Paul Industries designs, supplies and installs data center liquid cooling in New York, piping coolant distribution units, rack manifolds, rear-door heat exchangers and warm-water heat rejection for dense racks in Manhattan colocation floors, university research clusters and Western New York campuses. New York adds three twists to the national liquid cooling playbook: crowded high-rise buildings where every pipe route is contested, a cold Upstate climate that lets dry coolers carry warm-water loops most of the year, and a growing interest in sending server heat into heating networks. From its headquarters at 256 Shore Drive in Kilmarnock, Virginia, Paul Industries delivers this work in every region of the state.
Request a quote or call 201-450-8280
Planning data center liquid cooling in New York around power, space and weather
Data center liquid cooling in New York is planned around the same three variables as any other cooling project, but each one sits at an extreme here. Power is expensive and, for the largest new facilities, paused at the permit stage. Space in New York City is so tight that a liquid cooling loop must often share risers and ceiling voids with tenants. Weather swings from a humid coastal summer to a long Great Lakes winter, which changes how warm the facility water can run and how much of the year chillers are needed.
The technology choices themselves, cold plates, coolant distribution units, rear doors and immersion tanks, are explained on the data center liquid cooling page. This page covers how those choices land in New York buildings and on New York sites, and what an owner here should plan for before the first liquid-cooled rack arrives.
Where are New York’s dense racks going?
Dense racks in New York are going into three kinds of space: financial and colocation floors in Manhattan and the boroughs that host trading and analytics systems close to the networks, university and hospital research computing rooms across the state, and large campuses in Western New York built on power-plant and industrial land. Each kind of space brings a different starting point for the cooling loop.
Research computing gives the clearest example of where density is heading. The state-funded academic supercomputer at the University at Buffalo came fully online in 2026 on NVIDIA DGX GB200 systems, a platform NVIDIA builds as a liquid-cooled rack drawing about 120 kilowatts. The data centers in Western New York show the other scale: TeraWulf’s Lake Mariner campus in Barker, on a former coal plant site, lists 600 MW of total critical IT capacity and has leased high performance computing halls to Fluidstack. At 120 kilowatts per rack, air alone cannot remove the heat, so liquid reaches the chip.
New York data centers’ electricity demand is the other reason liquid cooling is rising here. A liquid-cooled rack moves most of its heat into water at temperatures high enough that the facility can reject it with dry coolers or a waterside economizer, which takes chiller and fan energy out of the bill in a state where each kilowatt-hour averaged 19.66 cents in 2024.
| Facility type | Typical starting point | Usual liquid cooling route | New York constraint to plan for |
|---|---|---|---|
| Manhattan colocation or carrier hotel floor | Raised floor, CRAH units, building condenser water | Rear-door heat exchangers or a CDU fed from condenser water for a few dense cabinets | Riser space, floor loading, FDNY hot work rules, landlord approvals |
| Outer-borough or Long Island enterprise hall | Chilled water plant built for air cooling | In-row CDUs on a new secondary loop, plant water reset upward | Chiller plant set for cold water, ceiling height for overhead pipe |
| University or hospital research computer room | Campus chilled water, sometimes steam-driven chillers | Direct-to-chip with facility water from campus loops or a dedicated dry cooler | Campus water temperatures, research schedules, heat reuse goals |
| Western New York campus on industrial land | New or converted buildings with large yards | Liquid-to-liquid CDUs, warm-water loops and banks of dry coolers | Snow, freeze protection, scale of pipe and pump galleries |
| Capital Region or Central New York corporate room | Small chilled water or DX systems | Rear doors or a packaged liquid-to-air CDU for a first dense row | Limited plant capacity, winter freeze risk on outdoor lines |
How does direct to chip cooling work in a New York retrofit?
Direct to chip cooling works by pumping a coolant through a cold plate fixed to each processor and accelerator, carrying heat out of the server through rack manifolds to a coolant distribution unit, which passes it across a heat exchanger into the building’s facility water. In a New York retrofit, the difficult part is rarely the server side, which the hardware maker supplies, but the facility side: finding a route for supply and return mains, a place for the CDUs, and facility water at the right temperature and quality.
Each direct to chip cooling cold plate sits on a closed secondary loop of treated water or water and propylene glycol, separate from the building loop. The CDU holds that loop’s pumps, filtration, expansion and controls. In a direct to chip cooling data center hall, the cold plates usually remove most of the server heat and fans remove the rest, so the room still needs some air cooling. Two phase direct to chip cooling, where a dielectric fluid boils inside the cold plate and condenses at the CDU, removes heat at a near-constant temperature but uses refrigerant-style piping and controls; single-phase water loops fit existing New York buildings well because their piping, materials and service practices match what those buildings already run.
A direct to chip cooling system in an occupied building is installed in stages. Paul Industries surveys the hall and the plant, designs the secondary loop and the facility water connection, prefabricates pipe spools off site to reduce work on the floor, installs CDUs and manifolds row by row, then flushes, pressure tests and fills each loop before the racks connect.
Liquid cooling in New York City buildings
Liquid cooling in New York City buildings meets constraints that a greenfield campus does not: floors rated for older loads, risers already full of condenser water, electrical and telecom, landlords who control every penetration, and fire department rules for any work that produces a flame. The facility water for a liquid-cooled row often comes from the building’s condenser water loop through a heat exchanger, because adding new risers in a Manhattan tower is costly and slow.
Fire department rules shape how the pipe is joined. In New York City, torch work with oxygen and a flammable gas must be done by a holder of an FDNY Certificate of Fitness, with a fire guard holding the F-60 certificate present to watch for fire, under a hot work permit. Paul Industries plans liquid cooling data center piping with mechanical joints such as press-fit copper and grooved steel where the specification allows, which reduces hot work on an occupied floor, and prefabricates welded spools off site where welding is the better choice. Pipe installation follows the 2022 New York City Mechanical Code, which builds on the 2015 International Mechanical Code.
Structural review comes first in older buildings. A row of liquid-cooled racks, filled manifolds and CDUs weighs far more per square foot than the cabinets the floor was designed for, so Paul Industries checks floor capacity against the building’s structural drawings and load ratings before equipment is placed and spreads loads with steel or relocated equipment where needed.
Warm water and the New York weather record
Warm facility water is the key to cheap liquid cooling in New York, because water returned at 80 or 90 degrees Fahrenheit can be cooled by outdoor air for most of the year without running a chiller. ASHRAE’s liquid cooling classes set the upper supply limits: W17 at 62.6 degrees, W27 at 80.6, W32 at 89.6, W40 at 104 and W45 at 113. Hardware makers state which class their equipment accepts, and the class decides how many hours a dry cooler can carry the load.
| Facility water class (upper supply limit) | Outdoor air needed (about) | New York City (LaGuardia) | Buffalo |
|---|---|---|---|
| W17 (62.6 F) | 49 F or below | About 3,510 h | About 4,490 h |
| W27 (80.6 F) | 69 F or below | About 6,550 h | About 7,340 h |
| W32 (89.6 F) | 79 F or below | About 8,110 h | About 8,470 h |
| W40 (104 F) and above | Nearly all hours | All but the hottest hours | All but the hottest hours |
The table shows why Upstate sites attract liquid-cooled halls. At W27, a Buffalo dry cooler covers about 84 percent of the year, against about 75 percent at LaGuardia, and at W32 both sites approach year-round free cooling with small trim chillers for heat waves. The trade-off is winter: Buffalo’s 99.6 percent heating design temperature is 2 degrees Fahrenheit, so any loop that runs outdoors carries glycol or is isolated behind a heat exchanger, and the glycol’s effect on heat transfer and pumping is part of the design.
Data center heat reuse in New York
Data center heat reuse in New York is moving from idea to project, because liquid cooling captures heat at temperatures useful for space and water heating and the state has many buildings that burn fuel for heat through long winters. The University at Buffalo offers the clearest public example: its process heat from the state academic supercomputer is to heat campus buildings, and the permanent facility due by the end of 2027 is planned to tie into the university’s thermal energy network in a closed loop.
Heat recovery from data centers works best when the source and the user are close, the source runs warm, and the user needs heat for many hours. A liquid-cooled hall returning water at 95 to 113 degrees can feed a heat pump or, in some cases, a low-temperature heating loop directly, which turns a cooling cost into a heating credit. In New York City, where building emissions are capped under Local Law 97 (LL97), recovered heat that displaces a boiler also reduces the building’s emissions total. Paul Industries designs the heat exchangers, heat pump connections, piping and controls that move that heat, and keeps the cooling loop protected if the heating side stops taking heat.
A heat reuse design starts with matching profiles. A data hall produces nearly the same heat every hour of the year, while a heating load peaks in January and almost disappears in July, so the cooling side always needs its own heat rejection sized for the full load. Thermal storage, a domestic hot water load or a year-round process user can widen the window in which recovered heat is used. Paul Industries models the hourly match between the hall’s heat and the user’s demand before sizing heat pumps and exchangers, so the investment is set by the heat that will actually be used.
Executive Order 62 and research computing
Executive Order 62, New York’s July 2026 pause on permits for large new data centers, defines a covered data center by a 50 megawatt threshold and excludes facilities used mainly for manufacturing, research, education or medical care. University clusters, hospital computing and research facilities, where much of New York’s densest liquid-cooled hardware sits, are therefore outside the order’s definition. Large commercial campuses at or above 50 megawatts that still need DEC discretionary permits wait for the state’s environmental study.
For liquid cooling, the practical result is that retrofits, research installations and halls below the threshold keep moving. Owners planning large commercial builds can use the waiting period to settle the facility water class, heat rejection and any heat reuse plan, because the study’s focus on water use and noise favors dry coolers and closed loops that liquid cooling makes practical.
CDUs, manifolds and secondary loops for New York halls
Coolant distribution units, rack manifolds and secondary loop piping form the part of a liquid cooling installation that the facility owner buys, and their design decides how reliable the racks will be. Paul Industries sizes CDUs on the rack heat load at the hardware maker’s flow and temperature limits, adds redundancy that matches the hall’s tier, and lays out manifolds so any one rack can be isolated without draining its neighbors.
| Component | Role | What Paul Industries checks |
|---|---|---|
| Coolant distribution unit (liquid-to-liquid) | Separates rack coolant from facility water; pumps, filters and controls the secondary loop | Capacity at the actual facility water temperature, pump redundancy, power feed, floor space and service access |
| Liquid-to-air CDU or rear door | Rejects rack heat into room air where no facility water is available | Room air capacity, CRAH margin, fan noise in shared buildings |
| Row and rack manifolds | Distribute coolant to each server’s cold plates | Isolation valves, quick-disconnect compatibility, drip containment, labeling |
| Secondary loop piping | Connects CDUs to manifolds | Material compatibility, cleanliness, joint method, hot work limits, pressure test |
| Facility water connection | Brings building, campus or dry cooler water to the CDUs | Supply temperature range, pressure, strainers, glycol, isolation from the main plant |
| Leak detection and controls | Finds leaks early and keeps flow and temperature stable | Sensor placement under manifolds and CDUs, alarms to the operator, interlocks |
Water quality, fill water and glycol
Water quality in a liquid cooling loop matters more than in a chilled water plant, because cold plate channels are narrow and the metals inside servers are mixed. The secondary loop is usually filled with treated deionized water or a propylene glycol mixture that the hardware maker approves, filtered at the CDU and tested on a schedule. Fill water from a New York City or Upstate municipal supply is never used straight from the tap; the loop is flushed, filled with the approved fluid and sampled before turnover.
Facility water that runs outdoors in a dry cooler needs glycol for the site’s design low, and that glycol lowers heat transfer and raises pump power compared with plain water. Paul Industries designs Upstate loops so the glycol stays on the outdoor side of a heat exchanger where possible, which keeps the CDU side on the fluid the hardware maker prefers and limits the volume of glycol to buy and maintain.
Testing before the first rack connects
Testing before the first rack connects protects both the servers and the schedule, and on a New York job it follows a fixed order: pressure test each loop section to the design specification and the mechanical code, flush until strainers stay clean, fill with the approved coolant, sample and record its chemistry, then run the CDUs on load banks or test heaters before real hardware goes on. Leak detection is tested by wetting each sensor, and every alarm is confirmed at the operator’s monitoring system.
The test records become part of the owner’s turnover package and feed the facility’s commissioning program; see data center commissioning in New York for how those tests fit the wider plan.
Adding liquid-cooled rows to an operating New York hall
Adding liquid-cooled rows to an operating New York hall is a sequence of small, reversible steps, because the servers around the work keep running and most halls have no spare room to build in. Paul Industries begins with a tie-in plan: where the new secondary mains connect to facility water, which valves isolate them, and how the existing plant will carry the extra load once the dense row is live. Hot taps or valves installed during a planned plant outage give the new loop its connection points without draining the whole system.
Work on the floor then follows the rack schedule. Mains are installed and tested ahead of the hardware delivery, CDUs are set and wired, manifolds go in row by row, and each section is flushed, filled and proven before the next is opened. Dust control, floor tile protection and after-hours work for noisy steps are agreed with the operator in advance. In a colocation building, the landlord’s method of procedure governs every step, and Paul Industries writes its procedures to fit that format so approvals move quickly.
The existing chilled water plant usually needs attention too. A plant that ran 44 degree water for air handlers may be able to raise its setpoint once dense racks move to liquid, which frees capacity and saves energy, but only after the remaining coils are checked. Paul Industries tests those coils and adjusts the controls as part of the same project.
What does data center liquid cooling cost in New York?
Data center liquid cooling costs in New York depend on the number and density of racks, whether facility water already exists at a usable temperature, CDU type and redundancy, pipe routing distance and method, building access and structural work, and how much heat rejection must be added. Manhattan installations add landlord approvals, night work and hot work controls; Upstate installations add dry coolers, glycol and freeze protection.
Savings are part of the calculation. At New York’s 2024 average retail price, each kilowatt of continuous load removed from fans or chillers is worth about $1,722 a year, so a liquid-cooled row that lets a hall shut down 40 kilowatts of air handler fans saves about $68,900 a year before any chiller savings. Paul Industries prepares a budget range from comparable scope once rack counts and the existing plant are known, then a firm price after a survey. Owners can buy CDUs, manifolds and prefabricated piping supply-only, choose design-build, or have the complete installation delivered.
Who designs and installs data center liquid cooling in New York?
Paul Industries designs, fabricates, supplies, installs, tests and maintains data center liquid cooling in New York, covering coolant distribution units, manifolds, secondary loops, rear-door heat exchangers, facility water connections, dry coolers and heat recovery. Headquartered in Kilmarnock, Virginia, and once based in northern New Jersey and later Pennsylvania, Paul Industries takes liquid cooling projects across New York City, Long Island, Westchester, the Hudson Valley, Albany, Syracuse, Rochester, Buffalo-Niagara and the Southern Tier.
The liquid cooling scope ties into the rest of the facility through data center cooling in New York, data center mechanical contractors in New York, process piping in New York and industrial welding services in New York. Research computing owners can also see research labs and universities, and owners weighing tanks over cold plates can compare data center immersion cooling. The same work runs in Virginia, the headquarters state, and through data center liquid cooling in New Jersey and data center liquid cooling in Pennsylvania, across all 50 states and at plants abroad through Paul Industries’ international work.
Liquid cooling work by Paul Industries across New York
Paul Industries delivers liquid cooling for colocation tenants, enterprise halls, research clusters and large campuses throughout New York, from a first rear-door row in a Manhattan suite to warm-water plants with heat recovery Upstate. Send the rack count, heat load per rack and the hardware maker’s coolant specification, a description or drawings of the existing cooling plant, and the building or site address. Call 201-450-8280 or request a quote, and visit the New York page for the full range of work Paul Industries delivers in the state.
Standards referenced: ASHRAE TC 9.9 liquid cooling guidelines (W17 to W45 facility water classes) · 2022 New York City Mechanical Code · New York City Fire Code hot work provisions (FDNY) · NYS Uniform Fire Prevention and Building Code · New York Executive Order No. 62 (2026) · ASME B31.9
Frequently asked questions
Who installs liquid cooling for colocation tenants in Manhattan and Brooklyn?
Paul Industries installs liquid cooling for colocation tenants and owners in Manhattan, Brooklyn and Queens, from rear-door heat exchangers on a few dense cabinets to CDUs and manifolds for whole rows. City work is planned around landlord approvals, riser space, floor loading and FDNY hot work rules, with prefabricated spools and mechanical joints used to keep torch work on occupied floors to a minimum.
Does Paul Industries pipe liquid cooling for research computing in Buffalo, Rochester or Ithaca?
Yes. Paul Industries designs and installs direct-to-chip loops, CDUs and facility water connections for university and hospital research computing in Buffalo, Rochester, Ithaca and across Upstate New York. Campus projects often draw facility water from central plant loops or a dedicated dry cooler, and many now plan for heat recovery into campus heating, which shapes the water temperature chosen from the start.
Can Paul Industries add liquid cooling to a hall in Westchester, on Long Island or in the Capital Region?
Yes. Paul Industries adds liquid cooling to enterprise and colocation halls in Westchester, Nassau, Suffolk and the Capital Region. Many of these halls run chilled water plants designed for air cooling, so the usual approach is a new secondary loop with in-row or perimeter CDUs, and an upward reset of facility water temperature where the remaining air-cooled equipment allows it.
Which direct to chip cooling system suits a Manhattan colocation suite?
In a leased Manhattan suite, the usual choice is a liquid-to-liquid CDU fed from the building’s condenser water through a heat exchanger, or a liquid-to-air CDU where the landlord will not allow a water connection. The decision turns on available facility water, floor space for the CDU, the lease terms on penetrations and the rack heat load. Paul Industries surveys the suite and the building plant before recommending one.
Is two phase direct to chip cooling used in New York halls?
Two-phase cold plates, which boil a dielectric fluid at the chip, are available and suit very high heat flux. Single-phase water or glycol loops suit many New York buildings well, because those buildings already handle water and the piping, controls and service practices carry over. Paul Industries installs either type and compares them on hardware requirements, piping, fluid cost and service before the owner commits.
Is direct to chip cooling closed loop in a New York installation?
Yes. The rack side runs on a closed secondary loop of treated water or glycol that the CDU pumps and filters, separate from the building’s water. The facility side may be closed as well, when heat goes to dry coolers, or connect to an open cooling tower loop through the CDU’s heat exchanger. Keeping both sides closed avoids evaporation and simplifies water treatment.
Does direct to chip cooling use water in a New York data hall?
The rack loop holds a fixed volume of water or water and glycol that circulates without being consumed. Whether the facility uses water overall depends on heat rejection: dry coolers use none, while cooling towers evaporate water. Because liquid cooling allows warm facility water, many New York halls can reject most of their heat through dry coolers and cut tower water use sharply.
What facility water temperature should a new Upstate New York liquid-cooled hall use?
The answer starts with the hardware maker’s accepted ASHRAE class. In Buffalo, an assumed dry cooler approach of about 10 degrees lets W27 water, at up to 80.6 degrees Fahrenheit, be produced without chillers for about 7,340 hours a year, and W32 for about 8,470. Warmer classes cut chiller use further and make heat reuse easier, so the highest class the hardware accepts usually wins.
Can a Western New York campus run liquid cooling through winter without freezing the loop?
Yes, with the right separation and fluid. Outdoor dry coolers in Western New York carry propylene glycol mixed for the site’s design low, Buffalo’s being 2 degrees Fahrenheit, with margin, and a heat exchanger keeps that glycol away from the CDU side. Drain points, heat tracing on exposed piping and controls that keep minimum flow through outdoor coils complete the protection.
Does Executive Order 62 apply to a university liquid cooling project in New York?
The order’s definition of a covered data center excludes facilities used mainly for research, education, manufacturing or medical care, and it applies to facilities of 50 megawatts or more. A university research cluster is therefore outside the definition, so its liquid cooling work proceeds under the usual building code, campus and utility approvals. Mixed-use facilities are judged by their primary use under the order’s definition.
How do FDNY hot work rules affect liquid cooling piping in a New York City building?
Any torch work with oxygen and a flammable gas in New York City requires an FDNY Certificate of Fitness holder to perform it and a fire guard with an F-60 certificate to watch for fire, under a hot work permit, and building managers usually add their own rules. Paul Industries limits hot work on occupied floors by using press-fit and grooved joints where allowed and welding spools off site.
Can server heat from a New York hall heat other buildings?
Yes, where a heating user is close and needs heat for many hours. Liquid-cooled racks return water warm enough to feed heat pumps or low-temperature heating loops, and the University at Buffalo plans to heat campus buildings with process heat from its supercomputer. Paul Industries designs the heat exchangers, pumps and controls so the heating side can take heat without risking the cooling loop.
How heavy are liquid-cooled racks for an older New York City floor?
Liquid-cooled racks with filled manifolds and adjacent CDUs concentrate far more weight per square foot than the cabinets many older city floors were designed for. Paul Industries checks the floor’s rated capacity against the building’s structural records before installation, spreads loads with steel frames, places CDUs over beams or in adjacent rooms, and sequences delivery through freight elevators sized for the equipment.
What does data center liquid cooling cost per rack in New York?
Cost per rack depends on how many racks share each CDU, whether usable facility water already reaches the room, pipe distance and joining method, structural work, and Manhattan access conditions. A row added to an existing plant costs less per rack than a first row that needs new heat rejection. With rack counts and plant details in hand, Paul Industries gives a budget figure based on similar installations and fixes the price after walking the site.
Where should leak sensors go in a New York liquid-cooled row?
Leak detection cable or spot sensors belong under each rack manifold, beneath every CDU, along overhead pipe runs above sensitive equipment, and at the low points of any drip trays. Every sensor is tested by wetting it during commissioning, and each alarm is confirmed at the operator’s monitoring system, so a drip from a quick disconnect is caught before it reaches a server or the floor below.
How often does a New York liquid cooling loop need maintenance?
Paul Industries typically sets a program that samples coolant chemistry and checks CDU filters quarterly, reviews pump and valve condition with each sample, and tests leak detection at least once a year, following the hardware maker’s coolant guidance. Glycol in outdoor Upstate loops is tested each autumn before freezing weather. Paul Industries offers service contracts that cover the CDUs, piping, dry coolers and controls together.
Can Paul Industries supply CDUs and manifolds without installing them?
Yes. Owners can buy coolant distribution units, manifolds, rear-door heat exchangers, dry coolers and prefabricated pipe spools from Paul Industries as supply-only equipment, or choose design-build, or have the full installation, testing and startup delivered under one contract. Equipment is matched to the hardware maker’s coolant specification and the building’s facility water before purchase.
Which details speed up a liquid cooling estimate for a New York hall?
Send the rack count and heat load per rack, the hardware maker’s coolant and facility water requirements, floor plans with the rack layout, details of the existing chilled water or condenser water plant, and the building address. For city buildings, add riser, ceiling and freight elevator dimensions. Paul Industries uses that package to plan a survey and return a budget range.
Bringing dense racks into a New York hall?
Send the rack count, heat load per rack, the hardware maker’s coolant specification and existing plant details. Call 201-450-8280 or request a quote.