Paul Industries provides validation and commissioning in Texas, commissioning and qualifying process equipment, utilities, clean spaces and automated systems for active ingredient, biologics, medical device and semiconductor plants, from installation qualification through performance qualification and requalification. Texas is in the middle of its largest pharmaceutical build-out, centered on two new campuses at Generation Park in Houston, while biologics, device and semiconductor plants elsewhere in the state keep adding systems that need commissioning and qualification. Paul Industries, headquartered at 256 Shore Drive in Kilmarnock, Virginia, delivers commissioning, qualification and validation as part of the same contract that designs, builds and starts up the systems.

Request a quote or call 201-450-8280

Headquarters 256 Shore Drive, Kilmarnock, Virginia
Generation Park, Houston Lilly $6.5 billion active ingredient site, groundbreaking 2026
Also at Generation Park Bristol Myers Squibb campus, about $2.3 billion
State licensing DSHS drug and device manufacturer licenses (Health and Safety Code Ch. 431)
Boiler status in an IQ TDLR certificate for registered boilers; autoclave vessels exempt since 2025
Reviewed November 2026

Validation and commissioning in Texas during the Houston drug plant build-out

Validation and commissioning in Texas is being reshaped by two greenfield campuses in Harris County: Lilly’s $6.5 billion active pharmaceutical ingredient site at Generation Park, where ground was broken in 2026, and Bristol Myers Squibb’s roughly $2.3 billion campus at the same park, announced in August 2026. Projects of that size run commissioning and qualification across dozens of process systems, utilities and buildings at once, and they draw on the same pool of engineers, technicians and documentation that every other Texas site relies on.

Two features make the Texas work different from the device-heavy and plasma-heavy programs elsewhere in the Southeast. First, much of the new Texas capacity is active ingredient manufacturing, which follows ICH Q7 rather than the finished-dosage rules alone, with chemical reactors, solvent systems and multipurpose equipment that need cleaning validation between products. Second, the state’s large semiconductor and advanced manufacturing base means commissioning teams in North and Central Texas spend as much time on ultrapure water, bulk gases and process cooling for fabs as on GMP systems. Paul Industries plans programs for both.

Pharmaceutical companies in Texas building plants now

Pharmaceutical companies in Texas with manufacturing under construction are concentrated around Houston, with biologics manufacturing in the Brazos Valley and device and diagnostics production in the major metros. The list below is a market picture drawn from public announcements, not a client list; the qualification work it implies is the same for any site of its type.

Pharmaceutical companies in Houston, Texas: Generation Park

Generation Park in northeast Houston now holds two of the biggest drug manufacturing commitments announced in Texas in recent years. Lilly’s site, about one million square feet, is planned to make next-generation small molecule medicines, including its oral GLP-1 medicine orforglipron, along with oligonucleotides, and to employ more than 600 people. Bristol Myers Squibb’s modular campus of about 600,000 square feet is designed for small molecules, biologics and antibody-drug conjugates, covering drug product and finished goods from late-stage development through commercial launch. For pharmaceutical companies in Houston, those two projects set the scale of qualification work in the region for the rest of the decade.

Biotech companies in Texas: College Station and the Texas Medical Center

Biotech companies in Texas manufacture biologics in College Station, where FUJIFILM operates a single-use biomanufacturing campus next to Texas A&M’s National Center for Therapeutics Manufacturing, and Houston’s Texas Medical Center anchors research, clinical and early manufacturing activity. Single-use biologics plants qualify bioreactors, mixers, chromatography and filtration skids, cold chain and controlled environments, with supplier documentation for single-use assemblies taking the place of some cleaning work.

Device and diagnostics manufacturing spread across Dallas-Fort Worth, Austin, San Antonio and Houston adds equipment and process validation under FDA’s Quality Management System Regulation, which aligns 21 CFR Part 820 with ISO 13485. Paul Industries offers pharmaceutical validation services and device equipment qualification on the same documentation standards. More on the sector is on the pharmaceutical industry page.

Qualifying an active ingredient plant under ICH Q7

An active ingredient plant is qualified under ICH Q7, the GMP guide for active pharmaceutical ingredients that FDA publishes as guidance, which expects design qualification, installation qualification, operational qualification and performance qualification of critical equipment and utilities, validation of cleaning procedures, and process validation before commercial distribution. The equipment differs from a finished-dosage plant: glass-lined and alloy reactors, filter dryers, centrifuges, crystallizers, solvent distillation and recovery, nitrogen inerting and vapor handling.

Multipurpose equipment drives the cleaning work. Where one train makes several intermediates or ingredients, cleaning validation sets residue limits from toxicology, proves the cleaning procedure removes product and solvent to those limits with validated analytical methods, and defines hold times for dirty and clean equipment. Paul Industries designs equipment and piping for cleanability, with drainable lines, spray coverage and sample points, so the cleaning studies confirm a design that was built to pass them.

Qualification focus by system in a Texas active ingredient plant
SystemQualification focusEvidence the owner keeps
Reactors and crystallizersTemperature control range and uniformity, agitation, pressure and vacuum integrity, charging accuracyCalibration records, OQ test results, jacket temperature mapping
Filter dryers and centrifugesInerting, vacuum, heating, discharge, containment for potent compoundsOxygen and pressure data, containment test results
Solvent recovery and distributionPurity of recovered solvent, segregation, inerting and vapor controlSpecifications, sampling plans, P&ID walkdowns
Purified water and clean steamChemistry and microbial quality over seasonal variation; steam qualityPhase sampling data, conductivity and TOC trends
HVAC and controlled areasPressure cascades, air change rates, particle and microbial classificationISO 14644 test reports, smoke studies
Automation and data systemsRecipe control, alarms, audit trails, electronic records and signaturesGAMP 5 risk assessments, test scripts, Part 11 assessments
Cleaning in placeSpray coverage, cycle parameters, residue removal to validated limitsRiboflavin coverage tests, cleaning validation reports

Which Texas requirements belong in the qualification file?

Texas requirements belong in the qualification file because an installation qualification confirms a system is installed as designed and fit to operate, and a state registration, license or permit is part of being fit to operate. Four Texas items come up most often.

Texas requirements an IQ or startup package should reference
Texas requirementSourceHow it enters qualification
Drug manufacturer and distributor licenseTexas Department of State Health Services, Health and Safety Code Chapter 431 and 25 TAC Chapter 229Site license current for the operations being qualified; licenses run two years
Device manufacturer licenseHealth and Safety Code Section 431.272, one license per place of businessConfirmed for device sites before process validation
Boiler certificate of operationTDLR under Health and Safety Code Chapter 755Current certificate for plant boilers and registered unfired steam boilers serving GMP utilities
Autoclave pressure vessels and device boilersSenate Bill 1185, effective September 1, 2025Recorded as exempt from state boiler registration within the stated limits
Air authorization for solvent and combustion sourcesTCEQ permits by rule, standard permits or Chapter 116 permitsAuthorization in place before startup; changes routed through change control
Boiler operator permit inside HoustonCity of Houston, by boiler sizeOperating staff permits recorded for the utility plant

Clean steam generators raise a classification question worth settling early. Texas registers unfired steam boilers, meaning unfired pressure vessels that generate steam, but excludes evaporators and heat exchangers from that definition, so the unit’s design and the inspection agency’s view decide whether it needs a Texas boiler certificate. Paul Industries confirms that status with the owner before the IQ is written, so the protocol cites the right record. Related equipment is covered on boiler repair in Texas and pressure vessel fabrication in Texas.

Commissioning and qualification on a Texas greenfield

Commissioning and qualification on a Texas greenfield work best when commissioning is planned as the first half of qualification, following the science and risk-based approach in ASTM E2500 and the ISPE Baseline Guide for commissioning and qualification. Systems are assessed for their impact on product quality, critical aspects are identified, and commissioning tests that verify those aspects are executed with good engineering practice and quality oversight, so qualification can rely on them instead of repeating them.

The sequence on a large site runs from user requirements and design review through factory acceptance tests at vendors, site acceptance tests, mechanical completion and turnover packages, commissioning, then qualification and finally process and cleaning validation. Each handoff has a record: the turnover package with material certificates, weld logs, pressure tests and as-builts; the commissioning report; and the qualification summary. Paul Industries builds systems with turnover packages arranged to the owner’s qualification plan, so commissioning starts from complete documents and qualification starts from executed commissioning.

How are water, clean steam, HVAC and clean spaces qualified?

Water, clean steam, HVAC and clean spaces are qualified before the process equipment they serve, because a product system cannot be qualified on unqualified utilities. Purified water and water for injection loops are qualified through a phased sampling program that ends with a full year of data, which in Texas captures summer feedwater temperatures and the seasonal changes in municipal supply chemistry. Clean steam is tested for non-condensable gases, superheat, dryness and condensate quality at the points of use.

Controlled areas are tested to ISO 14644 for airborne particles, with airflow, pressure cascade, recovery and filter integrity tests, then monitored for viable organisms during performance qualification. Humid Gulf Coast air makes dehumidification capacity part of the HVAC qualification, since a suite that holds its temperature but drifts in humidity fails its specification on a summer afternoon. These systems are built and qualified by Paul Industries and covered on high-purity water systems in Texas, cleanrooms in Texas and CIP and SIP systems in Texas.

Computerized systems and data integrity

Computerized systems at Texas plants are validated with a risk-based approach following GAMP 5, now in its second edition, and evaluated against 21 CFR Part 11 where they create or manage electronic records and signatures. Process control systems, building management systems that monitor GMP areas, data historians, laboratory systems and manufacturing execution systems each get a category, a risk assessment and testing scaled to their impact.

Data integrity is tested rather than assumed: audit trails capture who changed what and when, user roles prevent self-approval, time synchronization holds across systems, backups restore, and alarms reach the people who must act. Paul Industries tests these functions during commissioning and qualification and documents them in traceability matrices that link each requirement to its test.

Semiconductor and advanced manufacturing commissioning

Semiconductor and advanced manufacturing commissioning in North and Central Texas focuses on the utility systems that feed the fab: ultrapure water, process cooling water, bulk and specialty gases, chemical distribution, exhaust and abatement, and the electrical and controls behind them. Sherman’s first Texas Instruments 300 mm fab entered production in December 2025, with construction of the second finished, and fab construction around Austin and Taylor keeps commissioning demand high.

Fab commissioning is not a GMP program, but it borrows the same discipline: system boundaries, test scripts, punch lists, integrated systems tests and a documented handover to operations. Paul Industries commissions fab utilities with that structure, and the systems are described on ultrapure water systems in Texas. Data center commissioning, which shares the integrated testing approach, is on data center commissioning in Texas.

Process validation after the equipment is qualified

Process validation follows equipment and utility qualification and is organized in three stages under FDA’s process validation guidance: process design, where development and scale-up data define the control strategy; process performance qualification, where the commercial process is run on qualified equipment under a protocol to show it performs as expected; and continued process verification, where routine data confirm the process stays in control. ICH Q7 sets the corresponding expectations for active ingredients, with validation concentrated on the steps that determine impurity profile and quality.

The engineering contribution to process validation is to make the qualified state hold. Instruments that measure critical process parameters are calibrated and ranged to the control strategy, alarms and interlocks match the validated limits, and sampling points exist where the protocol needs them. Paul Industries builds and qualifies equipment with those requirements in the design, so process performance qualification runs on a plant that measures what the protocol asks it to measure.

Qualifying systems already installed

Qualifying systems already installed at a Texas plant, sometimes called retrospective or legacy qualification, starts with a gap assessment: what records exist, what the system actually looks like, and what evidence is missing compared with the plant’s current standard. Walkdowns rebuild P&IDs and equipment lists, instruments are checked and calibrated, materials of construction are confirmed by records or testing, and missing installation evidence is replaced with verification tests that can still be performed.

Operational and performance testing then proceeds as for a new system, with the risk assessment deciding the depth. Paul Industries qualifies systems it did not build as readily as those it did, and where the gap assessment finds a design problem, such as a dead leg on a water loop or an undrainable line, it offers the modification and the requalification together.

Temperature mapping in Texas warehouses, cold rooms and incubators

Temperature mapping in Texas warehouses, cold rooms, freezers, incubators and stability chambers shows whether a controlled space holds its range everywhere product sits, and the Texas climate makes the summer study the one that matters for most ambient warehouses. A large distribution space with dock doors on the west side and a metal roof can hold its setpoint at the thermostat while racks near the roof and doors drift well above it on an August afternoon.

A mapping study places calibrated data loggers in a grid through the space, including high and low racks, corners, doors and near heating and cooling sources, and records for long enough to capture daily and operational cycles, with door openings and defrost cycles included. Summer and winter studies are run for ambient spaces, and power-failure and door-open tests show how long a cold room or freezer holds after a loss of control. The results set where monitoring probes go and where product may and may not be stored.

Deviations, test failures and closing a protocol

Deviations during qualification are expected on a large program, and the way they are handled decides whether release dates hold. Each failed acceptance criterion or departure from the protocol is recorded at the time, assessed for impact on the system and the test, investigated to a root cause, corrected and retested where needed, and closed with quality approval before the summary report is signed.

Most deviations on Texas greenfields come from three places: documents that do not match the installed system, instruments out of calibration or ranged incorrectly, and software configurations changed after testing began. Walkdowns before execution, calibration checks at the start of OQ and configuration control from the first day of commissioning remove most of them. Paul Industries manages deviations inside its own execution so the owner’s quality group reviews closed records rather than open problems.

Typical sequence and records on a Texas CQV program
PhaseMain activitiesRecord produced
PlanningSystem boundaries, impact assessments, critical aspects, validation master planApproved plan and system list
Design reviewUser requirements traced to design, design qualification where requiredTraceability matrix and DQ report
Vendor testingFactory acceptance tests on skids and packaged equipmentFAT reports with deviations closed
Construction turnoverMechanical completion, punch lists, turnover packagesTurnover package per system
CommissioningStart-up, functional tests, integrated systems testsCommissioning report the IQ and OQ can cite
QualificationIQ, OQ and PQ for direct-impact systems; utility sampling phasesExecuted protocols and summary reports
ValidationCleaning validation, process validation, computerized system validationValidation reports and release for GMP use

Change control and requalification at operating Texas plants

Change control at an operating Texas plant decides whether a modification needs testing, partial requalification or a full program, and the answer comes from the change’s impact on the qualified state rather than its size. Replacing a pump with an identical model may need only installation checks; adding a branch to a water loop needs installation records, sanitization and a period of sampling; moving a process to a new reactor needs equipment qualification and process and cleaning validation.

Texas plants also face events that test the qualified state: utility outages, extreme cold such as the February 2021 storm, hurricane season on the coast and summer peaks in cooling demand. A requalification plan that states in advance which checks follow which kind of event shortens the restart. Paul Industries writes and executes change assessments and requalification protocols for systems it built and for systems already installed.

What does validation and commissioning in Texas cost?

The cost of validation and commissioning in Texas depends on the number and complexity of systems, their GMP impact, how much commissioning can be leveraged, the state of the design and turnover documents, the extent of computerized system validation and the duration of utility sampling, so a program is priced from a system list and a validation master plan rather than a percentage of construction cost. Programs that start from complete turnover packages and a commissioning plan aligned with ASTM E2500 cost less than programs that reconstruct missing records after the fact.

Paul Industries gives a budget range once the system list and project schedule are known, then a firm price for protocols, execution and reports when the scope is fixed, whether as a stand-alone qualification package, as part of a design-build system or bundled with complete installation.

Who qualifies process systems and utilities in Texas?

Paul Industries qualifies process systems and utilities in Texas, writing and executing commissioning plans, IQ, OQ and PQ protocols, cleaning and computerized system validation, temperature mapping and requalification for active ingredient, biologics, device and semiconductor plants. Because Paul Industries also designs, fabricates and installs the systems, the turnover records, commissioning results and qualification evidence come from one source under one schedule.

The national validation and commissioning page sets out IQ, OQ and PQ definitions, protocol content and handover requirements in more depth.

Commissioning and qualification from Paul Industries across Texas

Paul Industries qualifies systems for plants in Texas, the other 49 states and abroad from its Kilmarnock, Virginia headquarters at 256 Shore Drive; the company was formerly based in northern New Jersey, then Pennsylvania, and works as an East Coast contractor nationwide. Its headquarters-state page is validation and commissioning in Virginia, and validation and commissioning in Georgia shows a Southeast program. Everything else Paul Industries builds in the state is on Texas.

For validation and commissioning in Texas, Paul Industries plans the program, writes and executes protocols, tests computerized systems, closes deviations and delivers the summary reports that release systems for GMP use. To start, send the system list, the validation master plan or project schedule and the required release dates, and request a quote.

Standards referenced: 21 CFR Parts 210 and 211 · 21 CFR Part 11 · 21 CFR Part 820 (QMSR) · ICH Q7 · ICH Q9 and Q10 · EU GMP Annex 15 · ASTM E2500 · ISPE Baseline Guide Volume 5 (Commissioning and Qualification) · GAMP 5 Second Edition · ASME BPE · ISO 14644 · USP <1231> · Texas Health and Safety Code Chapter 431 · Texas Health and Safety Code Chapter 755

Frequently asked questions

Who provides commissioning and qualification for active ingredient plants around Houston?

Paul Industries provides commissioning and qualification for active ingredient and finished-dosage plants in the Houston area, including reactors, filter dryers, solvent systems, water and clean steam, HVAC and automation. Programs follow ICH Q7 and ASTM E2500, with commissioning tests planned so qualification can rely on them and cleaning validation designed for multipurpose equipment.

Does Paul Industries qualify biologics systems in College Station and Bryan?

Yes. Paul Industries qualifies bioreactors, media and buffer preparation, chromatography and filtration skids, cold storage, water systems and controlled environments for biologics plants in College Station, Bryan and the Brazos Valley. Single-use assemblies are qualified with supplier documentation, integrity testing and installation checks in place of some cleaning work.

Who handles commissioning for semiconductor sites in Sherman, Austin and Taylor?

Paul Industries commissions fab utility systems in Sherman, Austin and Taylor, including ultrapure water, process cooling, bulk gas and chemical distribution and exhaust, with test scripts, integrated systems testing and documented handover to operations. The work uses the same structure as GMP programs without the regulatory release step.

Does Paul Industries take validation work in Dallas-Fort Worth and San Antonio?

Yes. Paul Industries qualifies equipment, utilities and clean spaces for device, diagnostics, pharmaceutical and food plants in Dallas, Fort Worth, Denton, San Antonio and New Braunfels. Device programs follow the Quality Management System Regulation, and drug programs follow 21 CFR 211 and the owner’s validation master plan.

What pharmaceutical companies are in Texas with plants under construction?

Public announcements put two major Texas projects at Generation Park in Houston: Lilly’s $6.5 billion active ingredient site, which broke ground in 2026, and a Bristol Myers Squibb campus of about $2.3 billion that will make small molecules, biologics and ADCs. FUJIFILM runs a single-use biologics campus in College Station. These are market facts, and each project needs extensive qualification work.

Which Texas agency licenses drug and device manufacturers?

The Texas Department of State Health Services licenses drug manufacturers and distributors under Health and Safety Code Chapter 431 and 25 TAC Chapter 229, with licenses valid for two years. Device manufacturers and distributors need a DSHS license for each place of business under Section 431.272. The license sits alongside FDA registration and cGMP requirements.

How is cleaning validated in a multipurpose active ingredient plant?

Residue limits are set from toxicology for each product changeover, worst-case products and equipment are selected, the cleaning procedure is executed and sampled by swab and rinse with validated analytical methods, and dirty and clean hold times are established. Equipment designed for drainability and spray coverage makes the studies pass on the first runs.

Does a clean steam generator need a Texas boiler certificate?

It depends on how the unit is classed. Texas registers unfired steam boilers, which are unfired pressure vessels that generate steam, but excludes evaporators and heat exchangers from that definition. The generator’s design and the inspection agency’s review settle the classification, and Paul Industries confirms it before the IQ cites the record.

Are autoclaves registered with TDLR after the 2025 law change?

Senate Bill 1185 took autoclave pressure vessels out of the Texas boiler law on September 1, 2025, along with small boilers that are part of an FDA-regulated medical device within set size limits. Larger plant steam supplies to autoclaves stay in the program. The IQ records which applies to each unit.

How does ICH Q7 change equipment qualification at an active ingredient plant?

ICH Q7 expects qualification of critical equipment and utilities through design, installation, operational and performance qualification, and pairs it with cleaning validation and process validation for the ingredient. Early synthesis steps carry lighter expectations than final steps, so the program concentrates testing where impurities and quality are set.

How does an ASTM E2500 approach reduce duplicate testing on a Texas greenfield?

The approach identifies critical aspects of each system, verifies them once during commissioning under good engineering practice with quality oversight, and lets qualification cite those results instead of repeating them. Turnover packages and commissioning records must be complete and reviewed for that to work, which is why Paul Industries organizes them to the qualification plan.

What does a turnover package need before a Texas IQ can start?

The package should include approved drawings and as-builts, equipment data sheets, material certificates, weld logs and inspection records for hygienic piping, pressure test and passivation records, instrument calibration certificates, vendor manuals and factory acceptance results. Missing records are the most frequent cause of IQ delays.

How are solvent recovery and vapor control systems qualified at an active ingredient plant?

Recovered solvent quality is specified and tested against its intended reuse, segregation between products and grades is verified, and inerting, condensers and vapor control equipment are tested for the conditions they must hold. Changes to these systems are also reviewed against the site’s TCEQ air authorization.

Does a new solvent emission source need a TCEQ authorization before startup?

Yes. Process vents, dryers, solvent storage and combustion equipment need an air authorization, through a permit by rule, a standard permit or a Chapter 116 permit, before they operate. In the Houston area, a severe ozone nonattainment region since November 2022, emission thresholds are low, so the permit basis is set during design.

How is a purified water loop qualified through a Texas summer?

The loop is qualified in phases, starting with intensive daily sampling at every point of use, then routine sampling under normal operation, and ending with a full year of data. Texas summers raise feedwater temperature and can change municipal supply chemistry, so the year-long phase confirms the system holds specification through those conditions.

What sets the price of a qualification program for a Texas plant?

Price follows the number of systems and their GMP impact, the state of turnover documents, how much commissioning can be leveraged, computerized system scope, cleaning validation and the length of utility sampling. Paul Industries prices from a system list with a budget range first and a firm price when the plan is fixed.

Which documents let Paul Industries scope a Texas qualification program?

Send the system list or P&IDs, the validation master plan or project execution plan, user requirement specifications, existing commissioning or qualification documents, the computerized systems list and the target release dates. Paul Industries returns a budget range and a proposed approach for each system.

Qualifying new or changed systems at a Texas plant?

Send the system list, the validation master plan or schedule and your release dates. Call 201-450-8280 or request a quote.