Paul Industries installs data center liquid cooling in Indiana, from coolant distribution units and rack manifolds to the facility water loop, dry coolers and trim chillers that reject the heat outdoors. Indiana suits warm-water liquid cooling unusually well: its long cold season lets dry coolers carry most of the year, but its winters, hard water and pressure vessel rules each add a requirement that has to be built in from the start. Paul Industries offers supply-only, design-build and complete installation routes for new campuses and for rooms that are adding liquid-cooled racks to an air-cooled plant.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Indianapolis peak July normal high 85 F (NOAA, 1991-2020)
Indianapolis winter January normal low 21 F, so outdoor loops need freeze protection
Small vessels Chambers of 1.5 cu ft or less sit outside 675 IAC 30
Fill water Indianapolis supply typically 200 to 350 mg/L hardness
Reviewed November 2026

What is data center liquid cooling in Indiana, and where is it going in?

Data center liquid cooling in Indiana means carrying heat from processors and accelerators in a liquid, either through cold plates on the chips or through rear-door coils and immersion tanks, and moving it through a coolant distribution unit to a facility water loop that rejects it outdoors. The technology is the same everywhere; what changes in Indiana is the outdoor half of the system and the rules that apply to the equipment around it.

Two kinds of Indiana project are bringing liquid cooling in. The first is the large campus: Meta, which broke ground in Lebanon in February 2026 on a campus designed for 1 gigawatt, says the Lebanon halls will circulate their coolant in a sealed liquid loop that needs no water for most of the year, and the AWS campus at New Carlisle in St. Joseph County went fully operational in October 2025. These are market facts about where Indiana is heading. The second is the existing room: enterprise, hospital, university and colocation spaces in Indianapolis, Fort Wayne, South Bend and Evansville that have to place a few high-density racks into a building designed for air.

The loop-by-loop explanation of cold plates, CDUs and rear doors is on the national data center liquid cooling page. This page covers what Indiana adds.

Liquid cooling for a new data center: Indiana campus choices

A new data center in Indiana settles three liquid cooling questions before steel goes up: what facility water temperature the racks will accept, whether the outdoor loop carries glycol, and how the cooling plant will be phased as racks arrive. Every other decision, from pipe size to pump redundancy, follows those three.

Facility water temperature decides how much of the year the plant can run without compressors. Rack makers publish their supply limits against the ASHRAE TC 9.9 liquid cooling classes, which run from W17 to W45 and above, named for the maximum facility water supply temperature in degrees Celsius. An Indiana campus designed for W32 water (up to 32 degrees Celsius, about 90 degrees Fahrenheit) can reject heat through dry coolers on almost every hour of a South Bend or Fort Wayne year, and needs chiller or evaporative trim on the humid afternoons when the outdoor dry bulb climbs into the high 80s and 90s. Designs at W40 or W45 run dry nearly all year anywhere in the state.

Phasing decides the pipe. Large campuses install headers sized for the final load with valved, capped branches for future rows, then add CDUs and dry cooler cells as halls fill. Paul Industries plans the branch locations, isolation valves and flushing connections with the first phase, so later rows connect to a clean, live header without draining it.

How warm can the facility water run in Indiana?

Facility water in Indiana can run warm enough to reach the outdoor dry coolers without chillers on most hours of the year, because the state’s normal highs exceed 80 degrees Fahrenheit for only a few months and sit below about 52 degrees from November through March at Indianapolis. A dry cooler typically delivers fluid a few to roughly ten degrees Fahrenheit above the outdoor dry bulb, so the supply temperature the racks accept translates directly into the share of the year that needs no compressor.

ASHRAE facility water classes and how each fits Indiana weather
Facility water class (max supply)Typical heat rejection in IndianaWhere chillers still runNotes for Indiana sites
W17 (17 C, about 63 F)Chillers with waterside economizerMost of the warm season and shoulder monthsCommon where liquid loops share an existing chilled water plant
W27 (27 C, about 81 F)Dry or fluid coolers with chiller trimSummer days and humid nights, more often in EvansvilleGood fit for retrofits fed from an upgraded plant
W32 (32 C, about 90 F)Dry coolers for most hours; evaporative or chiller trim at peakHottest afternoons across Central and Southern IndianaA common target for new cold plate halls
W40 to W45 (40 to 45 C, about 104 to 113 F)Dry coolers all year in most of the stateRarely, if everOpens heat reuse; check that every rack and CDU is rated for it

The table is general. Paul Industries checks the chosen class against the design dry bulb for the nearest weather station, the dry cooler approach, and the temperature rise through the CDU, since a two or three degree approach at each exchanger adds up between the outdoor air and the cold plate.

Glycol, an intermediate exchanger, or treated water outdoors?

Freeze protection is required on any Indiana liquid cooling loop that runs outdoors, because January normal lows near 21 degrees Fahrenheit at Indianapolis, and colder nights in the north, will freeze water in a dry cooler coil that loses flow. Designers choose between glycol in the whole facility loop, glycol in an outdoor loop separated by a plate heat exchanger, and drain-down or controls-based protection.

Glycol throughout is simplest to build, but propylene glycol carries less heat per gallon than water and is thicker, so pumps, pipe and exchangers grow and the CDUs must be rated for the mixture. An intermediate exchanger keeps glycol outside and lets the indoor loop run on treated water, at the cost of one more approach temperature and one more piece of equipment to maintain. Drain-down and minimum-flow controls are reserved for small or well-sheltered systems, because one failed valve in a February storm can split a coil. Paul Industries works the choice through the energy model and the rack supply limit, and builds the freeze sequences into the controls before the first winter.

The rack-side technology cooling loop is separate from all of this. It runs on the fluid the rack or CDU maker specifies, often treated water or a propylene glycol mixture such as PG25, and it stays indoors.

Can an Indiana liquid loop heat buildings with its waste heat?

An Indiana liquid cooling loop can heat buildings with its waste heat when it runs warm enough, and Indiana’s long heating season gives that heat somewhere to go. NOAA’s normals put Indianapolis at about 5,250 heating degree days a year and South Bend near 6,400, several times their cooling degree days, so a campus that rejects heat all winter sits beside offices, warehouses and plants that buy heat all winter.

Return water from a W40 or W45 loop leaves the CDUs warm enough to preheat ventilation air or domestic water directly, and a heat pump can lift it to the temperature a hot water heating system needs. The engineering is straightforward; the questions are commercial and practical: who takes the heat, how far it has to go, and what serves the heating load when the IT load drops. Paul Industries designs the heat recovery exchanger, the isolation and bypass valves that let the data hall run whatever the heat customer is doing, and the controls that send heat outdoors whenever the building side cannot take it. Office and support spaces on the same campus are the simplest first customer, because the pipe runs are short and one owner controls both ends.

Rear doors and in-row coils for Indiana colocation suites

Rear-door heat exchangers and in-row coils suit Indiana colocation suites where a tenant needs more density than the room’s air system supports but the racks themselves are air cooled. A rear door removes heat at the back of the rack with chilled or warm water, so the room sees close to neutral exhaust air, and the existing air handlers keep handling humidity and the remaining load.

The piping question in a multi-tenant suite is access. Supply and return branches have to reach each door without crossing another tenant’s cage, valves must be reachable from the tenant’s own space, and drip protection has to sit over any equipment below the pipe. Doors also need water above the room dew point, which in an Indiana summer means the water temperature control has to follow the room’s humidity, not just the load. Paul Industries runs those branches from the existing chilled water plant or from a new CDU loop and sets the control so condensation never forms on the coil face.

Fill water and chemistry on hard Indiana supplies

Fill water for an Indiana liquid cooling loop has to be treated, because most Indiana supplies are very hard: the Indianapolis utility puts its typical hardness between 200 and 350 milligrams per liter, expressed as calcium carbonate. Untreated city water left in a warm loop deposits scale in microchannel cold plates, whose passages are a fraction of a millimeter wide, and dissolved oxygen and chloride feed corrosion of copper and steel.

Paul Industries fills technology cooling loops with deionized, reverse osmosis or softened water as the equipment maker specifies, adds the inhibitor package and biocide called for, and records the starting conductivity, pH and inhibitor level. Top-up connections get their own treated supply or a dosing pot, so nobody tops up a cold plate loop from a hose bib. Where the fill comes from the potable water system, the connection gets the backflow protection the Indiana Plumbing Code requires. For sites that need a permanent high-purity supply for fill and top-up, the treatment plant is covered on ultrapure water systems in Indiana.

Is data center water cooling closed loop on Indiana campuses?

Data center water cooling on most new Indiana liquid-cooled campuses is closed loop: the water or coolant that touches the cold plates stays in a sealed loop, and the heat crosses a heat exchanger to a second loop that rejects it outdoors. Whether the outdoor side evaporates water depends on the heat rejection choice, not on the liquid cooling itself.

A closed-loop facility side with dry coolers consumes almost no water after the initial fill, which is why campuses in Indiana describe their cooling as recirculating. A facility side with open cooling towers still evaporates water and still needs the air permit IDEM requires for towers on data centers. Many Indiana designs sit between the two, with dry coolers carrying the year and adiabatic or evaporative assistance on peak afternoons. The trade-offs for the whole plant are set out on data center cooling in Indiana.

CDUs, expansion tanks and Indiana’s pressure vessel rules

Indiana’s Boiler and Pressure Vessel Rules, 675 IAC 30, reach unfired pressure vessels such as expansion tanks, air separators and buffer tanks in a liquid cooling plant unless a listed exclusion applies, and the exclusions turn on chamber volume, relief setting, contents and location. Most small vessels inside a CDU fall below the thresholds; large loop expansion and buffer tanks often do not.

How 675 IAC 30 treats vessels in a liquid cooling plant
Vessel condition (each chamber)Status under 675 IAC 30-1-2(f)Typical liquid cooling example
1.5 cubic feet or less, any pressure, any locationOutside the articleSmall CDU expansion tanks and filter housings
15 cubic feet or less, relief at 300 psig or less, outside a place of public assemblyOutside the articleRow-level expansion tanks and air separators in a data hall
Every chamber relieved at 15 psig or lessOutside the articleAtmospheric or low-pressure reservoirs
Operated entirely full of water or a liquid no more hazardous, at 180 F or lessOutside the articleLiquid-full buffer vessels with no air cushion
Larger than the limits aboveRegulated: ASME construction, operating permit, inspection on the permit cycleCentral plant expansion tanks with an air or nitrogen cushion

Regulated unfired vessels in Indiana normally carry an operating permit that expires after three years, with external inspection on that cycle. Paul Industries sizes and specifies vessels with those limits in view, supplies ASME-constructed vessels with their data reports where the article applies, and lists every vessel’s volume and relief setting in the turnover records so the owner knows which ones the state inspects.

Retrofitting liquid cooling into an existing Indiana room

Retrofitting liquid cooling into an existing Indiana room starts with the plant that is already there: its chilled water temperature, spare capacity, pipe routes and power. A room on 44 to 45 degree chilled water can feed liquid-to-liquid CDUs directly, but it gives up the free cooling hours that warmer water would earn; a room that can raise its loop temperature, or add a separate warm-water loop with its own dry cooler, gets much more out of an Indiana winter.

The common Indiana cases are university research computing, hospital and insurance data rooms in Indianapolis, manufacturing plant rooms that host production systems, and colocation suites in the metro areas. Each has a live air-cooled load that must keep running. Paul Industries surveys pipe routes above the ceiling or under the floor, finds tie-in points on the existing headers, plans hot taps or line stops where draining is not acceptable, and stages the work so each step leaves the room with full cooling. Where the existing chillers need repair or replacement before they can carry new load, that work runs under chiller repair in Indiana.

Leak detection goes in with the piping: rope sensors under manifolds and along drip trays, spot sensors at CDUs, and alarms wired to the building system with automatic isolation where the owner wants it.

Condensation and humid Indiana summers

Condensation is the liquid cooling risk that Indiana summers sharpen, because NOAA’s hourly normals put the average July dew point at Indianapolis near 65 degrees Fahrenheit and at Evansville near 68. Any pipe, manifold or cold plate carrying water below the dew point of the air around it will sweat, and water dripping inside a rack is the failure liquid cooling is meant to avoid.

Warm-water loops avoid the problem by design, since W27 and warmer supply sits well above any indoor dew point. The risk returns in three places: retrofits that feed CDUs from a cold chilled water plant, rear doors and in-row coils on chilled water, and outdoor or unconditioned spaces such as mechanical galleries where humid air reaches cold pipe. Paul Industries insulates cold piping with a sealed vapor retarder, sets CDU supply control to track the measured room dew point with a margin, and adds dew point sensors in galleries where outdoor air enters. In winter the same galleries swing the other way, and heat tracing protects pipe that runs near louvers or exterior walls.

Testing a liquid cooling loop before racks connect

Testing a liquid cooling loop in Indiana follows the same sequence as anywhere, pressure test, flush, fill, vent and verify chemistry, but winter construction adds one step: water must never sit in piping in an unheated shell. A hydrostatic test on an outdoor header in January needs either heated enclosures, a glycol test medium accepted by the engineer, or a prompt drain and blow-down after the hold.

Paul Industries pressure tests to ASME B31.9 or the project specification, flushes to a cleanliness target agreed with the CDU and rack makers, usually measured by particle count or filter inspection, then fills and vents with treated water. Each branch is recorded before it is opened to a rack. The integrated tests that follow, with heat load banks and failure scenarios, are covered on data center commissioning in Indiana.

Data center liquid cooling maintenance through an Indiana year

Data center liquid cooling maintenance in Indiana combines the indoor loop’s water chemistry and filtration with seasonal work on the outdoor heat rejection equipment, whose demands change sharply between July and January. A program that treats both together keeps the cold plates clean and the dry coolers ready.

A seasonal liquid cooling maintenance calendar for Indiana
WhenIndoor loopOutdoor loop and heat rejection
MonthlyConductivity, pH, inhibitor level, filter differential pressureFan and pump status, alarm history
SpringBiological and particle samplingCoil cleaning after winter salt and debris; adiabatic pads or sprays put back in service
Early summerCheck CDU approach against commissioning dataConfirm trim chiller or evaporative assist before the humid season
AutumnFilter change and strainer cleaningGlycol concentration and inhibitor test; heat tracing and freeze sequences tested
WinterMonitor for condensation risk if supply drops lowSnow and ice clearance at coil inlets; watch minimum flow alarms

Paul Industries provides that program under service contracts covering CDUs, pumps, dry coolers and the facility plant together.

Data center liquid cooling cost in Indiana: what sets the number

Data center liquid cooling cost in Indiana is set by the rack density and count, the CDU arrangement and redundancy, the length and size of the facility loop, the freeze protection method, the fill water treatment and how much of the work happens inside a live room. New campus installations price per megawatt of liquid-cooled load; retrofits price by the room, because surveys, tie-ins and night work dominate.

Indiana adds identifiable items to the estimate: glycol and the larger pumps and exchangers it needs, or an intermediate heat exchanger; heat tracing and freeze controls; treated fill water on hard supplies; and ASME vessels where tank sizes cross the 675 IAC 30 limits. Paul Industries gives a budget range from comparable scope once rack count and density are known, and a firm price once routes and equipment are fixed.

Who installs and starts up liquid cooling for Indiana data centers?

Paul Industries installs and starts up liquid cooling for Indiana data centers, from CDUs and rack manifolds to facility loops, dry coolers and trim chillers. Paul Industries is headquartered at 256 Shore Drive, Kilmarnock, Virginia, and takes work across Indiana, in all 50 states and abroad. The scope covers Central Indiana and Boone County, Northwest Indiana and the Calumet region, South Bend and Elkhart, Fort Wayne, Lafayette, Kokomo, Columbus, Evansville and the Ohio River counties.

The wider mechanical package for a campus is on data center mechanical contractor in Indiana. The same service in the headquarters state is on data center liquid cooling in Virginia, and a cooler-climate comparison is on data center liquid cooling in Pennsylvania.

Paul Industries scope on Indiana liquid cooling

Paul Industries designs, supplies, prefabricates, installs, tests, starts up and maintains liquid cooling for Indiana data centers: CDUs, manifolds, technology and facility loops, dry coolers, trim chillers, freeze protection, water treatment, leak detection and the ASME vessels that serve them. Owners choose supply only, design-build or complete installation. See Indiana for the state overview and the Midwest for the region. Send rack counts, densities, supply temperature limits and drawings, then call 201-450-8280 or request a quote.

Standards referenced: ASHRAE TC 9.9 Liquid Cooling Guidelines (W classes) · Indiana Boiler and Pressure Vessel Rules, 675 IAC 30 · Indiana Mechanical Code, 675 IAC 18-1.6 · Indiana Plumbing Code, 675 IAC 16-1.4 · ASME B31.9 · ASME Boiler and Pressure Vessel Code, Section VIII

Frequently asked questions

Who installs liquid cooling for data centers around Lebanon and Boone County?

Paul Industries installs CDUs, manifolds, facility loops and dry coolers for data centers in Lebanon, Boone County and the corridors northwest of Indianapolis. New campuses there are being designed around closed-loop liquid cooling, so the work starts with header sizing for the final load and valved branches for later phases.

Does Paul Industries add liquid cooling to existing rooms in Indianapolis?

Yes. Paul Industries retrofits liquid cooling into enterprise, hospital, university and colocation rooms across Indianapolis and Central Indiana. Each job begins with a survey of the existing chilled water plant, pipe routes and power, then a staged plan that keeps the air-cooled load running while CDUs and manifolds are tied in.

Can Paul Industries pipe liquid-cooled halls in South Bend, New Carlisle and Northern Indiana?

Paul Industries takes liquid cooling work across St. Joseph, Elkhart and LaPorte counties and the rest of Northern Indiana. South Bend’s cool summers let warm-water loops run on dry coolers for nearly the whole year, while its winters make glycol or an intermediate heat exchanger a requirement on every outdoor loop.

Who handles liquid cooling for data rooms in Evansville and Southern Indiana?

Paul Industries installs and services liquid cooling in Evansville, Jeffersonville and the Ohio River counties. Evansville has the longest cooling season of Indiana’s main weather stations, so dry cooler loops there need more chiller or evaporative trim on humid afternoons than the same design in the north.

Which facility water temperature should an Indiana liquid-cooled hall use?

The warmest temperature every rack and CDU is rated for, because each extra degree adds dry cooler hours. Many new cold plate halls target the ASHRAE W32 class, about 90 degrees Fahrenheit supply, which runs on dry coolers for most Indiana hours. W40 to W45 designs run dry nearly all year.

Does an Indiana liquid cooling loop need glycol?

Any loop that runs outdoors in Indiana needs freeze protection, and glycol is the usual answer. The choice is whether glycol fills the whole facility loop or stays in an outdoor loop behind a plate heat exchanger. The indoor rack loop uses whatever fluid the rack or CDU maker specifies.

Can Indianapolis city water be used to fill a cold plate loop?

Untreated, no. Indianapolis water typically carries 200 to 350 milligrams per liter of hardness, enough to scale the fine passages of a cold plate. Loops are filled with deionized, reverse osmosis or softened water as the equipment maker specifies, then dosed with inhibitor and biocide and logged.

Does a CDU expansion tank need an Indiana pressure vessel permit?

Usually not, because 675 IAC 30 excludes vessels whose chambers hold 1.5 cubic feet or less at any pressure, and 15 cubic feet or less with relief at 300 psig or less outside places of public assembly. Larger central plant expansion and buffer tanks often exceed those limits and need ASME construction and an operating permit.

How does Meta's Lebanon campus describe its liquid cooling?

Meta describes its Lebanon campus, under construction since February 2026, as using a water-efficient closed-loop, liquid-cooled system that recirculates the same water and uses no water for most of the year. That is a public market fact about the campus, and it reflects the direction many new Indiana halls are taking.

Can dry coolers carry a liquid-cooled Indiana hall through July?

For warm-water designs at W40 and above, usually yes. At W32, dry coolers carry most July hours, but humid afternoons when the outdoor dry bulb passes the high 80s need trim from a chiller or evaporative assist. Paul Industries checks the dry cooler approach against the site’s design dry bulb before fixing the class.

How is a liquid cooling loop tested during an Indiana winter build?

The loop is pressure tested, flushed and filled like any other, but water cannot sit in pipe exposed to freezing. Outdoor sections are tested in heated enclosures, with an engineer-approved glycol test medium, or drained and blown down right after the hold. Indoor sections wait for heat in the building.

What leak detection goes in with Indiana liquid cooling piping?

Rope sensors under rack manifolds and along drip trays, spot sensors at CDUs and low points, and alarms wired to the building management system. Many owners add automatic isolation valves on each row so a detected leak closes the branch. Paul Industries installs and tests the detection with the piping.

How long does a liquid cooling retrofit take in an occupied Indiana room?

Duration depends on rack count, pipe routes and outage windows more than on the CDUs. A few rows in a room with a usable chilled water header move faster than a room needing a new warm-water loop and dry cooler. Paul Industries sets the schedule after the site survey, around the tie-in windows the owner can give.

Can liquid cooling piping go in before the racks reach an Indiana site?

Yes. Headers, branches and valves are installed, pressure tested, flushed and left filled with treated water or capped dry, depending on the timeline. When racks arrive, each branch is connected, vented and logged. That order lets the facility loop be proven while the IT schedule is still moving.

Does Paul Industries offer supply-only CDUs and manifolds in Indiana?

Yes. Paul Industries supplies CDUs, manifolds, dry coolers, pumps, heat exchangers and prefabricated piping skids on a supply-only basis, with submittals and startup support, and offers design-build and complete installation for the same equipment.

What should be sent to scope liquid cooling for an Indiana data center?

Send the rack count and density by phase, the rack and CDU makers’ supply temperature and fluid requirements, the existing plant data for retrofits, drawings or a site plan, and the site location. Call 201-450-8280 or use the quote form.