Paul Industries performs data center commissioning in West Virginia on the mechanical side of the job, flushing and pressure testing cooling and liquid cooling loops, starting up chillers, pumps and dry coolers, and running functional and integrated systems tests through turnover, from its headquarters at 256 Shore Drive, Kilmarnock, Virginia. West Virginia adds three things to a commissioning program: a building code that applies only where a county or city has adopted it, a 2026 code update that brings commissioning into the commercial energy standard, and microgrid campuses where the integrated test includes the power plant. Paul Industries plans each test around the code, the weather and the power arrangement of the site.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Building code in force 87 CSR 4 of 2022: 2018 I-codes, ASHRAE 90.1-2013 for commercial energy
2026 code filing 2024 I-codes with ASHRAE 90.1-2019, which adds commissioning to 90.1
Enforcement The adopting county or city enforces the code (W. Va. Code 15A-11-5)
Generator permits WV DEP general permits G60-D and G65-D for emergency units
Reviewed November 2026

How data center commissioning in West Virginia fits the permit and the plant

Data center commissioning in West Virginia proves that the cooling plant, the liquid cooling loops and the systems that support them do what the design says, and it produces the records that building officials, state agencies, insurers and the owner’s operators rely on. The commissioning levels are the familiar ones: factory witness testing, delivery and installation checks, startup and pre-functional checks, functional performance tests and integrated systems testing. What changes from state to state is who reviews the work, which code edition the tests answer to, and what the site’s weather and power allow on a given date.

Headquartered today in Kilmarnock, Virginia, after earlier years in northern New Jersey and then Pennsylvania, Paul Industries commissions plants for owners across the East Coast, in all 50 states and at facilities outside the United States. Its broader West Virginia plant work is described on the West Virginia overview, and the national data center commissioning guide describes each level in general terms. This page covers what a West Virginia project adds.

Where the West Virginia State Building Code applies

The West Virginia State Building Code applies in the counties and municipalities that have adopted it, and the adopting jurisdiction enforces it. W. Va. Code 15A-11-5 has the State Fire Commission write the code as a legislative rule, 87 CSR 4, gives it force in the counties and cities that adopt it, and requires a county or city that intends to adopt it to notify the State Fire Marshal. Counties and municipalities may also agree to provide inspection services for one another.

For a commissioning program, that structure means the first task is to establish who inspects the building. Berkeley County, for example, re-adopted the state code as its own building code ordinance on July 28, 2022, effective August 1, 2022, so a Martinsburg-area data hall answers to county building officials. Adoption varies by county and city across the state. The commissioning plan records the authority having jurisdiction, the code edition in force and the inspections that authority requires, before the first pressure test is scheduled.

Microgrid district campuses under the 2025 Power Generation and Consumption Act add another question. The act exempts projects inside those districts from county and municipal ordinances, so the plan for a West Virginia microgrid campus names the code basis the owner, the engineer of record and the state agencies have agreed for the buildings, and the commissioning tests are written against it.

Which West Virginia building code edition governs a data center?

The West Virginia building code edition in force on most data center permits in 2026 is the 2022 version of 87 CSR 4, effective August 1, 2022, which adopted the 2018 International Building Code, International Mechanical Code and related I-codes, with ASHRAE 90.1-2013 as the commercial energy standard. In 2026 the State Fire Commission filed an update that moves to the 2024 editions and to ASHRAE 90.1-2019 for commercial buildings, and at least one city, Buckhannon, has already passed an ordinance adopting it.

West Virginia current building codes and the 2026 update, with what each means for commissioning
Code87 CSR 4 of 20222026 filingCommissioning consequence
Building2018 International Building Code2024 International Building CodeInspections and certificate of occupancy steps the schedule works around
Mechanical2018 International Mechanical Code2024 International Mechanical CodeHydronic test pressure and duration, refrigeration machinery room requirements
Commercial energyASHRAE 90.1-2013ASHRAE 90.1-201990.1-2019 adds commissioning tied to Standard 202, with a preliminary report before occupancy
Computer rooms90.1-2013 provisions90.1-2019 allows ASHRAE 90.4 for rooms above 10 kW of IT loadMechanical load component and efficiency documentation under 90.4
Rule termSunset August 1, 2027Proposed sunset August 1, 2032The edition recorded at permit is the one the tests answer to

The practical answer for a project team is to confirm the edition with the authority having jurisdiction when the permit is filed and to write the commissioning plan to it. Where a building is permitted under the updated rule, the commercial energy standard itself requires commissioning documentation in the permit application, functional testing and a preliminary commissioning report before occupancy, which turns part of the commissioning program into a code obligation rather than an owner’s choice.

West Virginia building codes and regulations beyond the building permit

West Virginia building codes and regulations reach a data center commissioning program through several state agencies besides the building official. Each one adds a document or a test to the schedule, and the commissioning plan lists them alongside the code inspections.

State requirements that touch a West Virginia data center during commissioning
RequirementAgency and authorityWhen it affects commissioning
Emergency generator air permitsWV DEP Division of Air Quality; general permits G60-D and G65-DGenerator test runs and load bank hours are logged against the permit’s conditions
Aboveground fuel and chemical tanksWV DEP under the Aboveground Storage Tank Act, W. Va. Code 22-30Tanks over 1,320 gallons are registered and their leak detection and overfill alarms tested
High-pressure steam boilers and steam generatorsDivision of Labor under W. Va. Code 21-3-7 and 42 CSR 3Heat recovery steam equipment on microgrid campuses is inspected before integrated testing relies on it
Large water withdrawalsWV DEP Water Use Section under W. Va. Code 22-26Makeup meters are proven during startup so reported volumes are measured
Heating, ventilating and cooling workLabor Commissioner under W. Va. Code 21-16Startup and adjustment of HVAC equipment falls under the state’s HVAC licensing law

The tank law has a Charleston history worth knowing. The Aboveground Storage Tank Act passed in 2014, months after a chemical leak from a tank farm on the Elk River reached the intake of Charleston’s public water system, and it covers tanks of more than 1,320 gallons, with every tank of 50,000 gallons or more in its stricter level 1 class. Bulk diesel storage for a campus’s standby generators commonly falls inside it, so tank alarms and leak detection belong in the functional test scripts. The tank fabrication in West Virginia page covers building those tanks.

Commissioning levels on a West Virginia high impact data center

Commissioning levels on a West Virginia high impact data center follow the usual five steps, but the scale changes how they are run. A qualifying building holds 90 MW or more of critical IT load under the 2025 law, and it rarely opens at once. Each phase passes through every level, while the halls already in service keep running beside it, so the commissioning team works in a live campus from the second phase on.

The five commissioning levels as Paul Industries runs them on a phased West Virginia campus
LevelWhat is provenWest Virginia emphasis
Level 1: factory witnessChillers, CDUs, dry coolers and pumps perform at the factoryWinter operating modes, low ambient controls and glycol performance witnessed, not only summer capacity
Level 2: delivery and installationEquipment arrives undamaged and is set and piped to the drawingsHighland deliveries inspected for transit damage; equipment stored out of freezing conditions until filled
Level 3: startup and pre-functionalEach component runs correctly on its ownPressure tests to the adopted mechanical code, flushing to a measured filter result, refrigerant and machinery room checks
Level 4: functional performanceEach system meets its sequence of operationsEconomizer changeover, minimum supply temperature control and freeze protection sequences
Level 5: integrated systems testThe whole site responds correctly to failures and transfersUtility loss on grid-fed campuses; generator trip, black start and load steps on microgrid campuses

Phasing adds work that a single-building job does not have. Each new branch is pressure tested and flushed while isolated from the live loop, then filled and vented before its valves open, and the integrated test for the new phase is designed so a failure scenario never takes cooling away from halls already carrying load. Paul Industries writes those isolation and tie-in steps into method statements that the owner’s operators approve before work starts.

Integrated testing on a West Virginia microgrid campus

Integrated testing on a West Virginia microgrid campus treats the on-site power plant as the utility, so the failure scenarios include a generator or turbine trip, the loss of a gas supply line and a black start, alongside the usual chiller, pump and controller failures. On a grid-fed campus the classic test opens the utility breaker and watches the generators and cooling plant recover. On a microgrid campus the test has to show that cooling rides through the loss of a generation unit and restarts in an order the remaining units accept.

Load banks provide the heat for these tests before servers arrive, and on a microgrid they also provide the electrical load the generation plant needs to be tested against. Chillers start in sequence as load steps up, CDU pumps run on their ride-through power through each transfer, and the controls record supply temperature at the racks through every event. Paul Industries runs the mechanical side of these tests and coordinates each step with the electrical and generation teams on the owner’s integrated test schedule. The data center cooling in West Virginia page covers designing the plant for those step loads.

Testing cooling plants against West Virginia weather

West Virginia weather shapes when each cooling test can prove design capacity. Morgantown’s NOAA normals record 101.8 nights a year at or below freezing and only 13.2 days at or above 90 F, so a plant commissioned in winter proves its economizer and freeze protection modes while summer design conditions are months away, and a plant commissioned in July proves peak capacity while winter control waits for the first cold spell.

Two practices handle this. First, the functional tests are split by season, with summer capacity tests on towers and dry coolers deferred to a scheduled return visit when conditions approach design, and winter modes tested in the first cold spell. Second, where the schedule is fixed, load banks push the heat load above design so the outdoor equipment runs at full rejection even on a cool day, and the results are corrected to design conditions using the manufacturer’s rating data. Highland sites, where Canaan Valley’s January normal low is 17 F, also call for heated enclosures or glycol fill before any hydrostatic test, because test water left in a coil overnight freezes.

What each West Virginia season lets a commissioning team prove on a cooling plant
SeasonTypical Morgantown conditions (NOAA normals)Tests that fitTests that wait or use load banks
Winter, December to FebruaryHighs of 40 to 44 F, frequent freezing nightsFull economizer operation, freeze protection, minimum supply temperature control, tower basin heatPeak capacity of towers, dry coolers and air-cooled chillers
Spring and autumn shoulder monthsHighs of 53 to 77 FMode changeover between economizer, partial and mechanical cooling; chiller staging at low loadBoth design extremes
Summer, June to AugustHighs of 81 to 84 F, a few days at 90 F or aboveChiller and heat rejection capacity close to design, condensation control on cold plates and coilsWinter modes and freeze protection

Liquid cooling loops carry their own sequence of fill, venting, chemistry checks and heat load tests; the data center liquid cooling in West Virginia page covers those loops and their winter controls.

Pressure testing and flushing to the adopted mechanical code

Pressure testing on a West Virginia data center follows the mechanical code in force where the building was permitted. The 2018 International Mechanical Code, carried by the 2022 State Building Code, sets the hydronic piping test at 150 percent of maximum design pressure, never below 100 psi, with a hold of 15 minutes or longer, and the owner’s specification often asks for more. Paul Industries tests in sections that match the installation sequence, records gauge calibration, test pressure and hold time, and repeats any failed section after repair.

Flushing follows the test. Mains are flushed at velocities that move construction debris, with temporary strainers and bypasses keeping chillers, plate exchangers and CDUs out of the flush path, and the flush continues until filter checks show the loop is clean. Water treatment is then added and verified before the permanent equipment goes online. Paul Industries supplies the pumps, strainers, gauges and recorders for hydrostatic testing and flushing, and keeps the test records with the turnover package.

How to commission a data center in West Virginia, from permit to turnover

How to commission a data center in West Virginia comes down to an ordered sequence that ties each test to the code edition, the state filings, the weather and the power arrangement of the site. Paul Industries runs the mechanical side of that sequence as follows:

  1. Record the basis. Name the authority having jurisdiction, the 87 CSR 4 edition in force at permit, the commercial energy standard, the air permit for the generators and any microgrid district arrangement.
  2. Witness at the factory. Test chillers, CDUs, dry coolers and pump skids at the factory, including low ambient and freeze protection modes that matter in West Virginia winters.
  3. Inspect on delivery. Check equipment for transit damage on arrival and store it dry and above freezing until it is set, filled and protected.
  4. Test and flush. Pressure test each section to the adopted mechanical code and the specification, then flush to a measured filter result with sensitive equipment bypassed.
  5. Start up. Start each component with the manufacturer, check refrigerant safety functions in the machinery room, prove makeup and blowdown meters, and test tank alarms and leak detection.
  6. Prove the sequences. Run functional tests on economizer changeover, chiller staging, minimum supply temperature control, freeze protection and CDU dew point control.
  7. Test the whole site. Run integrated tests against utility loss on grid-fed campuses, or generator trip and black start on microgrid campuses, with load banks carrying the heat.
  8. Return for the season. Schedule the summer capacity checks and first-winter mode checks that fall after the opening date.
  9. Turn over. Hand operators test records, as-built markups, sequences, trend data and the documents each state filing relies on.

Each step produces a signed record, and no step starts until the one before it is closed, so a deficiency found during integrated testing traces straight back to the functional or startup record where it should have appeared.

Commissioning cooling upgrades in older West Virginia buildings

Commissioning a cooling upgrade in an older West Virginia building differs from commissioning a new hall because the existing systems have to keep running while the new ones are tested beside them. Server rooms in Charleston office towers, Huntington and Morgantown hospitals and university buildings often sit on chilled water systems decades old, with incomplete drawings and valves that have not been exercised in years.

The commissioning plan for these jobs starts with a survey of the existing plant: valve condition, actual flows and temperatures, controls that still match their sequences, and the condition of the water. New equipment is then tested in isolation, tied in during a planned window, and the existing systems are retested afterward so the owner knows the whole room, old and new, meets its sequences. Paul Industries carries out that survey, tie-in and retest work and documents the room as it actually exists after the upgrade.

What does data center commissioning in West Virginia cost?

The cost of data center commissioning in West Virginia depends on the number of systems, the number of phases, how many seasonal return visits the plan needs, and how much load bank time the integrated tests require. Energy for load banks is a visible part of that cost on a grid-fed site. Running 10 MW of load bank for 24 hours uses 240,000 kWh, which the EIA’s 2024 state averages price at about $18,700 for an industrial account (7.81 cents per kWh) and about $27,900 for a commercial one (11.62 cents). On a microgrid campus the same test burns the owner’s own gas instead, and the generator run hours count under the site’s air permit conditions.

Other drivers are the condition of the installed work, since every failed pressure test or dirty flush adds days; access rules on secure sites; and the number of integrated test scenarios the owner and insurer require. Paul Industries gives a budget range once the system list and phase plan are known, then a firm price when the test scripts are agreed.

Who provides data center commissioning in West Virginia?

Paul Industries provides data center commissioning in West Virginia for the mechanical systems: flushing, pressure testing, chiller and dry cooler startup, CDU fill and heat load testing, functional performance tests and the mechanical side of integrated systems testing, with the records to support permits, state filings and equipment warranties. It works within the owner’s commissioning program and alongside the commissioning authority, and it carries the same work through design-build and complete installation projects, where testing is planned from the first spool.

The same practice serves Virginia, its headquarters state, through data center commissioning in Virginia, and the neighboring Pennsylvania commissioning market, within its Mid-Atlantic coverage. For pharmaceutical and other regulated plants in West Virginia, the validation and commissioning in West Virginia page covers qualification work, and the complete campus mechanical scope is set out under data center mechanical contractors in West Virginia.

Commissioning from Paul Industries for West Virginia data halls

Paul Industries commissions cooling plants, liquid cooling loops and their supporting systems for West Virginia data halls, from single enterprise rooms to phased campuses under the 2025 microgrid law. The work runs from factory witness testing through pressure tests, flushing, startup, functional tests and integrated systems testing, with seasonal return visits and a turnover package written to the code edition in force. Send the system list, the phase plan and the permit details, and request a quote for commissioning in West Virginia.

Standards referenced: West Virginia State Building Code, 87 CSR 4 (W. Va. Code 15A-11-5) · International Building Code and International Mechanical Code (2018; 2024 in the 2026 update) · ANSI/ASHRAE/IES 90.1-2013 and 90.1-2019 · ASHRAE/IES Standard 202 · ASHRAE 90.4 · ASHRAE 15 · W. Va. Code 21-3-7 and 42 CSR 3 (high-pressure steam boilers) · Aboveground Storage Tank Act, W. Va. Code 22-30 · WV DEP general permits G60-D and G65-D · W. Va. Code 21-16 (heating, ventilating and cooling work) · ASME B31.9

Frequently asked questions

Who commissions data center cooling plants in Charleston and the Kanawha Valley?

Paul Industries commissions data center cooling plants in Charleston, South Charleston and across the Kanawha Valley, including state agency, hospital and enterprise data halls. Valley summers bring July normals of 86 F and 66 F, so tower and chiller capacity tests are scheduled for warm weather, while winter visits prove freeze protection and economizer changeover. Paul Industries flushes, tests and starts up the plant and records each step for the building official and the owner.

Does Paul Industries commission data halls in Martinsburg and the Eastern Panhandle?

Yes. Paul Industries commissions data halls in Martinsburg, Inwood, Charles Town and the rest of Berkeley and Jefferson counties. Berkeley County re-adopted the West Virginia State Building Code as its own building code ordinance in July 2022, so projects there answer to county building officials, and the commissioning plan schedules pressure tests and inspections with them. Paul Industries flushes, tests and starts up the cooling systems and runs the mechanical side of integrated testing.

Who provides data center commissioning for campuses in Mason County and along the Ohio River?

Paul Industries provides mechanical commissioning for data center campuses in Mason County, around Point Pleasant and along the Ohio River through Parkersburg and Huntington. Campuses there are planned in phases at gigawatt scale, so each new hall is pressure tested, flushed and integrated while earlier halls keep running. Paul Industries writes the isolation and tie-in steps into method statements the owner approves and records every test for turnover.

Does Paul Industries test cooling and liquid cooling loops for data centers in Morgantown and along I-79?

Yes. Paul Industries tests and starts up cooling plants and liquid cooling loops for data centers and research computing rooms in Morgantown, Fairmont, Bridgeport and Clarksburg. Work in operating university and secure rooms is planned around access rules and outage windows, with new loops pressure tested, flushed and filled in isolation before they connect to anything live. Each test is recorded with gauge calibration, pressures and hold times.

What do West Virginia building codes and regulations require before a data hall opens?

Before a West Virginia data hall opens, the adopting county or city’s building official completes the inspections its code requires, including tests of mechanical piping under the International Mechanical Code. State requirements run alongside: generator air permits with WV DEP, registration of aboveground tanks over 1,320 gallons, Division of Labor inspection of any high-pressure steam boilers, and water use reporting for large withdrawals. Buildings under ASHRAE 90.1-2019 also need a preliminary commissioning report.

Which West Virginia data center regulations apply when generators run for commissioning?

Generator runs during commissioning fall under the site’s WV DEP air permit. Emergency generators commonly register under general permit G60-D, for units at facilities with other emission sources, or G65-D, for a single emergency generator at a facility without other point sources, and the permit’s conditions govern testing and maintenance operation. Paul Industries logs every load bank and generator run hour during commissioning so the owner’s records match the permit.

How is integrated testing run on a West Virginia microgrid campus?

Integrated testing on a West Virginia microgrid campus runs failure scenarios against the on-site power plant: a generator or turbine trip, loss of a gas supply line and a black start, along with chiller, pump and controls failures. Load banks provide the heat and electrical load, and the tests confirm that cooling rides through each event and restarts in an order the remaining generation accepts. Paul Industries runs the mechanical side with the generation and electrical teams.

Does heat recovery steam equipment on a data center microgrid need a Division of Labor inspection?

West Virginia’s Division of Labor inspects high-pressure steam boilers, those carrying more than 15 psi, under W. Va. Code 21-3-7, and its rule 42 CSR 3 covers high-pressure steam boilers and forced flow steam generators, adopting the ASME Boiler and Pressure Vessel Code and the National Board Inspection Code. Steam-raising heat recovery equipment on a microgrid campus is therefore scheduled for inspection before integrated tests depend on it.

How are hydrostatic tests protected from freezing on a highland data center site?

Hydrostatic tests on a highland data center site are protected from freezing by testing inside heated enclosures, draining and blowing out sections before the end of each shift, or testing with a glycol mixture where the specification allows. Canaan Valley’s January normal low is 17 F, so test water left in an outdoor coil or an unheated building overnight freezes. Paul Industries plans winter test sequences around the forecast and records each drain-down.

When should a dry cooler capacity test be scheduled in West Virginia?

A dry cooler capacity test in West Virginia is ideally scheduled for July or August, when outdoor temperatures come closest to design; Morgantown averages only 13.2 days a year at or above 90 F. Where the schedule is fixed, load banks push the heat load above design so the coolers reject full capacity on a cooler day, and results are corrected to design conditions with the manufacturer’s rating data, followed by a seasonal return check.

How do commissioning levels apply to a West Virginia high impact data center built in phases?

On a West Virginia high impact data center, a building with at least 90 MW of critical IT load under the 2025 law, each phase passes through all five commissioning levels while earlier halls keep running. New branches are tested and flushed in isolation, then filled and vented before valves open, and each phase gets its own integrated test written so no failure scenario removes cooling from live halls.

Which state filings draw on commissioning records in West Virginia?

Several West Virginia filings draw on commissioning records: large-quantity water use reports to the DEP Water Use Section rely on makeup meters proven at startup; aboveground tank registrations rely on tested leak detection and alarms; generator run logs support air permit compliance; and boiler inspection records support Division of Labor permits for any steam equipment. Paul Industries organizes its turnover package so each filing finds its records in one place.

How is an older West Virginia server room retested after liquid cooling is added?

An older West Virginia server room is retested after liquid cooling is added by pressure testing, flushing and filling the new loops in isolation, then testing the CDUs under heat load before servers connect, and finally rerunning the room’s functional tests to confirm the existing air system and chilled water plant still meet their sequences with the new load split. Paul Industries also updates the room’s records so the operators have one current set.

Does the 2025 microgrid law remove inspections from a data center campus?

The 2025 Power Generation and Consumption Act exempts projects inside a microgrid district from county and municipal ordinances, which raises the question of how building code review is arranged for those campuses. State permits continue to apply where the law has not changed them: microgrid projects in Tucker and Mingo counties obtained state air permits, for example. The commissioning plan records the agreed code basis and every state inspection the site needs.

Which refrigeration safety checks belong in startup of a West Virginia chiller plant?

Startup of a West Virginia chiller plant includes the refrigeration safety checks the adopted mechanical code and ASHRAE 15 require for the machinery room: refrigerant detectors tested to alarm at their set points, alarms that start the emergency ventilation, relief valve piping run to a safe discharge, and signage and emergency shutoff in place. Paul Industries tests each function and records the results with the chiller startup reports.

Does Paul Industries provide commissioning as a separate scope from installation?

Yes. Paul Industries provides commissioning as its own scope on new or existing West Virginia cooling plants and liquid cooling loops, and it also carries commissioning inside its supply, design-build and complete installation projects, where testing is planned from the first spool. Either way, the work covers flushing, pressure testing, startup, functional tests and the mechanical side of integrated testing, with a turnover package written to the code edition in force.

Which documents let Paul Industries build a commissioning schedule for a West Virginia hall?

Paul Industries builds a commissioning schedule for a West Virginia hall from the mechanical drawings and sequences of operations, the equipment list with factory test dates, the phase plan, the permit and the authority having jurisdiction, the air permit for any generators, and the owner’s integrated test requirements. With those, it returns a test sequence with seasonal visits and load bank hours, a budget range, and then a firm price.

How does a West Virginia data hall turn over cleanly when it opens in phases?

A West Virginia data hall that opens in phases turns over cleanly when each phase has its own test records, its own as-built markups and its own integrated test report, filed in a structure that grows with the campus. Valve tags, balancing reports and sequences are updated at every phase, so operators never work from documents that describe a building that no longer exists. Paul Industries maintains that package through the final phase.

Commissioning a data hall in West Virginia?

Send the system list, the phase plan, the permit details and any generator air permit. Call 201-450-8280 or request a quote.