alaska fire marshal review a data center cooling plant?
Plans covering mechanical systems, fuel storage tanks and fire protection go to the Division of Fire and Life Safety under 13 AAC 50.027 before construction, unless the project sits in a community with a deferral, such as Anchorage, Fairbanks, Juneau, Kenai or Kodiak, where the municipal office reviews them. Paul Industries prepares the mechanical submittal documents and builds the review period into the schedule.
How much heat can an Alaska data hall give back to the buildings around it?
Nearly all of the electricity drawn by the servers becomes heat, so a 1,000 kilowatt hall releases about 1,000 kilowatts of heat continuously. How much is usable depends on its temperature and on having a heating load to absorb it. Return water from liquid-cooled racks is warm enough to serve heating coils, while air-cooled halls usually need heat pumps to lift it. Paul Industries matches the recovery design to the real heating demand.
Is an air-side economizer a good fit for an Anchorage data hall?
Air-side economizers suit Anchorage’s mild summers and long cool seasons and cut fan and compressor energy to a minimum. The work goes into intake placement away from drifting snow, filter frosting, very dry winter air, mixing controls that keep the cold aisle from overcooling, and closing dampers during smoke or volcanic ash events. Paul Industries compares the air-side design against a glycol water-side economizer on energy, maintenance and risk.
What does data center cooling ashrae guidance say about Alaska supply temperatures?
ASHRAE’s recommended server inlet range of 18 to 27 degrees Celsius applies in Alaska as everywhere. Because outdoor air is colder than that range most of the year, an Alaska plant can run toward the upper part of the band and gain economizer hours without risk. Paul Industries sets supply air or chilled water temperatures with the owner and the server vendors, then builds the controls to hold them.
Does Paul Industries supply cooling equipment for Alaska projects without installing it?
Paul Industries offers supply-only packages for Alaska projects: pump and heat exchanger skids, dry coolers, chillers, glycol fill stations and prefabricated piping, built and tested before shipment and documented for the receiving team. Owners who prefer one contract can choose design-build or complete installation instead, and Paul Industries also maintains the plant after startup under a service agreement.
How do power outages on the Railbelt affect data hall cooling controls?
When utility power drops, standby generators restart the cooling plant, and the controls decide how quickly chillers, pumps and fans return. In Alaska the economizer usually carries the load during that restart, because outdoor air or the glycol loop can remove heat with pumps or fans running alone. Paul Industries sets restart sequences, keeps pumps on uninterruptible power where the load requires it and tests the sequence during commissioning.
What should an Alaska owner send to price a data center cooling plant?
Send the site location, the IT load now and at full build-out, the redundancy target, the supply temperature the servers will accept, any heating load on the site or next door that could use recovered heat, building or pad drawings, utility tariff and the planned in-service date. Paul Industries uses that to return a budget range from comparable scope and, once the design is fixed, a firm price.
Planning cooling for an Alaska data hall?
Send the site, the IT load and growth plan, the redundancy target and any heating load next door. Call 201-450-8280 or request a quote.
