Paul Industries works as a data center mechanical contractor in Ohio, building central chilled water plants, campus yard piping, computer room air handling, liquid cooling distribution, generator fuel piping and the prefabricated pipe racks that tie them together. The Ohio market moves on numbers a mechanical plan has to respect: a pipeline of 53 data center buildings under construction and 140 more planned, a state sales tax exemption that covers cooling systems but stopped taking new requests in May 2026, and an AEP Ohio tariff whose four-year ramp suits phased builds. Paul Industries is headquartered at 256 Shore Drive in Kilmarnock, Virginia, and takes data center mechanical work across Ohio and nationwide.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Ohio pipeline 82 operating, 53 under construction, 140 planned buildings (Cleanview, Nov 2026)
Top counties Licking, Franklin and Union lead operating capacity
Tax exemption ORC 122.175 covers cooling systems; new requests paused since May 2026
AEP Ohio ramp Contract minimums of 50, 65, 80 and 90% in years one to four
Reviewed November 2026

What a data center mechanical contractor in Ohio builds and delivers

A data center mechanical contractor in Ohio builds the systems that move heat out of the data halls and keep the backup plant fed: chillers, cooling towers or dry coolers, pumps and headers, CRAH galleries or fan walls, liquid cooling CDUs and manifolds, campus loops between buildings, fuel oil piping for generators, plumbing, and the controls that run it all. On a multi-building Ohio campus the scope also includes the shared central plant, utility tunnels or yard pipe racks, and the tie-ins that let a new building join a loop already serving operating halls.

The national outline of that scope is on the data center mechanical contractors page. This page goes into the Ohio market, the Ohio rules that land on the mechanical package, and the numbers that change how an Ohio campus should be phased and priced.

How many data centers in Ohio are operating, under construction and planned?

Ohio had 82 operating data center buildings, 53 under construction and 140 planned as of November 17, 2026, grouped into 19, 18 and 33 campuses respectively, according to the Cleanview tracker. Counts differ by method: a University of Virginia Weldon Cooper Center report released in January 2026 counted more than 100 operational data centers in Ohio and 77 more expected by 2030, and other directories count colocation suites and enterprise rooms that the trackers leave out.

The data centers in Ohio being built now are larger than the older ones. The same Weldon Cooper report expected data centers’ share of Ohio’s energy use to roughly double, from 5.3 percent to 10.9 percent, within four years. For a mechanical contractor, that means fewer small rooms and more multi-building campuses with central plants, long yard piping runs and phased expansions, often on greenfield sites in counties that had little heavy construction before.

Where are data centers in Ohio located, region by region?

Data centers in Ohio cluster most heavily in Central Ohio, where Licking, Franklin and Union counties lead operating capacity in the Cleanview tracker, with smaller groups around Cincinnati and Dayton, Cleveland and Akron, and Toledo. The location of data centers in Ohio decides the climate the plant is sized for, the utility that serves it, and the water and sewer route for any evaporative cooling.

Ohio data center regions and what each one asks of the mechanical plan
RegionMain investor-owned utilityDesign wet bulb (0.4%, 2021 to 2025)Mechanical planning notes
Central Ohio: Columbus, New Albany, Licking and Union countiesAEP Ohio77.2 F at ColumbusSchedule DCT ramp for large loads; Columbus water allotments in business parks; phased campus loops
Southwest Ohio: Cincinnati and its northern suburbsDuke Energy Ohio78.3 F at LunkenHottest, most humid Ohio summers; extra margin on towers and dehumidification
Miami Valley: Dayton and surrounding countiesAES Ohio77.2 F at DaytonWeather close to Columbus, so plants size to a similar wet bulb and economizer split
Northeast Ohio: Cleveland, Akron, Canton, YoungstownFirstEnergy (Cleveland Electric Illuminating, Ohio Edison)76.2 F at Cleveland, 75.2 F at YoungstownMore economizer hours; deep winter cold at Akron-Canton
Northwest Ohio: Toledo and LimaToledo Edison (FirstEnergy) at Toledo76.7 F at ToledoColdest winters studied; Lake Erie watershed water rules for large withdrawals

Data centers in Central Ohio dominate the pipeline, but data centers in Cincinnati, Ohio and data centers in Northeast Ohio carry their own demand from enterprise owners, hospitals, universities and colocation providers. Paul Industries plans each region’s plant from its own station weather and utility tariff rather than a statewide average. All of these utilities sit inside the PJM regional grid.

Who is building data centers in Ohio, according to the public record?

Hyperscale cloud and social media companies, colocation developers and enterprise owners are all building data centers in Ohio. Cleanview’s list of the largest data centers in Ohio by operating capacity includes Meta’s New Albany campus, at about 637 MW, and Google’s Columbus campus, at about 400 MW. Google data centers in Ohio at New Albany and Columbus also appear in public water records reported in 2026. The New Albany International Business Park alone holds about 40 data centers on 12,000 acres.

Those names are market facts about Ohio. What they mean for any owner planning new data centers in Ohio is competition for the same inputs: utility capacity, long-lead chillers and switchgear, skilled field labor and laydown space. Proposed data centers in Ohio that lock in equipment and prefabrication early hold their schedules better.

Why are there so many data centers in Ohio?

Ohio has drawn so many data centers through a combination of planned industrial land with utilities, a state sales tax exemption for data center equipment, and utilities inside the PJM regional grid. Business parks such as New Albany planned water and power for heavy users years ahead, with a Columbus water service plan for the New Albany park approved in 2015. The Tax Credit Authority has granted exemptions under Ohio Revised Code 122.175, and the state reported that data centers already holding those benefits reported $27.2 billion of capital investment in 2025.

What are data centers in Ohio used for? The same things as anywhere: cloud services, social media, enterprise systems, research computing and, increasingly, dense accelerator clusters. Are there data centers in Ohio outside Central Ohio? Yes, in every major metro, and the trackers list planned campuses in rural counties as well. For mechanical planning, the reason a campus chose Ohio matters less than the conditions it now faces there.

Ohio data center tax exemption: what it covers on the mechanical scope

The Ohio data center tax exemption under Ohio Revised Code 122.175 lets the Tax Credit Authority exempt all or part of the sales and use tax on computer data center equipment, which the statute defines to include equipment cooling systems, electrical equipment and building and construction materials sold to contractors for incorporation into the data center. The exemption also extends to charges for delivering, installing and repairing exempt equipment, which puts much of a mechanical package inside its reach.

Elements of the Ohio data center sales tax exemption that matter to the mechanical package
ElementWhat Ohio Revised Code 122.175 saysMechanical scope impact
Covered equipmentEquipment cooling systems, power equipment and construction materials sold to contractorsChillers, towers, CRAHs, CDUs, pipe and fittings bought for the project
Covered servicesDelivery, installation and repair of exempt equipmentInstallation labor billed on exempt equipment
Investment testAt least $100 million over three consecutive years for projects begun in or after 2015Campus phasing and procurement timing
Payroll testAt least $1.5 million a year in site compensation from the 25th monthOwner obligation; no direct mechanical effect
Percentage and termSet in each agreement by the Tax Credit AuthorityPurchase orders must follow the agreement’s terms and dates
Status of new requestsPaused by the governor’s direction on May 27, 2026; approved agreements remainNew projects price the mechanical package with full sales tax unless an agreement exists

The money is real. Ohio’s state sales tax rate is 5.75 percent before county additions, so on $40 million of mechanical equipment and materials the state share alone is about $2.3 million, and a 50 percent exemption saves about $1.15 million. Ohio data center tax incentives were under review by a joint legislative committee in 2026, after the General Assembly passed a repeal in the 2025 budget that the governor vetoed. Paul Industries structures purchasing so exempt items are bought, documented and invoiced in line with the owner’s agreement.

How AEP Ohio’s ramp schedule shapes a phased mechanical build

AEP Ohio’s data center tariff, Schedule DCT, ramps a new large customer’s minimum contract capacity over up to four years, at 50 percent in year one, 65 percent in year two, 80 percent in year three and 90 percent in year four, which lines up naturally with a campus that brings halls online in phases. A 60 MW contract, for example, steps through minimums of 30, 39, 48 and 54 MW.

The mechanical plan should mirror that ramp. Paul Industries sizes yard headers, central plant buildings, electrical rooms for pumps and the main pipe racks for full build-out on day one, because trenching and racking twice costs far more than oversizing once. Chillers, towers, pumps and air handlers then go in by phase, timed to the IT ramp, so capital follows load. Valved and capped connections at every future tie-in point let later phases join the loop without shutting down operating halls. Power and cooling density questions for liquid-cooled phases are covered on data center liquid cooling in Ohio.

Ohio rules on the data center mechanical scope

Ohio rules on the data center mechanical scope come from the Board of Building Standards, the Division of Industrial Compliance, the State Fire Marshal, the Ohio Construction Industry Licensing Board and Ohio EPA. The table collects the ones a mechanical package touches most often.

Ohio rules that apply to data center mechanical work
TopicOhio rule and agencyWhat it requires of the work
Building and mechanical code2024 Ohio Building Code and Ohio Mechanical Code, effective March 1, 2024Design, installation and tests to the 2021 International codes with Ohio amendments
Trade licensingOhio Revised Code Chapter 4740, Ohio Construction Industry Licensing BoardHVAC, refrigeration, plumbing, hydronics and electrical contracting on commercial projects is done under OCILB licenses
Pressure vesselsOhio Revised Code 4104.10, Superintendent of Industrial ComplianceInspection in fabrication and a filed data report before a vessel operates
Underground generator fuel tanksOhio Administrative Code Chapter 1301:7-9, BUSTR in the State Fire Marshal’s officeEmergency generator tanks installed since May 16, 2011 meet the full underground tank rules
Construction stormwaterOhio EPA Construction Stormwater General PermitNotice of intent, approval letter and a stormwater pollution prevention plan for sites disturbing one acre or more
Generator air permitsOhio EPA Division of Air Pollution ControlAir permit for emergency generators even with limited run hours
Prevailing wageOhio Revised Code 4115.03 to 4115.16Prevailing wages on public improvements by public authorities, including publicly funded institutions

Testing and filings tied to these rules are carried through to turnover on data center commissioning in Ohio. Process-grade piping beyond the building services scope follows the practice on process piping in Ohio, and structural steel pipe racks are welded to AWS D1.1 alongside industrial welding services in Ohio.

Cooling water, sewer and withdrawal rules for an Ohio campus

Cooling water for an Ohio data center campus comes from a municipal system, from on-site wells, or from a mix, and each route brings its own Ohio rules. Business parks in Central Ohio plan supply in advance: the New Albany park’s water service plan with Columbus dates to 2015 and allows 16 million gallons a day. A campus with its own wells able to withdraw more than 100,000 gallons a day registers the facility with the Ohio Department of Natural Resources’ Division of Water Resources and reports withdrawals each year.

Sites in the Lake Erie watershed, which takes in Toledo, Cleveland and much of northern Ohio, face a further test under the Great Lakes compact. Ohio Revised Code 1522.12 requires a withdrawal and consumptive use permit for new or increased capacity of at least 2.5 million gallons a day from Lake Erie, 1 million gallons a day from rivers, streams or groundwater in the watershed, or 100,000 gallons a day from a high quality stream. Blowdown leaving the site goes to a public sewer or, where none is available, to a stream under an individual Ohio EPA discharge permit.

These rules shape the mechanical design as much as the weather does. Paul Industries compares water-cooled, hybrid and air-cooled plants for each campus, with water use, blowdown volume and permit steps set beside energy cost, so the owner picks a plant that the site’s water and sewer can actually carry.

Generator fuel and backup plant piping

Generator fuel systems on an Ohio data center campus include bulk storage, day tanks, transfer pumps, filtration and the fuel oil piping between them, and each part has an Ohio rule behind it. Underground tanks for emergency generators fall under the State Fire Marshal’s underground storage tank rules, including release detection, and the generators themselves need an Ohio EPA air permit. Paul Industries builds fuel piping with double-wall or contained sections where the design calls for them, pressure tests and flushes the lines, and proves transfer pump controls and alarms before the first generator test run.

Building plants ready for liquid cooling

Plants built on Ohio campuses in 2026 should be ready for liquid cooling even where the first halls are air cooled, because rack densities keep climbing and a central plant lasts far longer than a server generation. Readiness means headers with valved, capped branches for future CDU loops, chilled water temperatures that can be raised without starving the air handlers, room in the yard for dry coolers, and pumps and controls that can serve a warm-water loop. Paul Industries designs those provisions into the first phase so a later liquid-cooled hall connects with a tie-in rather than a plant rebuild.

Prefabrication and winter field work on Ohio campuses

Prefabrication suits Ohio data center campuses because winter cuts into outdoor productivity and quality. In the February 2021 cold spell, Columbus went more than sixteen days without rising above 32 F, and over the five years studied Toledo and Lima each logged between 80 and 92 hours a year at 10 F or colder. Welding, pressure testing and insulation of yard piping in those conditions need heated enclosures, preheat and careful scheduling.

Paul Industries moves as much of that work as possible into controlled shops off site: pipe rack modules with headers, supports and cable tray, pump skids with valves and instruments, chiller connection spools and CDU manifold assemblies. Modules arrive tested, cleaned and capped, and are set and connected in days rather than built in place over weeks. The rest of the field schedule follows the season: yard piping and tower work in the warm months, interior fit-out and tie-ins through the winter.

What Ohio owners should ask of a data center mechanical contractor

Ohio owners should ask a data center mechanical contractor how it will phase the plant against the utility ramp, how much of the scope it will prefabricate, how it handles exempt purchasing under a Tax Credit Authority agreement, how it schedules winter work, and what records come with turnover. An Ohio mechanical contractor on a campus should also show how new buildings join a live loop without risk to operating halls.

Paul Industries answers each of those in the proposal: a phasing plan tied to the IT and utility ramps, a prefabrication list, a purchasing plan for exempt items, a seasonal field schedule, and a sample turnover package with test reports, vessel filings, flushing records and sequences. One contract carries design, fabrication, installation and startup, so responsibility for the plant sits in one place.

Data center mechanical cost in Ohio: what moves the number

Data center mechanical cost in Ohio moves with the cooling architecture, the redundancy level, campus size and phasing, the amount of prefabrication, winter conditions during the schedule, and whether the owner holds a sales tax agreement. Equipment lead times and escalation affect every Ohio campus competing for the same chillers, switchgear and towers, so early procurement often saves more than any design tweak.

Operating cost belongs in the comparison too. Ohio’s average commercial electricity price for January through August 2026 was 13.61 cents per kWh, up from 11.17 cents a year earlier, which makes efficient pumping, economizers and warm-water cooling worth more than they were. Paul Industries prices Ohio packages as design-build, as complete installation to an owner’s engineered drawings, or as supply of prefabricated racks, skids and spools, with a budget range from comparable scope and a firm number once drawings and phasing are fixed. Cooling plant choices are compared in detail on data center cooling in Ohio.

Who installs and builds the mechanical systems in Ohio data centers?

Paul Industries installs and builds the mechanical systems in Ohio data centers, from central plants and yard piping to the white floor and the generator yard. Work covers new campuses in Central Ohio, expansions beside operating halls in Southwest and Northeast Ohio, and upgrades to enterprise rooms in Dayton, Toledo and beyond. Chillers already in service are kept running through chiller repair in Ohio.

On a typical Ohio campus phase, the Paul Industries scope runs from shop drawings and coordination models through fabrication of racks and skids, setting of chillers, towers and air handlers, welding and testing of chilled water, condenser water and fuel piping, insulation and heat tracing for the winter, controls installation, flushing and water treatment startup, and support through functional and integrated testing. After turnover, service agreements keep the plant on its maintenance schedule, with seasonal tower and economizer checks matched to Ohio’s weather and records kept for the next phase’s tie-ins.

The same mechanical scope is offered across the Midwest and in neighboring markets, including data center mechanical work in Pennsylvania and the headquarters state through data center mechanical contractor work in Virginia.

One mechanical contract for Ohio data center campuses

Paul Industries brings Ohio data center owners one accountable mechanical contract: plants sized to the station weather, phasing matched to the utility ramp, purchasing that follows the tax agreement, prefabrication that beats the winter, and a turnover package that stands up to every inspector and auditor. From New Albany and Columbus to Cincinnati, Cleveland and Toledo, see the Ohio page or request a quote.

Standards referenced: Ohio Building Code and Ohio Mechanical Code (2021 International codes with Ohio amendments) · Ohio Revised Code 122.175 · Ohio Revised Code Chapter 4740 (OCILB) · Ohio Revised Code 4104.10 · Ohio Administrative Code Chapter 1301:7-9 (BUSTR) · Ohio EPA Construction Stormwater General Permit · ASME B31.9 · ASME B31.1 · AWS D1.1

Frequently asked questions

Which contractor builds central plants for data center campuses in New Albany and Licking County?

Paul Industries builds central chilled water plants, yard piping and campus loops for data center campuses in New Albany, Johnstown and across Licking County, the county with the most operating data center capacity in the Cleanview tracker. Work is phased to the AEP Ohio ramp and prefabricated off site to beat Ohio winters. Paul Industries also ties new buildings into loops serving live halls.

Does Paul Industries take data center mechanical work in Cincinnati, Dayton and Southwest Ohio?

Paul Industries takes data center mechanical work in Cincinnati, Dayton, Mason and the I-75 corridor between them. Southwest Ohio has the state’s most humid summers, with a 78.3 F design wet bulb at Cincinnati’s Lunken airport from 2021 to 2025, so towers, chillers and dehumidification carry extra margin. Duke Energy Ohio and AES Ohio serve most of the region.

Who handles data center mechanical systems in Cleveland, Akron and Youngstown?

Paul Industries handles data center mechanical systems in Cleveland, Akron, Canton and Youngstown, for colocation halls, hospital and university rooms and enterprise sites. Northeast Ohio’s cooler summers give waterside economizers more hours, while lows near minus 10 F at Akron-Canton call for freeze protection on every outdoor component. FirstEnergy’s Ohio utilities serve most sites there.

Does Paul Industries build data center mechanical systems in Toledo and Northwest Ohio?

Paul Industries builds data center mechanical systems in Toledo, Perrysburg, Lima and Findlay. Northwest Ohio had the coldest winters of the stations studied, with Lima averaging about 92 hours a year at or below 10 F, so heat tracing, glycol and winter scheduling get extra attention. Sites in the Lake Erie watershed also check the state’s withdrawal permit thresholds for large water use.

How many data centers in Ohio are under construction right now?

The Cleanview tracker listed 53 data center buildings under construction in Ohio on November 17, 2026, across 18 campuses, with 82 buildings operating and 140 planned. Other sources count differently, so the figures are best read as an order of magnitude. For mechanical contractors, the pipeline means sustained demand for chillers, towers, pipe and skilled field labor across Ohio.

Are data centers banned in Ohio?

Data centers are not banned in Ohio. In May 2026 the governor paused new requests for the data center sales tax exemption while a joint legislative committee studies the industry, and his office described the step as a pause on tax exemption requests rather than a ban. Approved agreements remain in place, and construction continues across the state.

Is installation labor on exempt data center equipment taxed in Ohio?

Ohio Revised Code 122.175 extends the data center exemption to charges for delivering, installing and repairing exempt computer data center equipment, which the statute defines to include equipment cooling systems. The percentage and term come from each agreement with the Tax Credit Authority. Paul Industries invoices exempt items and installation in the form the owner’s agreement requires.

Can a new Ohio data center still get the sales tax exemption in 2026?

The Tax Credit Authority stopped considering new data center exemption requests after the governor’s May 27, 2026 direction, while a joint legislative committee studies data centers. Projects with approved agreements keep them. A new campus without an agreement should price its mechanical package at full sales tax until the policy changes. Paul Industries prices both cases when an owner asks.

What does the AEP Ohio ramp mean for chiller procurement?

The AEP Ohio Schedule DCT ramp raises a new data center’s minimum contract capacity from 50 percent in year one to 90 percent in year four, so cooling equipment can arrive in matching phases. Paul Industries buys and installs chillers and towers by phase while building headers, plant rooms and racks for full build-out at the start.

Do underground diesel tanks for Ohio data center generators fall under state rules?

Underground tanks that store fuel for emergency generators in Ohio fall under the Bureau of Underground Storage Tank Regulations rules in Ohio Administrative Code Chapter 1301:7-9, and those installed on or after May 16, 2011 must meet the whole chapter, including release detection. Paul Industries builds the fuel piping and coordinates tank work with those rules.

Does a data center construction site in Ohio need a stormwater permit?

An Ohio data center construction site that disturbs one acre or more needs coverage under Ohio EPA’s Construction Stormwater General Permit, a stormwater pollution prevention plan and a notice of intent with an approval letter before work starts. Stormwater ponds and controls then stay in service after construction. Paul Industries plans yard piping and laydown around those controls.

Does prevailing wage apply to an Ohio data center?

Ohio’s prevailing wage law applies to public improvements built by public authorities, including institutions supported by public funds, so a state university or agency data center is covered when it meets the law’s thresholds. Privately owned campuses follow their contract terms. Paul Industries prices public projects with the required wage determinations and reporting.

Can a warehouse or factory in Ohio be converted into a data hall?

Many Ohio warehouses and factories can become data halls when floor loading, roof height, utility capacity and room for heat rejection equipment check out. Older industrial buildings can offer heavy floors, high bays and truck access that suit a data hall. Paul Industries surveys the building, the mechanical routes and the yard before an owner commits.

How does Paul Industries keep a live Ohio campus loop running during a new building tie-in?

Paul Industries keeps a live Ohio campus loop running during a tie-in by building valved connections for future phases into the original headers, using hot taps where none exist, and working under a written method of procedure with redundancy confirmed at each step. Tie-ins are scheduled for mild weather, when chillers and economizers have the most spare capacity.

What records come with the mechanical turnover on an Ohio data center?

Mechanical turnover on an Ohio data center includes pressure test reports, pressure vessel data reports and filings, refrigerant charge and leak records, flushing and water quality results, valve and equipment tag lists, as-built drawings, sequences and the commissioning report. Paul Industries delivers them in one indexed package for the operator, the owner and future inspectors.

What should an Ohio owner send to price a data center mechanical package?

An Ohio owner should send the site address and utility, the IT load per phase and the build-out target, the cooling basis of design, drawings at their current stage, the phasing schedule, any Tax Credit Authority agreement terms, and the desired delivery route. Paul Industries returns a phased scope, a prefabrication plan, a budget range and a schedule.

Building a data center campus in Ohio?

Send the site, utility, IT load per phase, cooling basis of design and any tax agreement terms. Call 201-450-8280 or request a quote.