Paul Industries works as a data center mechanical contractor in Massachusetts, designing, prefabricating, installing and testing chiller plants, chilled and condenser water piping, liquid cooling loops, heat rejection and generator fuel systems for colocation, enterprise and research data centers from Boston to the Pioneer Valley. Massachusetts asks more of a data center project than most states: host community approval and a state framework for large loads since September 2026, electricity at more than twice the national industrial price, a cold winter that rewards economizer design, and air and fuel permits that neighbors watch closely. Paul Industries builds the mechanical scope to those conditions under one contract.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
State permitting Projects over 25 MW peak demand must follow the state data center framework (executive order, September 8, 2026)
Sales tax exemption 20 years, $50 million and 100 jobs minimum; new applications paused June 25, 2026
Electricity price 18.19 cents/kWh industrial average in 2024; US 8.13 (EIA)
Grid ISO New England; Eversource, National Grid and municipal light plants
Reviewed November 2026

What a data center mechanical contractor in Massachusetts builds

A data center mechanical contractor in Massachusetts builds the systems that move heat out of the white space and keep power on when the grid drops: chillers, cooling towers or dry coolers, plate heat exchangers for economizer operation, chilled water and condenser water mains, coolant distribution units and secondary loops for liquid-cooled racks, computer room air handlers and fan walls, humidification, and the diesel storage, day tanks and fuel piping behind the generators. The same contractor sets pipe supports and seismic bracing, insulates and labels the systems, flushes and pressure tests every loop, and brings the controls and sequences to the point where integrated testing can start.

The national scope, delivery models and division of work are described on the data center mechanical contractors page. This page covers what changes in the Commonwealth: where the market sits, the approvals a project now needs, the price of power, the climate, and the state rules that touch the mechanical work.

Data centers in Massachusetts: the regions and their mechanical work

Data centers in Massachusetts cluster in four places: carrier and colocation buildings in Boston, a large colocation campus in Lowell, research computing in Holyoke, and enterprise and colocation rooms in the office parks of Route 128 and the I-495 belt. The market is older and denser than in the newer hyperscale states, which means much of the mechanical work happens inside existing buildings, beside operating halls, on constrained urban sites.

Boston’s data centers occupy converted commercial and industrial buildings downtown and in the surrounding neighborhoods, where cooling plants sit on roofs and in cellars and every crane pick needs a street permit. Lowell hosts a large colocation building in a residential neighborhood; MassDEP approved eight more emergency generators there in March 2025, bringing the total to nineteen, and residents appealed. In Holyoke, the Massachusetts Green High Performance Computing Center, a university research computing facility that opened in 2012 and earned LEED Platinum, was sited to draw on Holyoke Gas and Electric’s largely hydroelectric supply.

Massachusetts data center regions and what they mean for the mechanical scope
RegionTypical facilityMechanical characterSite conditions to plan for
Boston and the inner coreCarrier hotels, colocation in converted buildingsRetrofit plants, roof and cellar equipment, phased cut-ins beside live hallsCrane and street occupancy permits, structural limits, noise ordinances
Lowell, Lawrence and the Merrimack ValleyLarge colocation in former industrial buildingsPlant expansions, generator and fuel additionsAir permits under close public scrutiny, Lowell moratorium on new projects
Route 128 and the I-495 beltEnterprise rooms, colocation, lab computingChilled water from building plants, liquid cooling for research clustersOccupied buildings, office park zoning, shared utilities
Holyoke, Westfield and the Pioneer ValleyResearch computing, proposed hyperscale campusFree cooling, hydro-backed power, large campus plants if builtHolyoke’s citywide ban on new facilities, colder winters
Worcester and Central MassachusettsEnterprise, hospital and university computingBuilding plant extensions, dry coolers, glycol loopsFreeze protection, campus outage windows

The Pioneer Valley and the Westfield proposal

Data center sites in the western part of the state draw interest for cheaper land, hydroelectric and transmission access, and cooler weather, and they now meet some of the firmest community resistance in the state. A developer proposed a campus of 10 to 14 buildings on about 120 acres in Westfield, with $2.5 billion to $4 billion of total investment and an Eversource transmission interconnect and new substation (NBC Boston, August 2025). In June 2026 the Holyoke City Council voted 9 to 4 for a citywide zoning ban on new data centers, which ended a proposed 20 megawatt Holyoke data center on Water Street. Any mechanical plan for the valley starts with the host community’s position.

Where can a data center still be built in Massachusetts after the 2026 bans?

Massachusetts allows data centers statewide, but during 2026 several cities and towns stopped new ones, and a governor’s order now puts host community approval ahead of state permitting. Holyoke adopted a citywide zoning ban in June 2026, Lowell approved a yearlong moratorium in March 2026 with a possible 180-day extension, Haverhill barred data centers in every zoning district, Shutesbury adopted a moratorium, and the Boston City Council has taken up a zoning change that would keep existing facilities operating while barring their expansion.

Governor Healey’s order of September 8, 2026 sets the statewide terms. Pending projects must reach community benefits agreements with host communities that align with state standards before state permitting begins, projects with peak electricity demand above 25 megawatts must show they meet the administration’s framework, nondisclosure agreements between state agencies and data center developers are blocked, and a Ratepayer Protection Fund receives payments from projects that draw on grid supply before their own clean energy is in place. The framework also asks for adequate water supply, wastewater capacity and minimal air emissions, which reach straight into the cooling and generator design.

Massachusetts data center tax incentives and the 2026 pause

Massachusetts data center tax incentives center on a sales and use tax exemption created by Chapter 238 of the Acts of 2024, effective November 20, 2024, for data centers that receive certification from the Secretary of Economic Development. A qualifying facility must cost at least $50 million to construct or substantially refurbish and equip, with the costs incurred within ten years of certification, and must maintain at least 100 jobs in the state. The exemption runs 20 years and covers eligible computing and networking equipment and, for facilities with certification, software, electricity and construction costs.

On June 25, 2026, Governor Healey stopped accepting new applications for the exemption until stronger protections for ratepayers and communities are in place, and the administration said no applications had been received by then. For a mechanical package, the practical effect is bookkeeping: a project that expects to apply when the program reopens keeps its equipment purchases, construction costs and dates documented from the start, and Paul Industries organizes its invoices and turnover records so those figures can be pulled without reconstruction.

How do Massachusetts power prices and ISO New England shape the plant?

Massachusetts power prices shape a data center’s mechanical plant more than any other cost, because Massachusetts industrial customers paid an average of 18.19 cents per kilowatt-hour in 2024, compared with 8.13 cents across the United States (EIA). Every point of power usage effectiveness saved is worth more than twice what it would be in a typical state. The grid is run by ISO New England, most sites are served by Eversource or National Grid, and some towns, Holyoke among them, have municipal light plants.

As an illustration with stated assumptions, a 10 megawatt IT load running all year at a power usage effectiveness of 1.4 draws 2 megawatts more than the same load at 1.2. That difference is 17.5 million kilowatt-hours a year, roughly $3.2 million at 18.19 cents. Numbers on that scale justify waterside economizers, larger heat exchangers, variable speed pumps and fans, warmer chilled water supported by the ASHRAE thermal guidelines, and liquid cooling where rack densities climb. The utility energy efficiency programs offered under the Mass Save name by Eversource, National Grid and other sponsors run commercial new construction paths that are worth checking at the design stage.

Mechanical design choices and why they pay in Massachusetts
Design choiceWhat it doesWhy it fits Massachusetts
Waterside economizer with plate heat exchangersLets cold tower water carry the data hall load with chillers offLong cold season; Boston January normals are 37 F high and 23 F low
Dry coolers on glycolRejects heat without evaporating waterAnswers the state framework’s water expectations; no tower freeze risk
Warmer chilled water supplyRaises chiller efficiency and stretches economizer hoursEach kilowatt saved is priced at 18.19 cents
Liquid cooling with coolant distribution unitsTakes high-density rack heat at warm water temperaturesResearch clusters at universities and labs push density up
Heat recovery to neighboring buildingsExports low-grade heat to a campus or district loopBoston and Cambridge buildings face emissions limits on their heating
Variable speed pumps and fansMatches flow to loadPart-load hours dominate in phased Massachusetts expansions

Cooling a data center through a Massachusetts year

Cooling a data center through a Massachusetts year means designing for two very different conditions: a humid summer peak, when Boston averages 82 degree afternoons and 66 degree nights in July under the 1991 to 2020 NOAA normals, and a long winter in which the outdoor air can do most of the work. The design question is how many hours the chillers can stay off, and how to keep everything that holds water from freezing while they do.

Freeze protection drives a large share of the detail. Cooling tower basins need heaters or indoor sumps, makeup and drain lines need heat tracing, plate heat exchangers on the tower side need controls that keep water moving, and dry coolers run on glycol at a strength chosen for the site’s design low temperature. Snow and ice loads matter for rooftop equipment and its supports in Boston and the hill towns alike. In summer, tower capacity is sized to the design wet bulb, and air-cooled equipment near the coast is specified with coil coatings against salt air. The cooling equipment itself is covered in more depth on data center cooling systems in Massachusetts, and direct-to-chip and immersion work on data center liquid cooling in Massachusetts.

Generators, fuel and MassDEP air permits

Generators and their fuel are the most visible part of a Massachusetts data center’s mechanical scope, because MassDEP air permits and fire code tank permits sit on them and neighbors read the filings. Emergency engines can be installed under the Environmental Results Program at 310 CMR 7.26(42), with a certification filed within 60 days after first fire and minimum stack height requirements by engine size; other sources need a plan approval under 310 CMR 7.02 before construction.

Fuel storage runs on parallel rules. The state fire code, 527 CMR 1.00, governs tank installation and fire department permits; aboveground tanks of more than 10,000 gallons need a permit from the State Fire Marshal under 502 CMR 5.00; and underground tanks are registered with MassDEP under 310 CMR 80.00, with a compliance self-certification every three years. Paul Industries installs bulk tanks, day tanks, transfer pumps, fuel piping and leak detection, and provides the pressure test and installation records those permits ask for. Welded fuel and process connections follow the practice described on industrial welding services in Massachusetts.

State rules that reach the mechanical work on a Massachusetts data center
RuleWhat it coversWhat the mechanical package provides
780 CMR, 10th editionBuilding, mechanical and energy code, in force from October 11, 2024 on the 2021 International CodesPermit drawings, equipment submittals, inspection access
Stretch and specialized energy codes, 225 CMR 22 and 23Higher efficiency requirements in adopting municipalitiesEquipment efficiencies and controls that meet the version the town adopted
MGL c.146 s.45A and 522 CMR 9.00Refrigeration systems of 20 tons or more need an annual certificate of inspectionChiller documentation and relief device data ready for the first inspection
MGL c.146 s.84Licensing for pipefitting and refrigeration technician workTrades holding the license class each piping and refrigeration task requires
310 CMR 7.26(42) and 7.02Emergency engine certification or plan approvalStack heights, exhaust routing and fuel system details for the filing
527 CMR 1.00, 502 CMR 5.00, 310 CMR 80.00Fuel storage permits and tank registrationTank, piping and leak detection records, pressure tests

Prevailing wage, labor rules and public projects

Massachusetts prevailing wage law, chapter 149 sections 26 and 27, applies to public works constructed by public entities, so a privately funded colocation or enterprise data center generally falls outside it while a facility built by a state university, a municipality or another public body usually falls inside. The Department of Labor Standards reads each case on its facts, looking at public ownership and public funds. Where the law applies, the awarding authority’s wage schedule sets the rates, and Paul Industries prices the mechanical work to that schedule.

Pipefitting and refrigeration work in the Commonwealth is work that requires a license under chapter 146, and the license classes for refrigeration technicians follow the size of the system. Those requirements apply on every data center job, public or private.

Data center construction in Massachusetts on tight and occupied sites

Data center construction in Massachusetts often means building inside or beside something that already runs: a converted mill in the Merrimack Valley, an office building in the Route 128 ring, a carrier hotel downtown or a university computing room. The mechanical work is planned around live halls, shared utilities and tight access rather than an empty field.

Prefabrication is the main tool. Paul Industries builds pipe rack modules, pump skids and valve assemblies off site, tests them, and delivers them sized for freight elevators, alley access and crane picks, so field work inside an operating building is mostly bolting up and welding closure pieces. Cut-ins to live chilled water mains are made with hot taps or line stops where a shutdown is unacceptable, under a written method of procedure that names each valve, each step and the rollback. Commissioning of the finished systems is described on data center commissioning in Massachusetts, and the chillers that serve existing halls on chiller repair in Massachusetts.

How much water should a Massachusetts data center cooling plant use?

Water use has become a design question for every new Massachusetts data center, because the state framework asks projects to show adequate water supply and wastewater capacity, and host communities read cooling tower consumption closely. Open cooling towers evaporate water in proportion to the heat they reject and send blowdown to the sewer, so a large campus on towers can draw on a town system for much of the year. Dry coolers on glycol use almost no water but need more fan power and more space, and they give up some summer efficiency; hybrid coolers and adiabatic assist sit between the two.

Paul Industries works through that tradeoff with the owner on actual numbers: annual water use for each option at the site’s weather, sewer discharge volumes and chemistry, fan and pump energy at Massachusetts power prices, and the space and structure each needs. Many Massachusetts designs end with dry coolers or hybrid units for most hours, a small evaporative trim for the hottest afternoons, and a waterside economizer that keeps chillers off through the winter. Where towers stay, water treatment, blowdown control and makeup metering are built in so consumption can be reported to the town.

Testing, turnover and the records Massachusetts asks for

Testing and turnover on a Massachusetts data center produce the records that several different authorities and the owner will ask for later, so they are planned from the first submittal rather than gathered at the end. Every loop is flushed, cleaned and pressure tested, then treated and filled; chillers and pumps are started and run under load; and controls are proven through each sequence before integrated systems testing begins.

Mechanical turnover records on a Massachusetts data center and who uses them
RecordWho reads itWhy it matters
Hydrostatic and pneumatic test reports by loopBuilding inspector, ownerCloses the mechanical permit and sets the baseline for future cut-ins
Chiller data, relief device records, refrigerant chargeState refrigeration inspectorSupports the first section 45A certificate of inspection
Generator stack, exhaust and fuel system detailsMassDEP, host communityBacks the emergency engine certification or plan approval
Tank, piping and leak detection test recordsFire department, State Fire Marshal, MassDEPSupports fuel storage permits and tank registration
Equipment invoices and construction cost breakdownOwner’s tax advisersDocuments eligible purchases if the sales tax exemption reopens
Water treatment, flushing and fill recordsOperations teamProtects coolant quality for liquid-cooled racks from day one

Who builds data center mechanical systems in Massachusetts?

Paul Industries builds data center mechanical systems in Massachusetts. The company is an East Coast contractor with its headquarters at 256 Shore Drive, Kilmarnock, Virginia; it was based in northern New Jersey and later in Pennsylvania before that. Its Massachusetts data center work runs from Boston and the inner core to Lowell and Lawrence, Route 128, the I-495 belt, Worcester, Springfield, Holyoke and the Pioneer Valley, and the same team takes projects in every one of the 50 states and at facilities abroad, described on the international page.

Owners can buy the scope in the form that fits the project: supply-only prefabricated racks, skids and spools; design-build of the central plant and piping; or complete installation of the mechanical package through testing and turnover. Paul Industries designs, fabricates, supplies, installs, tests and starts up those systems, and services them after the hall goes live. Among mechanical contractors in Boston and across the state, that single line of responsibility from design through service is the reason owners bring the whole package to Paul Industries. The approach on campus builds in the headquarters state is described on data center mechanical contractor in Virginia, and urban retrofit work on data center mechanical contractor in New York.

What does data center mechanical work cost in Massachusetts?

Data center mechanical work in Massachusetts is priced from the IT load, the cooling architecture, the redundancy level, the site and its access, and the approvals schedule. A retrofit of a hall in an occupied Boston building carries premiums for night work, rigging and phased cut-ins; a new building on open land carries the costs of yard piping, heat rejection and fuel storage at scale; and a liquid-cooled research cluster adds coolant distribution units, secondary loops and water quality control.

Massachusetts adds a few cost lines of its own: freeze protection and heat tracing, coil coatings near the coast, glycol in dry cooler loops, air permit documentation for generators, and the time that host community approvals and benefits agreements add before mechanical work can begin. Paul Industries prepares a budget range from comparable scope as soon as the load, the cooling concept and the site are known, then a firm price from drawings and an equipment list.

Data center mechanical work from Paul Industries in Massachusetts

Paul Industries designs, prefabricates, installs, tests and services chiller plants, piping, liquid cooling, heat rejection and fuel systems for data centers being built in Massachusetts and for the halls already running there, with the records that state permits, inspections and tax filings ask for. Process piping on campus is covered on process piping in Massachusetts, and the wider regional view on the Northeast page. For a price, send the IT load and phasing, the cooling concept, redundancy, site plans and the approval status. Call 201-450-8280 or request a quote; every other service Paul Industries delivers in the Commonwealth appears on the Massachusetts page.

Standards referenced: Chapter 238 of the Acts of 2024 (M.G.L. c.64H s.6(zz)) · Massachusetts Executive Order No. 658 (2026) · 780 CMR (Massachusetts State Building Code, 10th edition) · 225 CMR 22 and 23 (stretch and specialized energy codes) · MGL c.146 s.45A and 522 CMR 9.00 · MGL c.146 s.84 · 310 CMR 7.26(42) and 310 CMR 7.02 · 527 CMR 1.00 · 502 CMR 5.00 · 310 CMR 80.00 · MGL c.149 ss.26-27 · ASHRAE TC 9.9 thermal guidelines

Frequently asked questions

Which contractor builds data center mechanical systems in Boston and the inner core?

Paul Industries builds data center mechanical systems in Boston, Cambridge, Somerville and the surrounding inner core, where most work happens in converted buildings beside operating halls. Plants on roofs and in cellars, crane picks under street occupancy permits and phased cut-ins to live mains are routine there. Paul Industries prefabricates racks and skids sized for the building’s access and plans each tie-in under a written method of procedure.

Does Paul Industries take data center mechanical work in Lowell, Lawrence and the Merrimack Valley?

Yes. Paul Industries takes mechanical work at data centers in Lowell, Lawrence, Haverhill and the rest of the Merrimack Valley, including plant expansions, chiller and pump additions and fuel system work in existing facilities. New projects in Lowell face a moratorium approved in March 2026, and Haverhill has barred data centers in every zoning district, so much of the work there is upgrades to operating buildings.

Who builds mechanical systems for data centers in Western Massachusetts, from Holyoke to Westfield?

Paul Industries builds and services data center mechanical systems in Holyoke, Westfield, Springfield and across the Pioneer Valley. The valley offers hydro-backed power, transmission access and long free-cooling seasons, and a large campus has been proposed in Westfield. Holyoke banned new data centers in June 2026, so projects there center on existing facilities, while new builds elsewhere begin with the host community’s approval.

Which contractor expands data halls in Waltham, Lexington, Marlborough and Andover?

Paul Industries builds and expands data center mechanical systems in Waltham, Lexington, Burlington, Marlborough, Andover, Devens and other Route 128 and I-495 communities. Many of these rooms serve research, biotech and corporate computing inside occupied buildings, so the work often extends a building’s chilled water plant or adds a liquid cooling loop for a high-density cluster without disturbing the tenants around it.

Why do Massachusetts data center projects so often start as expansions of existing buildings?

Massachusetts has an older, denser data center market than the newer hyperscale states, and several cities now restrict new facilities. The market is made up of carrier and colocation buildings in Boston, a large colocation campus in Lowell, university research computing in Holyoke, and many enterprise and colocation rooms in office parks along Route 128 and I-495. Expanding a hall inside one of those buildings avoids a new siting fight, so plant upgrades, liquid cooling retrofits and generator additions make up a large share of the mechanical work.

Are data centers coming to Massachusetts despite the city and town moratoriums?

Interest remains, with a large campus proposed in Westfield and expansions at existing facilities, but the path is narrower than in other states. Since September 2026, new projects need host community agreements before state permitting, and those above 25 megawatts must meet the state framework on energy, water and emissions. Mechanical designs that use little water and recover heat answer several of those expectations directly.

What does the September 2026 executive order ask of a new Massachusetts data center?

It requires community benefits agreements with host communities that align with state standards before state permitting begins, asks projects with peak demand above 25 megawatts to show they meet the administration’s framework, blocks nondisclosure agreements between state agencies and developers, and creates a Ratepayer Protection Fund. The framework also expects adequate water and wastewater capacity and minimal air emissions, which shape cooling and generator choices.

Which purchases does the Massachusetts data center sales tax exemption cover?

The exemption created by Chapter 238 of the Acts of 2024 covers eligible computing, networking and storage equipment, and, once a facility receives certification, software, electricity and construction costs, for 20 years. A facility must cost at least $50 million and maintain at least 100 jobs. New applications were paused on June 25, 2026, so projects planning to apply later keep complete purchase and cost records from the start.

Does Massachusetts prevailing wage apply to a privately funded data center?

Chapter 149 sections 26 and 27 apply to public works constructed by public entities, so a private data center built without public funds generally falls outside them. A facility built by a public university, a city or another public body usually falls inside, and the awarding authority’s wage schedule then sets rates. Paul Industries prices the mechanical package to whichever schedule the contract specifies.

Do emergency generators at a Massachusetts data center need a MassDEP air filing?

Yes. Emergency engines installed under 310 CMR 7.26(42) need a certification filed within 60 days after first fire and must meet minimum stack height rules by size; sources outside that program need a plan approval under 310 CMR 7.02 before construction. Generator filings in Massachusetts draw public attention, so stack and exhaust routing, fuel system details and test schedules are settled early in the mechanical design.

Which state inspection applies to the chillers in a Massachusetts data center plant?

Refrigeration and air conditioning systems of 20 tons or more need a certificate of inspection under chapter 146 section 45A, renewed by inspection at least once a year, with the rules in 522 CMR 9.00. Most data center chillers are well above that size. Paul Industries hands over relief device data, pressure test results and refrigerant records so the first inspection finds a complete file.

Why do Massachusetts winters favor waterside economizers in data centers?

Boston’s January normals are a 37 degree Fahrenheit high and a 23 degree low, and for much of the year tower water alone can take the hall’s heat through a plate heat exchanger and the chillers stay off. At 18.19 cents per kilowatt-hour, those chiller-off hours are worth more than in most states. Freeze protection on towers, basins and makeup lines is the price of using them.

What freeze protection does a data center cooling plant need in the Berkshires and Pioneer Valley?

Plants in the colder western part of the state need heated tower basins or indoor sumps, heat-traced makeup and drain lines, glycol at a strength matched to the site’s design low in dry cooler loops, and controls that keep water moving through exposed heat exchangers. Snow loads on rooftop equipment and supports are part of the structural check. Paul Industries designs those details into the plant and tests them before the first winter.

Can an older Massachusetts mill or office building take a data hall?

Many can, subject to the host community’s zoning and the state framework. The mechanical checks are floor loading for chillers and racks, roof or yard space for heat rejection, routes for large pipe, generator and fuel locations that meet air and fire rules, and access for prefabricated modules. Paul Industries surveys those items and designs the plant and piping to the building rather than to an idealized layout.

How do Massachusetts electricity prices change a data center's mechanical design?

At 18.19 cents per kilowatt-hour for industrial customers in 2024, against 8.13 nationally, efficiency features that are marginal elsewhere pay back quickly in Massachusetts: larger economizer heat exchangers, warmer chilled water, variable speed pumps and fans, liquid cooling at high density, and heat recovery to neighboring buildings. Paul Industries runs the energy comparison on the owner’s load and tariff before the design is fixed.

Can a Massachusetts data center buy Paul Industries pump skids and pipe racks as supply-only packages?

Yes. Paul Industries fabricates pump skids, valve assemblies, pipe rack modules and spools to the project drawings, tests them off site, and ships them with weld, pressure test and material records for the owner’s installer. The same packages can instead be installed by Paul Industries under a design-build or complete installation contract when the owner wants one party responsible for the whole mechanical scope.

How is a new loop connected to an operating Massachusetts data hall without a shutdown?

New branches are connected to live chilled water or condenser water mains with hot taps or line stops, so the existing loop keeps flowing while the new valve and branch are installed. Each step follows a written method of procedure with the valve sequence, isolation checks and rollback plan. Paul Industries flushes, pressure tests and treats the new section before it is opened to the live system.

What should an owner send Paul Industries to price a Massachusetts data center mechanical package?

Send the IT load and phasing, rack densities and any liquid cooling plans, the cooling concept and redundancy level, site or building plans, utility and generator arrangements, and the status of host community approvals and permits. For a retrofit, add photos of the existing plant and its access routes. Paul Industries returns a budget range from comparable scope, then a firm price from drawings and an equipment list.

Planning data center mechanical work in Massachusetts?

Send the IT load, phasing, cooling concept, redundancy level and site plans, with the status of host community approvals. Call 201-450-8280 or request a quote.