Paul Industries designs, prefabricates, installs and starts up data center liquid cooling in Ohio: coolant distribution units, rack manifolds, secondary loops, facility water headers and the dry coolers or chillers behind them. Ohio gives liquid cooling a strong case. Dry coolers alone can hold 32 C facility water for about nine hours in ten at Columbus, Ohio’s best-known academic computing center already runs GPUs on warm-water cold plates, and the AEP Ohio data center tariff rewards every kilowatt a site moves from cooling to computing. Paul Industries, headquartered at 256 Shore Drive in Kilmarnock, Virginia, takes liquid cooling work across Ohio and in all 50 states.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Columbus example OSC Cardinal: 128 H100 GPUs on direct-to-chip cooling via two CDUs
AEP Ohio tariff New data center loads of 25 MW or more bill at least 85% of contract capacity
Dry cooler reach W32 water from dry coolers alone about 91% of Columbus hours
Ohio industrial power 10.23 cents/kWh, January to August 2026 (EIA)
Reviewed November 2026

What does data center liquid cooling in Ohio involve?

Data center liquid cooling in Ohio involves carrying heat from processors and accelerators in a liquid loop, through a coolant distribution unit (CDU), into a facility water system that rejects it outdoors, sized for a climate with humid summers and subzero winters. The core work is the same in any state: cold plates or rear-door coils at the rack, manifolds and hoses, CDUs, a secondary loop with controlled chemistry, and a facility water loop. Ohio adds three planning questions: which facility water class the weather at the site supports without chillers, how to protect outdoor equipment through a Toledo or Akron cold snap, and how cooling power counts against a utility contract.

The general architecture and terms are explained on the national data center liquid cooling page. Here the focus is on Ohio weather data, Ohio utilities, Ohio city water and the Ohio Mechanical Code.

A working Columbus example: the Ohio Supercomputer Center’s Cardinal cluster

The Ohio Supercomputer Center (OSC) brought its Cardinal cluster online in November 2024 at the State of Ohio Computer Center in Columbus, and it cools every node with direct-to-chip liquid cooling fed by two CDUs. Cardinal has 378 Dell nodes in nine racks, including 32 GPU nodes carrying four NVIDIA H100 accelerators each. OSC describes warm water flowing over cold plates on the chips, with a secondary loop of antifreeze-like coolant exchanging heat with the building’s warm water loop.

The OSC example matters to Ohio owners for two reasons. It is the first cluster in OSC’s data center to use direct-to-chip cooling on GPUs, after earlier systems cooled only CPUs that way, which mirrors the path many enterprise halls in Ohio are on now. And it ranked No. 15 on the Green500 list of energy-efficient systems, showing that warm-water cooling in a Columbus building delivers efficiency at research scale. Any other hall still starts from its own loads, redundancy target and existing plant.

How does the AEP Ohio data center tariff change the density math?

The AEP Ohio data center tariff, Schedule DCT, makes new data center loads of 25 MW or more pay for at least 85 percent of their contracted capacity each month, so a site pays for capacity whether it uses it for computing or for cooling. The Public Utilities Commission of Ohio adopted the settlement on July 9, 2025, and the tariff took effect on July 23, 2025. Contracts run through a ramp of up to four years, rising from 50 percent of contract capacity in year one to 90 percent in year four, and then eight more years.

Under a minimum bill like that, cooling power is a direct cost against the contract. A campus with a 100 MW contract is billed for at least 85 MW once ramped. Every megawatt of fans, chillers and pumps that liquid cooling removes is a megawatt that can serve racks under the same contract. That is the strongest Ohio argument for liquid cooling: the Ohio Power data center tariff turns cooling efficiency into usable IT capacity, not just a smaller bill. For sites served by AES Ohio, Duke Energy Ohio or the FirstEnergy utilities, the logic holds wherever demand charges and contract capacity dominate the bill, and Paul Industries checks the actual tariff before sizing anything.

Which facility water temperature can Ohio weather support?

Ohio weather supports warm facility water very well: with dry coolers alone and an assumed 10 F approach, Columbus could have held ASHRAE class W32 water, up to 32 C or 89.6 F, for about 91 percent of hours between 2021 and 2025, and W40 water for all but about 3 hours a year. ASHRAE’s liquid cooling classes name the upper limit of facility water supply temperature, so the class the IT vendor supports decides how much of the year runs without compressors.

Share of hours dry coolers alone could hold each ASHRAE facility water class in Ohio, hourly data 2021 to 2025, assuming a 10 F approach
StationW27 (80.6 F supply)W32 (89.6 F supply)W40 (104 F supply)Hours a year above the W40 limit
Columbus74.4%90.8%100%About 3
Cincinnati (Lunken)74.3%90.1%100%About 4
Dayton74.3%90.9%100%About 2
Lima78.2%92.6%100%About 4
Toledo77.6%91.7%99.9%About 7
Cleveland77.8%93.7%100%About 1
Youngstown81.6%94.5%100%None

The table explains why so many Ohio liquid cooling designs pair dry coolers with a small trim chiller. At W32, Columbus still had about 800 hours a year when the dry bulb ran above the dry cooler’s limit, mostly summer afternoons. A trim chiller, an adiabatic pre-cooling pad or a connection to the existing chilled water plant covers those hours. At W40 the trim stage nearly disappears, but fewer IT products are qualified for water that warm. Paul Industries reads the IT vendor’s class, the station data and the redundancy target together before picking the split.

Data center liquid cooling vs air cooling in an Ohio hall

Data center liquid cooling vs air cooling in an Ohio hall comes down to rack density, fan energy and how many hours the plant can run without compressors. Air cooling handles moderate racks well and lets an Ohio waterside economizer carry roughly half the year. Liquid cooling carries far denser racks, cuts the fan power that air cooling spends moving room air, and accepts water warm enough that compressors run only on the hottest afternoons.

Most Ohio halls end up hybrid. Cold plates take most of the heat from GPUs and CPUs, while room air handlers still remove the heat from memory, drives, power supplies and the room itself. The air side can then run warmer and smaller. Paul Industries sizes both sides together so the air system is neither stranded nor short when the liquid-cooled rows arrive. Room-side cooling plants are covered on the data center cooling in Ohio page.

How does data center liquid cooling work at the rack?

Data center liquid cooling works at the rack by pumping coolant through a liquid cooling cold plate clamped to each processor, where heat passes through a thin metal base into the fluid, which then returns through rack manifolds to a CDU. The CDU holds a heat exchanger, pumps, filters and controls. It keeps the technology cooling loop, the loop that touches the servers, separate from the facility water loop, so each side can carry its own chemistry, pressure and temperature.

Data center liquid cooling options for Ohio halls and the Ohio-specific design notes for each
ApproachWhere it fitsOhio design notes
Single-phase direct-to-chip with CDUsGPU and CPU racks from moderate to very high densityWarm facility water suits dry coolers for most Ohio hours; glycol on the outdoor side for subzero nights
Rear-door heat exchangersExisting air-cooled racks needing more capacityWater must stay above the room dew point, which runs high in Ohio summers
Liquid-to-air CDUs in the rowPilot rows where no facility water reaches the hallHeat still lands on the room air plant; useful as a bridge during phased Ohio retrofits
Single-phase immersionPurpose-built rooms and edge sitesFloor loading and fluid handling decide the room; heat rejection mirrors direct-to-chip
Two-phase direct-to-chipVery high heat flux processorsRefrigerant-type fluids bring the refrigeration chapter of the Ohio Mechanical Code into the review

Immersion tanks are described further on the data center immersion cooling page. Whatever the approach, Paul Industries treats the data center liquid cooling design as one hydraulic system, from cold plate pressure drop through manifold balancing to facility pump selection.

Data center liquid cooling design decisions to settle before racks are ordered

Data center liquid cooling design for an Ohio hall goes smoothly when five decisions are settled before the IT order is placed: the facility water class, the CDU arrangement, the flow and temperature rise per rack, the redundancy level, and the controls that tie it all to the building system. Each decision fixes pipe sizes, pump selections and plant capacity, so changing one after equipment is bought costs time and money.

Flow follows directly from heat and temperature rise. Water carrying heat with a 10 C rise needs about 1.43 liters per minute for every kilowatt, so a 100 kW rack needs roughly 143 liters per minute, close to 38 gallons per minute, through its manifold. A smaller temperature rise means more flow, larger pipes and more pump power; a larger rise means warmer return water, which suits dry coolers and heat recovery in Ohio’s climate. Paul Industries sets the rise with the IT vendor’s cold plate data, then sizes manifolds, CDUs and facility headers to match.

Controls and alarms that tie CDUs to the building system

CDU controls in an Ohio hall hold the supply temperature to the racks, keep secondary pressure inside the cold plate rating, and stage pumps for redundancy. They also need clean links to the building management system so operators see flow, temperatures, pressures, coolant conductivity and leak alarms on one screen. Paul Industries maps every point, writes the alarm priorities with the operations team, and proves pump failover, power loss ride-through and valve closure on leak detection during startup. The facility side gets the same attention: dry cooler fan staging, trim chiller enable points and glycol loop freeze alarms all follow written sequences tested before the first production rack connects.

Freeze protection and coolant through an Ohio winter

Freeze protection for Ohio liquid cooling loops starts with the outdoor side, because the airports nearest many Ohio sites recorded lows of minus 10 F in Toledo and at Akron-Canton, and minus 7 F in Columbus, over the five winters studied. The facility loop serving outdoor coils usually carries propylene glycol at a strength chosen for a margin below the station record, or the outdoor coils sit on a separate glycol loop behind a plate exchanger so the indoor loop can stay on water.

The technology cooling loop inside the hall never sees outdoor air, but its coolant still matters. Many cold plate vendors call for a premixed inhibited propylene glycol or a treated water formula with set limits on conductivity, particles and biological growth. Paul Industries fills, samples and documents each loop to the vendor’s specification and adds the coolant checks to the service plan through glycol cooling systems maintenance.

Fill water from Ohio city supplies

Fill water for an Ohio technology cooling loop should not come straight from the tap, because municipal water carries hardness, chlorine and dissolved solids that foul fine cold plate channels and attack metals over time. Columbus, for example, softens its water to about 120 ppm of hardness and carried total chlorine near 1.4 ppm leaving its two surface water plants in 2025, which suits drinking water and does not suit a microchannel heat exchanger.

Paul Industries fills secondary loops with deionized water and the specified inhibitor, or with the vendor’s premixed coolant, and fits side-stream filtration and conductivity monitoring at the CDU. Facility water loops serving dry coolers or towers get a treatment program matched to the city supply at that address, whether that is Columbus, Cincinnati’s Ohio River and aquifer sources or a Lake Erie utility. Water quality equipment for those loops ties into the closed-loop cooling systems work Paul Industries already provides.

CDUs, manifolds and pressure tests under the Ohio Mechanical Code

CDUs, manifolds and the piping between them fall under the Ohio Mechanical Code, which adopts the 2021 International Mechanical Code for hydronic piping in Chapter 12 and, since October 15, 2025, the 2024 edition of Chapter 11 for refrigeration. The hydronic test in that chapter calls for a hydrostatic test at one and a half times the maximum system design pressure and at least 100 psi, a figure that every manifold, hose and quick connect in the loop has to be rated for or isolated from during the test.

Paul Industries prefabricates headers and rack manifolds off site in stainless steel or another material matched to the coolant, cleans and caps them, and pressure tests them before they reach the hall. In the field, each loop is filled, vented, flushed through temporary strainers, tested and then connected to the racks in stages. The piping standards behind that work, ASME B31.9 for building services and ASME B31.3 where a loop is treated as process piping, are the same ones Paul Industries applies on process piping in Ohio. Functional testing and integrated tests with the IT load are covered on data center commissioning in Ohio.

Adding liquid cooling to an operating Ohio hall

Adding liquid cooling to an operating Ohio hall works best when the facility water connection, the CDU locations and the routing are settled before the first liquid-cooled rack is ordered. Many Ohio halls built in the last decade have chilled water plants that can spare capacity in winter and shoulder months, and warm-water loops can draw from the chilled water return rather than the supply, which raises the temperature the CDUs see and protects the existing plant.

The sequence Paul Industries follows in a live hall is survey, design, prefabrication, tie-in and phased startup. Tie-ins to existing headers use hot taps or planned valve isolations under a written method of procedure. Overhead routes avoid working above energized equipment where possible, and every joint above IT gear gets leak detection beneath it. Each row is filled, tested and proven on load banks before production servers connect. Timing helps in Ohio. Tie-ins to a chilled water plant are easiest from late autumn through early spring, when the waterside economizer carries much of the load and the chillers have spare capacity for the new rows. Dry coolers and roof work go up best from April through October, before freezing weather slows outdoor piping tests and glycol fills. Paul Industries plans the work in that order where the schedule allows: outdoor equipment and facility headers in the warm months, indoor tie-ins and row connections through the cold ones.

Records close each phase. Every row leaves with its pressure test sheet, flushing and fill records, coolant analysis, valve tag list and the alarm test results, so the operator can trace any later question back to the day the loop was built. Campus-level piping and new central plants for liquid-cooled buildings are described on the data center mechanical contractor in Ohio page.

Are data centers liquid cooled in Ohio today?

Data centers in Ohio are liquid cooled today in research computing, in GPU clusters inside enterprise and colocation halls, and in newly designed buildings sized for dense accelerator racks. The OSC Cardinal cluster in Columbus is a public example of direct-to-chip cooling on GPUs. Many other Ohio rooms run rear-door coils or a few liquid-cooled rows inside an air-cooled hall, which is often the first step for an owner testing the approach.

Data center liquid cooling systems arrive in Ohio halls through two routes: the IT vendor ships racks with cold plates and manifolds, and the facility provides CDUs and water; or the facility buys the full chain, including the data center liquid cooling equipment at the rack, as one package. Paul Industries works either way, supplying and installing the facility side and coordinating rack-level connections with the IT schedule.

Data center liquid cooling cost in Ohio: capital and power

Data center liquid cooling cost in Ohio depends on rack count and density, whether the hall already has facility water, the CDU arrangement and redundancy, the heat rejection plant and the amount of work done inside a live room. Capital cost per rack falls as density rises, because the facility water, CDUs and heat rejection serve more kilowatts per connection.

Operating cost is where Ohio numbers help. The average Ohio industrial electricity price for January through August 2026 was 10.23 cents per kWh, up from 8.10 cents in the same months of 2025, according to the EIA. At 10.23 cents, removing 1 MW of continuous cooling power saves about $896,148 a year, before demand charges. On an AEP Ohio contract with an 85 percent minimum, that same megawatt can instead serve IT load.

What drives data center liquid cooling cost on an Ohio project
Cost driverLower cost caseHigher cost case
Facility waterExisting chilled water return with spare capacityNew warm-water plant with dry coolers and trim chiller
CDU arrangementRow CDUs shared across racks, N+1Dedicated CDUs per row with 2N pumping
Hall conditionEmpty shell or new buildingOperating hall with tie-ins under a method of procedure
Outdoor equipmentRoof or yard space near the hall, short glycol runsLong runs with heat tracing for Ohio winters
Coolant and water qualityVendor premix with simple side-stream filtersCustom chemistry with continuous monitoring and polishing

Paul Industries offers design-build, complete installation to an owner’s engineered drawings, and supply of prefabricated manifolds, headers and pump skids. A firm price follows a survey and the IT vendor’s cooling specification.

Who designs, pipes and installs data center liquid cooling in Ohio?

Paul Industries installs data center liquid cooling in Ohio, carrying projects from load study and design through prefabrication, installation, flushing, testing, startup and service. Projects range from a few GPU racks in an enterprise room in Dayton to multi-megawatt rows in Central Ohio campuses, and Paul Industries takes them on in new buildings and in halls that stay live throughout. The same work is offered across the Midwest and in neighboring markets, including data center liquid cooling in New York and, in the headquarters state, data center liquid cooling in Virginia.

Ohio rack cooling loops built by Paul Industries

Paul Industries builds the whole liquid path for Ohio racks: facility water headers, dry coolers and trim chillers, CDUs, manifolds, coolant fill and the controls and alarms that tie them to the building system. Every loop leaves with test records, coolant data and a sequence the operators have run themselves. For a hall in Columbus, Cincinnati, Cleveland, Toledo or elsewhere in the state, visit the Ohio page or request a quote.

Standards referenced: ASHRAE Thermal Guidelines for Data Processing Environments (liquid cooling classes W17 to W+) · Ohio Mechanical Code (2021 International Mechanical Code, Chapter 12 hydronic piping) · ASME B31.9 · ASME B31.3 · AEP Ohio Schedule DCT

Frequently asked questions

Who installs liquid cooling for GPU racks in Columbus and New Albany halls?

Paul Industries installs liquid cooling for GPU racks in Columbus, New Albany, Dublin and Hilliard halls, from CDUs and manifolds to facility water and dry coolers. Central Ohio weather lets dry coolers hold W32 water for about 91 percent of hours, so most designs need only a trim stage for summer afternoons. Paul Industries builds the loops, tests them and connects racks in stages.

Which Southwest Ohio sites, from Cincinnati to Dayton, suit dry coolers for liquid loops?

Paul Industries pipes liquid cooling in Cincinnati, Dayton, Mason and across Southwest Ohio. Cincinnati’s Lunken airport logged about 870 hours a year above the dry bulb limit for W32 water with dry coolers alone, the most of the stations studied, so trim cooling there is sized with extra care. Paul Industries designs the split between dry coolers and chillers from that station record.

Can Paul Industries add liquid-cooled rows to a hall in Cleveland, Akron or Toledo?

Paul Industries adds liquid-cooled rows to operating halls in Cleveland, Akron, Canton and Toledo, tying into existing chilled water or building a new warm-water loop. Northeast Ohio’s cooler summers favor dry coolers, with Cleveland near 94 percent of hours inside the W32 dry cooler limit, while winter lows down to minus 10 F call for glycol on the outdoor side.

Does the AEP Ohio data center tariff apply to a 10 MW hall?

The AEP Ohio data center tariff, Schedule DCT, sets its full process for new data centers or expansions of 25,000 kW or more, which also pay a load study fee. AEP Ohio contacts smaller requesters directly. Paul Industries reviews which tariff applies before sizing cooling, because minimum demand rules change the value of every kilowatt the cooling plant uses.

How does the 85 percent minimum bill affect a liquid cooling decision?

The 85 percent minimum bill means a site on Schedule DCT pays for most of its contracted capacity whether that power runs servers or cooling equipment. Liquid cooling lowers fan and compressor power, so more of the contracted megawatts go to IT. Paul Industries calculates the cooling power of each option against the contract capacity to show the owner how much computing each design leaves room for.

What water temperature do liquid-cooled racks need in Ohio?

Liquid-cooled racks in Ohio usually take facility water in the ASHRAE W27 to W40 range, from 80.6 F to 104 F at the upper limit, depending on what the IT vendor qualifies. W32 is a common target because dry coolers in Ohio can hold it for about 90 to 95 percent of hours. Paul Industries confirms the class with the IT vendor before fixing the plant design.

Can an Ohio liquid cooling loop run without any chiller?

An Ohio liquid cooling loop can run without a chiller when the IT accepts W40 water, because station data from 2021 to 2025 show only a handful of hours a year when dry coolers with a 10 F approach could not hold 104 F supply. Most owners still add an adiabatic stage or a connection to an existing chilled water plant for redundancy. Paul Industries designs either path.

What glycol strength suits outdoor dry coolers in Ohio?

Outdoor dry coolers in Ohio need a propylene glycol strength chosen with a margin below the station’s record low, which reached minus 10 F at Toledo and Akron-Canton between 2021 and 2025. Higher glycol strength lowers heat transfer and raises pump power, so some designs keep glycol on a separate outdoor loop behind a plate exchanger. Paul Industries sizes and tests the mix at startup.

Can Columbus tap water be used to fill a CDU secondary loop?

Columbus tap water should not be used to fill a CDU secondary loop. The city softens to about 120 ppm of hardness and carries chlorine for disinfection, both fine for drinking and harmful in microchannel cold plates. Paul Industries fills secondary loops with deionized water and inhibitor or the vendor’s premixed coolant, then logs conductivity and particle counts at turnover.

What pressure test does an Ohio liquid cooling loop need?

Hydronic piping in an Ohio liquid cooling loop is tested under the Ohio Mechanical Code, which adopts the 2021 International Mechanical Code hydronic chapter calling for one and a half times the maximum design pressure and at least 100 psi. Components rated lower, such as some hoses and quick disconnects, are isolated during the test and checked to their own ratings. Paul Industries records each test for the owner.

Is the Ohio Supercomputer Center's cooling a model for a commercial hall?

The Ohio Supercomputer Center’s Cardinal cluster shows that warm-water direct-to-chip cooling works on GPUs in a Columbus building and earned a Green500 ranking for efficiency. A commercial hall can follow the same principle, CDUs feeding cold plates from a warm facility loop, while sizing redundancy and controls to its own service levels. Paul Industries builds that approach for colocation and enterprise owners across Ohio.

How long does it take to add liquid cooling to a live Ohio data hall?

Adding liquid cooling to a live Ohio data hall usually takes several months from survey to the first connected row, with long-lead CDUs and dry coolers often setting the pace. Prefabricating manifolds and headers off site shortens the time spent working in the room. Paul Industries phases tie-ins around the hall’s change windows and brings rows online one at a time.

What leak protection goes into an Ohio liquid-cooled row?

An Ohio liquid-cooled row usually gets drip trays or sensing cable under manifolds and overhead joints, leak detection inside CDUs, isolation valves at each rack, and alarms routed to the building management system with automatic valve closure where the owner chooses. Paul Industries installs and tests each sensor, then proves the alarm and shutoff sequences before production servers connect.

Can heat from Ohio liquid cooling loops be reused?

Heat from Ohio liquid cooling loops leaves at temperatures warm enough to preheat ventilation air, domestic water or adjacent building heating loops through a plate exchanger or heat pump, especially in Ohio’s long heating season. The value depends on having a steady heat user close by. Paul Industries evaluates the load match and designs the connection when an owner wants to recover that heat.

Does liquid cooling change the refrigerant rules for an Ohio data center?

Single-phase liquid cooling with water or glycol adds no refrigerant to the hall, so the refrigeration chapter of the Ohio Mechanical Code applies to the chillers behind it rather than to the racks. Two-phase systems use refrigerant-type fluids, which bring that chapter, now based on the 2024 International Mechanical Code, into the review. Paul Industries checks those requirements during design.

Which details does Paul Industries need to price an Ohio liquid cooling retrofit?

An Ohio owner should send the rack count and power per rack, the IT vendor’s cooling specification and water class, the hall layout, details of existing chilled water, the site address and utility, and the change windows available. Paul Industries returns a defined scope, a budget range and the cooling power of each option measured against the site’s power contract.

Bringing dense racks into an Ohio hall?

Send the rack count, power per rack, IT cooling specification, hall layout and utility for the site. Call 201-450-8280 or request a quote.